OR Landscape Contractor flashcards
OR Landscape Contractor · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Oregon Landscape Contractors Board
- The Oregon state agency that licenses landscape contracting businesses under ORS Chapter 671, adopts rules in OAR chapter 808, and investigates complaints against licensees.
- Limited landscape contracting license
- An Oregon LCB license that authorizes only specified specialty work, such as irrigation installation or landscape maintenance, instead of the full scope of landscape contracting.
- Landscape contracting under ORS 671
- Work performed for compensation that involves planning, installing, constructing, planting, or maintaining landscape and its appurtenances for another person, which requires an LCB license.
- Root flare
- The widened zone where trunk tissue transitions to root tissue; it must sit at or slightly above finished grade, because a buried flare girdles and kills the tree.
- Balled-and-burlapped stock
- Nursery trees and shrubs dug with a soil ball wrapped in burlap and secured with twine or a wire basket; remove at least the top half of the wrapping before backfilling.
- Right plant, right place
- Selecting species by matching site conditions such as hardiness zone, light, soil moisture and drainage, mature size, and maintenance budget to the plant's known requirements.
- Leaf arrangement
- The pattern of leaves along a stem, either alternate, opposite, or whorled, and one of the primary keys used with leaf type, margin, buds, and bark for identification.
- Precipitation rate formula
- Precipitation rate in inches per hour equals 96.25 times the zone flow in gallons per minute, divided by the irrigated area in square feet.
- Matched precipitation rate
- Design practice of keeping only heads with equal precipitation rates on the same zone, so every part of the area receives uniform water and none is over- or under-irrigated.
- Reduced pressure zone assembly
- A backflow preventer with a differential relief valve that discharges if pressure is lost, used on high-hazard connections such as irrigation with chemical injection, and tested annually.
- Cycle-and-soak irrigation
- A controller method that runs a zone in several short cycles separated by soak pauses so water infiltrates clay soil instead of running off the surface.
- Gross margin percentage
- Revenue minus direct job costs, divided by revenue; it measures what remains from each sales dollar to cover overhead and profit on a project.
- Labor burden
- The cost above base wage for payroll taxes, workers' compensation insurance, benefits, and paid leave, typically adding 25 to 40 percent to the hourly rate.
- Break-even revenue
- The sales volume at which total revenue equals total costs, calculated as annual fixed overhead divided by the company's gross margin percentage.
- Quantity takeoff
- Systematic measurement of every material and labor item from the plans, such as area, length, count, and volume, producing quantities to which unit costs are applied.
- Oregon construction lien deadline
- In Oregon, a construction lien must be recorded within 75 days after completion of the improvement in order to preserve the claimant's right to lien the property.
- Change order
- A written, signed amendment to the contract that defines a change in scope, price, or schedule; changed work should not proceed until the document is executed.
- Soil textural triangle
- A chart used to name soil texture from the percentages of sand, silt, and clay in a sample; loam falls near 40 percent sand, 40 percent silt, and 20 percent clay.
- Compaction and bulk density
- Compaction presses soil particles together, raising bulk density and lowering pore space and air, which restricts root growth and infiltration; it happens when wet soil is trafficked.
- French drain
- A subsurface drain of perforated pipe set in washed gravel and wrapped in filter fabric, laid at a minimum one percent fall to carry groundwater to an outlet.
- Paver base thickness
- Compacted aggregate base is typically 4 inches for pedestrian pavers and 6 to 8 inches for vehicle areas, topped with 1 inch of bedding sand.
- Retaining wall batter
- The deliberate backward lean of a segmental retaining wall, about 1 inch per foot of height, which improves stability by keeping the wall's weight over its base.
- Concrete control joint
- A sawed or tooled groove forming a weakened plane so concrete cracks there rather than randomly; typical spacing is 8 to 10 feet in a 4-inch slab.
- One-third mowing rule
- Remove no more than one-third of the grass blade height at any single mowing; cutting more shocks the plant, thins the stand, and invites weeds.
- Thatch layer
- The layer of dead stems, roots, and crowns between the soil surface and green grass; when it exceeds about one-half inch, core aerification or dethatching is needed.
- Deep and infrequent irrigation
- Watering turf heavily but rarely so moisture penetrates the full root zone, encouraging deeper roots and greater drought tolerance than light daily sprinkling.
- Economic threshold
- The pest population level at which the cost of control equals the damage the pest causes; integrated pest management treats only when monitoring shows it is reached.
- Restricted-entry interval
- The label-specified period after a pesticide application during which workers may not enter the treated area without required protective equipment; it appears on every agricultural label.
- Mode-of-action rotation
- Alternating pesticides from different IRAC, FRAC, or WSSA groups so a pest population is exposed to different chemistries and resistance is less likely to develop.
- Call 811 before digging
- Oregon's free utility locate service; a contractor must notify it at least two business days before excavation and wait for buried lines to be marked.
- Excavation protective system
- Sloping, benching, shoring, or a trench shield required for excavations 5 feet or deeper; soil type sets the maximum allowable slope, from 0.75:1 to 1.5:1.
- Hearing protection threshold
- Oregon OSHA requires hearing protection and a hearing conservation program when noise exposure reaches 85 decibels averaged over eight hours; use double protection above 100 dBA.