Introduction to OSHA

  • The Occupational Safety and Health Act was signed December 29, 1970, and took effect April 28, 1971; OSHA operates within the U.S. Department of Labor.

  • Construction is regulated under 29 CFR Part 1926, general industry under Part 1910, and agriculture under Part 1928.

  • Section 5(a)(1), the General Duty Clause, requires each employer to furnish a workplace free from recognized hazards likely to cause death or serious physical harm where no specific standard applies.

  • Employers must report a work-related fatality to OSHA within 8 hours and an in-patient hospitalization, amputation, or loss of an eye within 24 hours.

  • Inspection priority order: imminent danger, fatality or catastrophe, valid employee complaint, referral, then programmed inspection.

  • Employee rights include requesting an inspection, accompanying the compliance officer, reviewing injury records, and protection from retaliation under Section 11(c).

  • Establishments with more than 10 employees must keep the OSHA 300 log and record newly discovered recordable cases within 7 calendar days.

  • An OSHA-approved State Plan must be at least as effective as federal OSHA and must cover private-sector employees.

  • Citations must be posted at or near the place of the violation until abatement is verified or for 3 working days, whichever is longer.

Quick reference

Focus Four Hazards: Falls

  • 29 CFR 1926.501(b)(1): an employee on a walking/working surface with an unprotected side or edge 6 feet or more above a lower level must be protected by guardrail system, safety net system, or personal fall arrest system.

  • Fall protection trigger heights differ by activity: 6 feet for most construction, 10 feet for scaffolds, 15 feet for steel erection, and any height above dangerous equipment.

  • Guardrail systems use a top rail at 42 inches plus or minus 3 inches and a midrail at approximately 21 inches, withstanding 200 pounds on the top rail and 150 pounds on the midrail.

  • A personal fall arrest system consists of a full-body harness, connecting means, and anchorage rated at 5,000 pounds per employee or designed with a safety factor of at least 2.

  • Personal fall arrest systems must limit free fall to 6 feet, limit arresting force on the body to 1,800 pounds, and stop the employee within a deceleration distance of 3.5 feet.

  • Hole covers must be secured against displacement and support at least twice the weight of employees, equipment, and materials imposed on them.

  • Warning lines used during roofing work are erected at least 6 feet from the unprotected edge and use stanchions supporting at least 16 pounds.

  • Controlled access zones, safety monitoring systems, and designated areas are fall protection options permitted only in the specific situations listed in 1926.501.

  • Fall arrest equipment must be inspected before each use and removed from service after any impact loading or visible damage.

Quick reference

Focus Four Hazards: Struck-By

  • Struck-by hazards are grouped into flying objects, falling objects, swinging objects, and rolling objects.

  • Hard hats are required wherever employees are exposed to falling or flying objects or to electrical shock and burn hazards (1926.100).

  • Employees must never work or walk beneath a suspended load; tag lines control loads from outside the fall zone.

  • The swing radius of a crane superstructure or excavator house must be barricaded so employees cannot enter the pinch area.

  • Equipment operators must have an unobstructed view of travel paths; use spotters, horns, and backup alarms, and travel in reverse only when the area is confirmed clear.

  • Flaggers and employees exposed to vehicular traffic must wear high-visibility warning garments (1926.201).

  • Materials must be stacked, cross-tied, and secured so they cannot slide, collapse, or tip; hand tools used at height are secured with lanyards or tethers.

  • Where falling objects are a hazard above workers, protection such as toeboards, screens, debris nets, or canopies must be provided (1926.501(c)).

  • Employees must not position themselves between a piece of heavy equipment and a fixed object such as a wall or stockpile.

Quick reference

Focus Four Hazards: Caught-In or Caught-Between

  • Caught-in or caught-between injuries result from being crushed, pinched, squeezed, or amputated between parts of equipment, structures, or collapsing material.

  • Trench and excavation collapses are the leading cause of caught-in fatalities in construction work.

  • Machine guards must remain in place; 1926.300 requires guarding of belts, gears, pulleys, sprockets, chains, and points of operation.

  • 1926.417 requires that energy sources be locked out and tagged out during repair, maintenance, servicing, or adjustment.

  • Loose clothing, jewelry, and long hair must be secured whenever working near rotating or moving equipment.

  • Excavations 5 feet or deeper require a protective system, and spoil piles and equipment must be kept at least 2 feet from the edge.

  • Workers must de-energize and secure equipment before entering hoppers, bins, mixers, or other enclosed components.

  • Never straddle or reach into an operating attachment; shut down and block equipment before performing maintenance.

Quick reference

Focus Four Hazards: Electrocution

  • Overhead power lines are presumed energized until the utility confirms de-energization and visibly grounds the lines.

  • 1926.1408 sets minimum approach distances for equipment near power lines; for lines rated up to 50 kV the minimum is 10 feet, and the alternative planning option for cranes requires 20 feet for lines up to 350 kV.

  • Temporary 15- and 20-ampere receptacles on construction sites require GFCI protection or an assured equipment grounding conductor program (1926.404(b)(1)).

  • Portable and extension cords must have intact insulation, an unbroken grounding pin, no splices, and strain relief at connection points.

  • Lockout/tagout procedure: de-energize, lock, tag, and verify the absence of voltage with a tester before work; only a qualified person may perform this.

  • If equipment contacts an energized line, the operator stays inside the cab and warns others away; exit only if fire forces it, by jumping clear and shuffling away.

  • Electrical equipment must be approved, guarded, and free of recognized hazards, with live parts enclosed to prevent accidental contact.

  • Portable metal ladders must be kept at least 10 feet from energized power lines and other electrical sources.

  • Water and damp conditions increase shock severity; keep cords and tools out of standing water and use GFCI protection.

Quick reference

Personal Protective Equipment

  • 29 CFR 1926.95 requires employers to provide required PPE at no cost to employees, with exceptions for non-specialty safety-toe footwear and non-specialty prescription eyewear.

  • PPE selection follows a hazard assessment of the work area; defective or damaged equipment must not be used.

  • Hard hats are required where employees are exposed to head injury from falling or flying objects or from electrical shock or burns (1926.100).

  • Eye and face protection under 1926.102 includes safety glasses with side shields, goggles, and face shields, and must meet ANSI Z87.1.

  • Hearing protection is required at or above a 90 dBA 8-hour time-weighted average; a hearing conservation program is triggered above 85 dBA.

  • Respiratory protection requires a medical evaluation, annual fit testing, training, and a written program when respirators are required.

  • High-visibility garments are required for flaggers and employees exposed to vehicular traffic.

  • PPE training must address when protection is necessary, how to don, doff, and adjust it, its limitations, and its care and maintenance.

  • Personal fall arrest harnesses and lanyards must be inspected before each use.

Quick reference

Health Hazards in Construction

  • Crystalline silica under 1926.1153 has a permissible exposure limit of 50 micrograms per cubic meter as an 8-hour TWA and an action level of 25 micrograms per cubic meter.

  • Silica controls rely on engineering methods such as wet cutting, dust collection, and enclosed cabs before respirators are used.

  • Asbestos under 1926.1101 has a PEL of 0.1 fibers per cubic centimeter over 8 hours and requires regulated areas, exposure monitoring, and medical surveillance.

  • Lead under 1926.62 has a PEL of 50 micrograms per cubic meter over 8 hours, with blood lead monitoring and medical removal protection.

  • Noise under 1926.52 has a PEL of 90 dBA as an 8-hour TWA; exposure above 85 dBA requires a hearing conservation program.

  • Hazard Communication (1926.59) requires container labeling, safety data sheets, and employee training for every hazardous chemical on site.

  • Welding stainless steel can generate hexavalent chromium, which has a PEL of 5 micrograms per cubic meter under 1926.1126, and requires ventilation and respiratory protection.

  • Fuel-powered equipment in enclosed spaces produces carbon monoxide; the atmosphere must be tested and ventilated before and during occupancy.

  • Heat illness prevention relies on water, rest, shade, and gradual acclimatization; heat stroke is a medical emergency requiring immediate cooling and transport.

Quick reference

Scaffolds, Stairways, and Ladders

  • Fall protection is required on scaffolds 10 feet or more above a lower level (1926.451(g)); top rails are 38 to 45 inches high with a midrail and toeboards at least 3.5 inches high.

  • Each scaffold and scaffold platform must support at least 4 times the intended load, or 6 times for suspension scaffolds.

  • Rated scaffold loads are 25 psf for light duty, 50 psf for medium duty, and 75 psf for heavy duty.

  • Scaffolds must be erected, moved, or altered only under the supervision of a competent person, on firm footing, plumb, level, and fully planked with gaps no greater than 1 inch.

  • Access to scaffold platforms must be by ladder, stairway, or ramp; cross braces must never be used as a means of access.

  • Scaffolds, materials, and conductive items must be kept at least 10 feet from energized power lines.

  • Portable ladders follow the 4-to-1 rule (base 1 foot out for every 4 feet of working length, about 75 degrees) and must extend 3 feet above the landing.

  • Stepladders must be fully open and locked, never used as a side-standing ladder, and the top two steps must not be used as a standing level.

  • Stairways with 4 or more risers, or rising more than 30 inches, require a stairrail or handrail; handrails are 30 to 37 inches above the tread nosing.

Quick reference

Excavations and Trenching

  • 1926.652 requires a protective system for excavations 5 feet or deeper unless the competent person determines the excavation is in stable rock; shallower excavations are evaluated by the competent person.

  • A competent person must inspect excavations and protective systems before each shift, after rainstorms, and after any event that could affect stability.

  • Spoil piles, equipment, and materials must be kept at least 2 feet back from the edge of an excavation.

  • Trenches 4 feet or deeper require a ladder, stairway, or ramp for egress placed so lateral travel is no more than 25 feet.

  • Maximum allowable slopes are 1.5:1 (about 53 degrees) for Type A soil, 1:1 (45 degrees) for Type B, and 0.75:1 (about 34 degrees) for Type C; Type C soil must not be benched.

  • Underground utilities must be located before digging by calling the state one-call system (811); exposed installations must be protected and supported, and hand digging is used near marked lines.

  • Hazardous atmospheres must be tested before entry where they may exist, with oxygen between 19.5 and 23.5 percent and flammable gas below 10 percent of the lower explosive limit.

  • Water accumulation requires a special support system and removal of the water; adjacent structures, sidewalks, and walls must be monitored for cracks and movement.

  • Walkways crossing excavations 30 inches or wider must have standard guardrails on all open sides.

Quick reference

Cranes, Material Handling, and Tools

  • Under 29 CFR 1926.1400 (Subpart CC), crane operators must be certified or qualified, and signal persons and riggers must be qualified.

  • A crane must never lift beyond the rated capacity shown on the load chart for its configuration; capacity decreases as radius and boom length increase.

  • The swing radius of the crane must be barricaded, and employees must stay clear of the counterweight tail swing.

  • A single designated signal person directs the operator, but any employee may give an emergency stop signal.

  • Rigging hardware and slings must be inspected before each lift and removed from service if damaged; sling tension increases as the angle from horizontal decreases (multiplier equals 1 divided by the sine of the angle).

  • Cranes must maintain the minimum approach distance from energized lines under 1926.1408, or the line must be de-energized, grounded, or isolated with a dedicated spotter.

  • A suspended load must never be left unattended, and no one may ride the load or the hook.

  • Stored lumber must not exceed 20 feet in height, and must not exceed 16 feet when handled manually; stored materials must be stable and cross-tied.

  • Abrasive wheel guards must cover the spindle and wheel flanges with the tool rest set no more than 1/8 inch from the wheel; powder-actuated tools may be operated only by trained, authorized employees with eye and hearing protection.