PE Construction study materials
PE Construction study resources

PE Construction cheat sheet

PE Construction · Keep the key ideas within reach.

Quick reference

Project Planning (breadth)

  • WBS decomposes scope into deliverable-oriented levels; the lowest level, the work package, is the unit for estimating, scheduling, and responsibility assignment.

  • PERT expected duration te = (a + 4m + b) / 6; standard deviation = (b - a) / 6.

  • Total float = LS - ES = LF - EF; free float = ES(successor) - EF(activity).

  • The critical path is the longest continuous path through the network; it has zero total float and sets project duration.

  • Gantt bar charts show timing but not logic ties; CPM and PERT networks show dependencies and float.

  • Constructability review applies construction knowledge during design to reduce cost, schedule, and safety risk.

  • Life-cycle cost = initial capital cost + present value of operations, maintenance, and replacement over the service life.

  • Regulatory approvals (NPDES stormwater permit, environmental permits, building permits) should be identified during preconstruction planning.

Quick reference

Means and Methods (breadth)

  • Earth retention selection: sheet piles for high groundwater and tight sites; soldier piles with lagging for stiff soils; slurry walls for deep cuts; secant piles where groundwater cutoff is needed.

  • Dewatering selection: sumps for shallow seepage; wellpoints for drawdown to about 4-6 m; deep wells for greater depths; ejectors for low-permeability fine soils.

  • Crane load charts give capacity as a function of radius and boom length; required capacity includes the load, rigging, and block weight.

  • Underwater concrete is placed by tremie with the pipe discharge kept submerged; free fall in air is limited to about 1.5 m to prevent segregation.

  • Compaction equipment: smooth-drum rollers for granular base; sheepsfoot for cohesive soils; vibratory rollers for granular soils; pneumatic-tired rollers for both.

  • OSHA 1926 Subpart P: trenches 5 ft or deeper need a protective system; spoil and equipment are kept at least 2 ft from the edge.

  • Asphalt compaction follows breakdown, intermediate, and finish rolling within a specified temperature window; rolling too cold yields inadequate density.

  • Formwork design pressure depends on concrete placement rate, concrete temperature, slump, and the consolidation method.

Quick reference

Soil Mechanics (breadth)

  • Effective stress sigma' = sigma - u; Mohr-Coulomb shear strength tau = c' + sigma' tan(phi').

  • Atterberg limits: PI = LL - PL; high-plasticity clays are expansive and prone to shrink-swell.

  • Modified Proctor (ASTM D1557) uses more compaction energy than Standard Proctor (ASTM D698), giving higher maximum dry unit weight at lower optimum moisture content.

  • Consolidation settlement Sc = [Cc H / (1 + e0)] log10[(sigma'0 + delta sigma) / sigma'0].

  • Darcy's law: q = k i A, where i is the hydraulic gradient equal to head loss divided by flow length.

  • Relative density Dr = [(emax - e) / (emax - emin)] x 100%; granular soils above about 70% relative density are considered dense.

  • Liquefaction risk is highest in loose, saturated, uniformly graded sands with shallow groundwater under seismic loading.

  • Bearing capacity failure modes: general shear in dense soils, local and punching shear in loose soils; a factor of safety of 3 is typical for shallow foundations.

Quick reference

Structural Mechanics (breadth)

  • Static equilibrium requires sum of forces in x and y equal zero and sum of moments about any point equal zero.

  • Simple beam with uniform load w: maximum moment wL^2/8 at midspan; maximum shear wL/2 at the supports.

  • Cantilever with uniform load w: maximum moment wL^2/2 at the fixed support.

  • Simple beam with a point load P at midspan: maximum moment PL/4.

  • Bending stress sigma = M/S with section modulus S = I/c; horizontal shear stress tau = VQ/(It).

  • Euler buckling: Pcr = pi^2 EI / (KL)^2; K = 1.0 pinned-pinned, 0.5 fixed-fixed, 0.7 fixed-pinned, 2.0 fixed-free.

  • Shear diagram slope equals the distributed load; moment diagram slope equals shear; maximum moment occurs where shear crosses zero.

  • Truss analysis assumes pinned joints and loads applied only at joints; member forces are found by method of joints or method of sections.

Quick reference

Hydraulics and Hydrology (breadth)

  • Rational method: Q = CiA; rainfall intensity is selected for a duration equal to the time of concentration.

  • Manning equation in US customary units: V = (1.486/n) R^(2/3) S^(1/2), and Q = VA.

  • NRCS curve number: S = 1000/CN - 10; Q = (P - 0.2S)^2 / (P + 0.8S) when P exceeds 0.2S.

  • Orifice flow Q = C A sqrt(2gH); weir flow Q = C L H^(3/2).

  • Darcy-Weisbach head loss hf = f (L/D) (V^2/2g); Hazen-Williams is commonly used for water distribution piping.

  • Detention storage volume equals the area between the inflow and outflow hydrographs.

  • Stormwater pollution prevention plans typically require silt fence, check dams, inlet protection, and sediment basins.

Quick reference

Materials (breadth)

  • Concrete strength and durability are governed mainly by water-cement ratio; typical structural ratios are 0.40 to 0.50.

  • Design compressive strength is based on 28-day cylinder tests (6x12 in or 4x8 in specimens tested per ASTM C39).

  • Air entrainment of 4-8% improves freeze-thaw resistance; each percent of entrained air reduces compressive strength by roughly 3-5%.

  • Slump (ASTM C143) measures consistency and workability, not strength; water should be adjusted at the batch plant, not added at the site.

  • ASTM A615 Grade 60 reinforcement has a specified yield strength of 60 ksi.

  • Mortar types in descending compressive strength order: M, S, N, O, K.

  • Asphalt PG binder grades such as PG 64-22 denote high and low pavement service temperatures in degrees Celsius.

  • Curing maintains moisture and temperature above 50 F for about 7 days, or 14 days for high-early-strength or severe exposure conditions.

Quick reference

Construction Operations and Methods (depth)

  • Bank, loose, and compacted volumes relate through swell and shrinkage; compacted volume = bank volume x (1 - shrinkage).

  • Load factor = loose volume / bank volume; shrinkage = 1 - (compacted volume / bank volume).

  • Crane required capacity = load + rigging + block weight; verify the pick against the load chart at the maximum working radius.

  • Concrete pumping requires adequate slump and a pump line diameter compatible with maximum aggregate size; prime with grout and control vertical free fall.

  • Trenchless methods include horizontal directional drilling, microtunneling, pipe bursting, and auger boring.

  • Deep excavation monitoring uses settlement points, inclinometers, and piezometers to detect wall movement and groundwater change.

  • Steel erection fall protection is required at 15 ft; controlled decking zones are limited to specific leading-edge work with written procedures.

  • Hot-weather concreting: cool aggregates and mixing water, use retarders, place at lower slump, and cure immediately; avoid placement above about 90 F ambient.

Quick reference

Project Scheduling (depth)

  • Forward pass: ES = maximum EF of predecessors; EF = ES + duration.

  • Backward pass: LF = minimum LS of successors; LS = LF - duration.

  • Total float = LS - ES = LF - EF; critical path activities have zero total float.

  • Free float = ES(successor) - EF(activity); it is the delay possible without affecting any successor's early start.

  • Lag adds required waiting time between activities; lead allows overlap and is modeled as negative lag.

  • Resource leveling shifts activities within float to smooth resource peaks and may extend project duration.

  • Crashing adds resources to critical-path activities, prioritizing the lowest cost-per-day slope first.

  • Fast-tracking overlaps sequential activities and increases coordination and rework risk.

Quick reference

Project Estimating and Cost Control (depth)

  • AACE estimate classes range from Class 5 conceptual at -30%/+50% accuracy to Class 1 definitive at -5%/+10% accuracy.

  • Unit cost buildup: material + labor + equipment + subcontract + indirect costs + overhead + profit.

  • Contingency covers identified and unidentified risk; the allowance decreases as design and estimate maturity increase.

  • Earned value: EV = percent complete x BAC; CV = EV - AC; SV = EV - PV.

  • CPI = EV/AC and SPI = EV/PV; values below 1.0 indicate over budget or behind schedule.

  • EAC = BAC/CPI when the current cost trend continues; EAC = AC + (BAC - EV) when remaining work proceeds at the budget rate.

  • Labor productivity must be adjusted for weather, site access, and crew skill; crew-day output is the usual estimating unit.

  • Change order pricing order: contract unit rates first, then negotiated lump sum, then time and materials with documented costs.

Quick reference

Project Administration and Management (depth)

  • Contract types include lump sum, unit price, cost-plus-fixed-fee, guaranteed maximum price, and design-build; each shifts cost risk differently between owner and contractor.

  • AIA A201 General Conditions defines owner, contractor, and architect roles; AIA A101 is the owner-contractor agreement form.

  • Submittals, RFIs, and change orders must follow contractual time limits; failure to respond within the stated period can be deemed approval.

  • Type I differing site condition: a latent subsurface or hidden physical condition differing materially from the contract documents.

  • Type II differing site condition: an unknown physical condition of an unusual nature differing from conditions ordinarily encountered.

  • Concurrent owner and contractor delay generally bars compensable delay damages for either party.

  • Performance bonds guarantee completion; payment bonds guarantee payment to subcontractors and suppliers; the Miller Act covers federal work.

  • Substantial completion allows owner occupancy and starts warranty periods; final completion follows punch list closeout.

Quick reference

Construction Safety (depth)

  • OSHA 29 CFR 1926 governs construction; Subpart M requires conventional fall protection at 6 ft for general construction work.

  • Scaffold fall protection is required at 10 ft; steel erection fall protection is required at 15 ft.

  • Excavations 5 ft or deeper require a protective system unless a competent person determines there is no hazard.

  • Spoil, materials, and equipment are kept at least 2 ft from excavation edges; ladders are required within 25 ft of lateral travel in trenches 4 ft deep or more.

  • Crane clearance from power lines: 10 ft for lines up to 50 kV, with greater distances at higher voltages per the OSHA table.

  • A competent person identifies existing and predictable hazards and has authority to take prompt corrective action; required for excavations, scaffolds, and fall protection.

  • Permit-required confined spaces require atmospheric testing, an attendant stationed outside, and a rescue plan before entry.

  • OSHA 1926.1153 silica exposure controls include engineering controls such as wet cutting, respiratory protection, and medical surveillance above the action level.