PE Construction flashcards
PE Construction · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Work breakdown structure
- A deliverable-oriented hierarchical decomposition of project scope. The lowest level is a work package that can be estimated, scheduled, and assigned to one responsible party.
- Total float formula
- Total float equals late start minus early start, or late finish minus early finish. It is the time an activity can slip without delaying the project completion date.
- PERT expected duration
- The PERT three-point estimate is (optimistic + 4 times most likely + pessimistic) divided by 6. Weighting the most likely value reduces bias in probabilistic scheduling.
- Tremie concrete placement
- Concrete is placed underwater through a vertical pipe whose discharge end stays submerged in fresh concrete, preventing water washout and segregation. The pipe stays full and is lifted slowly.
- Sheepsfoot roller use
- A sheepsfoot roller compacts cohesive soils such as clay and silt by kneading. It is most effective when the feet penetrate the lift and walk out as density increases.
- Wellpoint dewatering
- A wellpoint system uses a header pipe and closely spaced suction points to lower groundwater about 4 to 6 meters. Deeper drawdown requires staged or deep-well systems.
- Effective stress principle
- Effective stress equals total stress minus pore water pressure. It controls soil shear strength, compressibility, and consolidation settlement, forming the basis of Terzaghi soil mechanics.
- Plasticity index
- The plasticity index equals liquid limit minus plastic limit. It indicates the water content range over which soil behaves plastically; high values suggest expansive clay.
- Darcy's law
- Flow through soil equals hydraulic conductivity times hydraulic gradient times cross-sectional area (q = k i A). It describes laminar seepage and supports dewatering and stability analyses.
- Simply supported beam moment
- For a uniform load w over span L, maximum bending moment is wL squared over 8 at midspan, and maximum shear is wL over 2 at the supports.
- Euler buckling load
- Critical buckling load equals pi squared times EI divided by (KL) squared, where K depends on end conditions. Slender columns buckle before reaching yield stress.
- Section modulus
- Section modulus equals moment of inertia divided by distance to the extreme fiber. Bending stress in a beam is computed as moment divided by section modulus.
- Rational method
- Peak runoff Q equals runoff coefficient times rainfall intensity times drainage area (Q = CiA). Intensity is chosen for a storm duration equal to the time of concentration.
- Manning's equation
- Open-channel velocity equals 1.486/n times hydraulic radius to the two-thirds power times slope to the one-half power in US customary units. Discharge is velocity times area.
- NRCS curve number
- The curve number method estimates direct runoff from rainfall using hydrologic soil group, land use, and antecedent moisture. Runoff Q = (P - 0.2S) squared over (P + 0.8S).
- Water-cement ratio
- Lower water-cement ratio increases concrete strength, reduces permeability, and improves durability but reduces workability. Typical structural ratios range from 0.40 to 0.50.
- Air entrainment
- Entrained air bubbles, typically 4 to 8 percent by volume, provide freeze-thaw durability by relieving hydraulic pressure in saturated concrete. Air content increases as maximum aggregate size decreases.
- Swell and shrinkage factors
- Swell is the volume increase when bank soil is excavated and loosened. Shrinkage is the volume decrease when loose soil is compacted. Both convert bank, loose, and compacted quantities.
- Horizontal directional drilling
- A trenchless method that installs pipes and conduits beneath obstacles with minimal surface disturbance. Drilling fluid maintains borehole stability, and the method suits road and river crossings.
- Concrete cold-weather protection
- Fresh concrete must be maintained above 50 F until it reaches about 500 psi strength. Methods include heated water and aggregates, accelerators, insulating blankets, and heated enclosures.
- Forward pass scheduling
- The forward pass calculates early start and early finish for each activity by working from project start through the network, adding durations to the controlling predecessor finish.
- Free float
- Free float is the early start of the successor minus the early finish of the activity. It is the delay possible without affecting any successor early start.
- Schedule crashing
- Crashing shortens duration by adding resources to activities on the critical path. It increases cost and should target the lowest cost-per-day slope first.
- Earned value CPI
- Cost performance index equals earned value divided by actual cost. A CPI below 1.0 means the project is over budget relative to the work performed.
- Estimate accuracy class
- AACE estimate classes range from Class 5 conceptual at minus 30 to plus 50 percent accuracy to Class 1 definitive at minus 5 to plus 10 percent.
- Schedule performance index
- SPI equals earned value divided by planned value. Values below 1.0 indicate that work is progressing slower than the baseline schedule planned.
- Differing site conditions
- Type I latent conditions are hidden physical conditions differing materially from contract documents. Type II is an unknown physical condition of unusual nature. Both usually entitle the contractor to adjustment.
- Performance bond
- A surety bond guaranteeing the contractor will complete the work per contract terms. If the contractor defaults, the surety arranges completion or pays the owner the bond amount.
- Substantial completion
- The stage when work is sufficiently complete for its intended use, allowing owner occupancy. It starts warranty periods and limits assessment of liquidated damages.
- Excavation protective system threshold
- OSHA requires a protective system for excavations 5 feet or deeper unless a competent person determines no hazard exists. Shallower excavations also need protection when hazards are present.
- Crane power line clearance
- For overhead lines up to 50 kV, equipment must stay at least 10 feet away. Higher voltages require greater distances per the OSHA table, and a dedicated spotter is required.
- Competent person definition
- One who can identify existing and predictable hazards and has authority to take prompt corrective measures. Required for excavations, scaffolds, fall protection, and other high-hazard work.