PECB ISO 21502 Lead Project Manager · Put your knowledge to work in context.

The PECB Certified ISO 21502 Lead Project Manager credential is issued by PECB after a candidate passes the associated exam and meets the certification requirements. The credential is aimed at project managers, project sponsors, expert advisers, project team members, executives and directors involved in governance, direction and audits of projects, and individuals seeking to understand or advance in project management. The exam assesses three competency domains: fundamental principles and concepts of project management; integrated project management practices; and individual management practices for a project. PECB describes the supporting five-day training course as covering initiation, planning, monitoring, directing, controlling and closing a project based on ISO 21502 guidelines, with lecture sessions, practical examples, discussions, and quizzes in both stand-alone and scenario-based formats. The PECB ISO 21502 Lead Project Manager case studies are 5 cases and about 2,946 words.

1

Fixed launch date before a defined benefit

A government agency has approved a citizen-portal project with a fixed launch date set by a minister's public announcement. The budget is EUR 2.4 million, the team is assembled, and the vendor contract is signed.

628 words, about 3 min
2

Three unlogged changes on an ERP baseline

An ERP rollout is at month 6 of a 12-month schedule. The approved baseline covers eight workstreams, a budget of USD 3.1 million and a go-live before fiscal year end.

602 words, about 3 min
3

Single qualified engineer reassigned at zero float

A pharmaceutical validation project is in execution. The only qualified computer-system-validation engineer, who is employed by a functional department, has been reassigned for four weeks to a regulatory audit.

603 words, about 3 min
4

Supplier fails a performance threshold before go-live

A hospital is replacing its patient-records interface. The supplier contract includes a 30-day acceptance test and a 10% retention payment.

563 words, about 3 min
5

Pressure to close before service acceptance

A local government data-migration project reports all deliverables complete on time and under budget. The project was to migrate 1.2 million records to a new case-management system and decommission two legacy servers.

550 words, about 3 min