The Analyst Who Added Standard Deviations
A critical path has five sequential activities, each independently estimated with a standard deviation of 2 days. Expected path duration is 50 days and the sponsor's target is day 55. The analyst adds the five deviations, gets σ = 10 days, computes z = (55 − 50) / 10 = 0.5, reads 69%, and reports 'only 69% confidence - we need to crash the path.' A second analyst proposes the opposite fix: cut the pessimistic estimate on activity 3, which has O = 4, M = 6, P = 20, while the other four activities each have ranges of 8 days or less. Crashing activity 1 by 2 days costs $18,000; the risk-response work on activity 3 costs $6,000 and does not shorten its expected duration.
1. Check the analyst's standard deviation and probability, and show the correct figures.
Read the worked answer
The addition is wrong. Variances add; standard deviations do not.
Correct method:
- Each activity: σ = 2 → variance = 4
- Path variance = 4 + 4 + 4 + 4 + 4 = 20
- Path σ = √20 = 4.47 days
Correct probability for day 55:
- z = (55 − 50) / 4.47 = 1.12
- P ≈ 87%
The analyst's 69% understates confidence by about 18 points. Summing σ overstates path uncertainty whenever there is more than one activity - and the error grows with the number of activities: two activities would give 4.0 instead of 2.83, five give 10.0 instead of 4.47, ten would give 20.0 instead of 6.32. The root-sum-square rule reflects partial offsetting: independent activities do not all hit their pessimistic values in the same run, which is precisely the diversification the naive sum ignores.
Consequence in this case: the analyst's number triggered a crash decision that the schedule did not need. Fix the arithmetic before spending the money.
2. Compare the two proposed interventions and recommend one, with reasoning.
Read the worked answer
Recommend the activity 3 risk response, and do not crash activity 1.
Activity 3 dominates the variance:
- σ₃ = (P − O) / 6 = (20 − 4) / 6 = 2.67; variance ≈ 7.11
- The other four activities have σ ≤ 8/6 = 1.33, variance ≤ 1.78 each, about 7.1 combined at most
- So activity 3 alone accounts for roughly half the path variance
If the response cuts P from 20 to 12: σ₃ = (12 − 4)/6 = 1.33, variance 1.78 - path variance drops from about 14.2 to 8.9, path σ from about 3.8 to about 3.0.
Crashing activity 1 by 2 days:
- Moves the mean from 50 to 48 → z = (55 − 48)/4.47 = 1.57 → about 94%
- It also costs 3× more ($18,000 vs $6,000) and buys the schedule nothing durable: it shifts the mean but leaves a fat pessimistic tail on activity 3, so the downside scenario is unchanged.
Judgement:
- If the goal is a date, crashing buys probability fastest and most predictably - so if day 55 were a hard external commitment and the response could not be delivered in time, crashing wins on speed.
- If the goal is a robust plan, the variance reduction is the better buy: cheaper, it shrinks the tail instead of hiding it, and it addresses where the uncertainty actually lives.
- Best of all, and what the numbers support: do the $6,000 response, re-run the probability, and only crash if the recomputed figure is still below tolerance. Crashing to fix a 69% that was really 87% is spending against a spreadsheet error.
3. The sponsor asks why the confidence figure is not simply 'one number we can hold people to.' Frame the answer using this path's numbers.
Read the worked answer
Because the output is a probability at a date, not a date - and the two cuts of this same data give very different management messages.
- Day 50 (the mean) → z = 0 → 50%. A coin flip. Half the time the plan is late.
- Day 52 (μ + 0.5σ) → z = 0.45 → about 67%.
- Day 55 (sponsor's target) → z = 1.12 → about 87%.
- Day 59 (μ + 2σ) → z = 2.0 → about 98%.
All four are true statements about the same path. Choosing one is a risk-tolerance decision owned by the sponsor, not a calculation owned by the scheduler. The scheduler's job is to present the ladder and say what each rung costs.
Three caveats to attach to any number quoted from this model:
- It assumes independence. The five activities are sequential and almost certainly share a team; correlation widens the tail and lowers every figure above.
- It assumes the critical path is the only path that matters. A near-critical path with a wide range can govern - the 87% is only as good as the path enumeration behind it.
- It is only as good as the three-point inputs. The formula transforms judgement; it does not create it. Activity 3's P = 20 is doing most of the work here, and if that number is a guess, so is the 87%.
Suggested wording for the sponsor: 'Eighty-seven percent at day 55 with current estimates, assuming the conversion risk is not addressed. If we fund the $6,000 response, the band tightens. Which confidence level do you want to sign up to, and at what date?'