PERT - the Program Evaluation and Review Technique - is a project scheduling method rather than a single issuing body's certification. It is taught and assessed inside project management, operations, engineering, and construction curricula, and many employers and training providers offer their own PERT-based exams. This page supports study for PERT-style assessment: the ability to model a project as a network of activities, estimate durations three ways, identify the critical path and float, and translate that network into a defensible probability statement about schedule completion. Candidates are typically coordinators, planners, analysts, or PMP-track practitioners who already know basic scheduling terminology and want the quantitative side. The PERT study guide has 4 sections and about 1,542 words.

01

Project Network Modeling and Activity Sequencing

A schedule network converts the activity list and its dependencies into a graph. The dominant convention is activity-on-node (AON) , also called the precedence diagram, where boxes are activities and arrows are precedence links.

347 words, about 2 min
02

Three-Point Estimating (Optimistic, Most Likely, Pessimistic)

Three-point estimating replaces a single duration with a range: O (optimistic - everything goes right), M (most likely - the mode, the duration you would bet on), and P (pessimistic - a realistic worst case, not a disaster scenario). Two weighted formulas appear on exams: Triangular: TE = (O + M + P) / 3 - equal weights, a simple average.

386 words, about 2 min
03

Critical Path and Float/Slack Analysis

Every activity carries four dates. The forward pass moves left to right: ES = latest EF among predecessors (plus lag); EF = ES + duration.

427 words, about 2 min
04

Schedule Probability, Variance, and Risk Interpretation

PERT treats project duration as a random variable, approximately normal, with mean TE (the critical path length built from three-point estimates) and standard deviation σpath = √(sum of variances of activities on the critical path). Then: Z = (T − TE) / σpath where T is the target date.

382 words, about 2 min