PERT key terms
PERT · Get comfortable with the vocabulary.
- Project Network Diagram
- Related: Activity-on-Node (AON), Activity-on-Arrow (AOA), Predecessor
A graphical model showing project activities as boxes or arrows and linking them with dependency lines, so the sequence and logical flow of work can be analyzed.
- Activity-on-Node (AON)
- Related: Activity-on-Arrow (AOA), Project Network Diagram, Predecessor
A network drawing method where each activity is represented by a node, usually a box, and arrows show only logical dependencies between activities rather than duration.
- Activity-on-Arrow (AOA)
- Related: Activity-on-Node (AON), Dummy Activity, Project Network Diagram
A network drawing method where arrows represent activities and nodes represent events or points in time; dummy arrows are sometimes added to keep the logic correct.
- Predecessor
- Related: Successor, Finish-to-Start (FS), Start-to-Start (SS)
An activity that must begin or finish before another specified activity can start or finish, establishing the required order of work in the network.
- Successor
- Related: Predecessor, Finish-to-Start (FS)
An activity whose start or finish depends on the start or completion of another activity earlier in the network sequence.
- Finish-to-Start (FS)
- Related: Predecessor, Successor, Start-to-Start (SS)
A dependency type where the successor activity cannot start until the predecessor activity has finished; it is the most common relationship in project schedules.
- Start-to-Start (SS)
- Related: Finish-to-Start (FS), Lead, Lag
A dependency type where the successor activity cannot start until the predecessor activity has started, allowing two activities to run in parallel after a common start.
- Lag
- Related: Lead, Finish-to-Start (FS), Predecessor
A deliberate waiting period inserted between two dependent activities, expressed in time units, that delays the successor beyond the normal relationship.
- Lead
- Related: Lag, Start-to-Start (SS)
A negative lag that allows a successor activity to begin before its predecessor finishes, effectively accelerating the start of downstream work.
- Dummy Activity
- Related: Activity-on-Arrow (AOA), Merge Activity
A zero-duration, resource-free arrow used in activity-on-arrow networks to show a logical dependency that cannot otherwise be drawn correctly.
- Merge Activity
- Related: Dummy Activity, Predecessor, Critical Path
An activity with two or more immediate predecessors, where separate paths come together; its start waits for every incoming path to finish.
- Milestone
- Related: Project Network Diagram
A significant point or event in the project with zero duration, used to mark completion of a major deliverable or phase.
- Three-Point Estimating
- Related: Optimistic Estimate, Most Likely Estimate, Pessimistic Estimate
A technique that uses optimistic, most likely, and pessimistic duration estimates to capture uncertainty and compute an expected activity duration and variance.
- Optimistic Estimate
- Related: Pessimistic Estimate, Most Likely Estimate, Three-Point Estimating
The shortest realistic time an activity could take if everything goes unusually well, with no major problems or delays.
- Most Likely Estimate
- Related: Optimistic Estimate, Pessimistic Estimate, Beta Distribution
The duration an activity is expected to take under normal conditions, assuming typical problems and normal productivity, and the most probable single value.
- Pessimistic Estimate
- Related: Optimistic Estimate, Most Likely Estimate
The longest realistic time an activity could take if major problems occur, excluding extreme catastrophes or highly unlikely events.
- PERT Expected Duration
- Related: Beta Distribution, Three-Point Estimating, Activity Standard Deviation
The weighted average duration calculated as (Optimistic + 4 times Most Likely + Pessimistic) divided by 6, used as the mean activity time in PERT analysis.
- Beta Distribution
- Related: PERT Expected Duration, Triangular Distribution, Pessimistic Estimate
A probability distribution often used in PERT to model activity duration, allowing asymmetry around the most likely value and bounded optimistic and pessimistic limits.
- Triangular Distribution
- Related: Beta Distribution, Three-Point Estimating
A three-point probability distribution that uses optimistic, most likely, and pessimistic values with simple averaging, producing a less peaked shape than the beta distribution.
- Activity Standard Deviation
- Related: Activity Variance, Pessimistic Estimate, Optimistic Estimate
A measure of duration uncertainty for one activity, calculated as (Pessimistic minus Optimistic) divided by 6 in classic PERT, showing how spread out possible durations are.
- Activity Variance
- Related: Activity Standard Deviation, Project Variance
The square of an activity's standard deviation, representing the spread of its possible durations and used to build project-level schedule variance.
- Critical Path
- Related: Total Float, Forward Pass, Near-Critical Path
The longest-duration path through the network, which determines the shortest possible project completion time and has zero total float when no constraints exist.
- Total Float
- Related: Free Float, Critical Path, Backward Pass
The amount of time an activity can be delayed without delaying the project completion date, calculated as late start minus early start or late finish minus early finish.
- Free Float
- Related: Total Float, Successor, Early Start
The amount of time an activity can be delayed without delaying the early start of any immediate successor activity in the network.
- Forward Pass
- Related: Backward Pass, Early Start, Early Finish
A calculation that moves from network start to finish, assigning early start and early finish dates based on predecessor durations and dependencies.
- Backward Pass
- Related: Forward Pass, Late Finish, Late Start
A calculation that moves from network finish to start, assigning late finish and late start dates and revealing where float exists.
- Early Start
- Related: Early Finish, Forward Pass, Predecessor
The earliest possible date an activity can begin, given the finish dates of its predecessors and the project start date.
- Early Finish
- Related: Early Start, Forward Pass
The earliest possible date an activity can complete in the schedule, equal to its early start plus its estimated duration.
- Late Start
- Related: Late Finish, Backward Pass, Total Float
The latest date an activity can begin without delaying the project completion date, found by subtracting its duration from its late finish.
- Late Finish
- Related: Late Start, Backward Pass, Successor
The latest date an activity can complete without delaying the project completion date, determined from successors' late starts during the backward pass.
- Near-Critical Path
- Related: Critical Path, Total Float, Schedule Risk Analysis
A network path whose total float is very small, so modest duration slippage could make it critical and change the project finish date.
- PERT Probability Calculation
- Related: Z-Score, Standard Normal Distribution, Target Completion Date
A method that converts the difference between a target date and expected project duration into a Z-score, then uses the normal distribution to estimate on-time probability.
- Z-Score
- Related: Standard Normal Distribution, PERT Probability Calculation, Project Variance
The number of standard deviations a target completion date lies above or below the expected project duration, used to look up completion probability.
- Standard Normal Distribution
- Related: Z-Score, Confidence Level
A bell-shaped probability curve with mean zero and standard deviation one, used with Z-scores to find the chance of finishing by a given date.
- Target Completion Date
- Related: PERT Probability Calculation, Confidence Level
A specified deadline or desired project finish date that is compared with the expected duration to compute the probability of finishing on time.
- Confidence Level
- Related: Target Completion Date, Standard Normal Distribution, PERT Probability Calculation
The probability, expressed as a percentage, that the project will finish by a particular date or within a particular duration.
- Project Variance
- Related: Activity Variance, Path Variance, Critical Path
The sum of the variances of activities on the critical path, used as the measure of uncertainty for the overall project duration.
- Path Variance
- Related: Project Variance, Activity Variance, Near-Critical Path
The combined variance of all activities along a particular network path, indicating how much that path's duration may vary.
- Monte Carlo Simulation
- Related: Three-Point Estimating, Schedule Risk Analysis, Confidence Level
A computer-based technique that repeatedly samples activity durations from probability distributions to build a distribution of possible project completion dates.
- Schedule Risk Analysis
- Related: Monte Carlo Simulation, Near-Critical Path, Confidence Level
The process of examining uncertainty in activity durations and dependencies to understand the likelihood of meeting schedule targets and identify risky paths.