PERT · Get comfortable with the vocabulary.

Project Network Diagram

A graphical model showing project activities as boxes or arrows and linking them with dependency lines, so the sequence and logical flow of work can be analyzed.

Related: Activity-on-Node (AON), Activity-on-Arrow (AOA), Predecessor
Activity-on-Node (AON)

A network drawing method where each activity is represented by a node, usually a box, and arrows show only logical dependencies between activities rather than duration.

Related: Activity-on-Arrow (AOA), Project Network Diagram, Predecessor
Activity-on-Arrow (AOA)

A network drawing method where arrows represent activities and nodes represent events or points in time; dummy arrows are sometimes added to keep the logic correct.

Related: Activity-on-Node (AON), Dummy Activity, Project Network Diagram
Predecessor

An activity that must begin or finish before another specified activity can start or finish, establishing the required order of work in the network.

Related: Successor, Finish-to-Start (FS), Start-to-Start (SS)
Successor

An activity whose start or finish depends on the start or completion of another activity earlier in the network sequence.

Related: Predecessor, Finish-to-Start (FS)
Finish-to-Start (FS)

A dependency type where the successor activity cannot start until the predecessor activity has finished; it is the most common relationship in project schedules.

Related: Predecessor, Successor, Start-to-Start (SS)
Start-to-Start (SS)

A dependency type where the successor activity cannot start until the predecessor activity has started, allowing two activities to run in parallel after a common start.

Related: Finish-to-Start (FS), Lead, Lag
Lag

A deliberate waiting period inserted between two dependent activities, expressed in time units, that delays the successor beyond the normal relationship.

Related: Lead, Finish-to-Start (FS), Predecessor
Lead

A negative lag that allows a successor activity to begin before its predecessor finishes, effectively accelerating the start of downstream work.

Related: Lag, Start-to-Start (SS)
Dummy Activity

A zero-duration, resource-free arrow used in activity-on-arrow networks to show a logical dependency that cannot otherwise be drawn correctly.

Related: Activity-on-Arrow (AOA), Merge Activity
Merge Activity

An activity with two or more immediate predecessors, where separate paths come together; its start waits for every incoming path to finish.

Related: Dummy Activity, Predecessor, Critical Path
Milestone

A significant point or event in the project with zero duration, used to mark completion of a major deliverable or phase.

Related: Project Network Diagram
Three-Point Estimating

A technique that uses optimistic, most likely, and pessimistic duration estimates to capture uncertainty and compute an expected activity duration and variance.

Related: Optimistic Estimate, Most Likely Estimate, Pessimistic Estimate
Optimistic Estimate

The shortest realistic time an activity could take if everything goes unusually well, with no major problems or delays.

Related: Pessimistic Estimate, Most Likely Estimate, Three-Point Estimating
Most Likely Estimate

The duration an activity is expected to take under normal conditions, assuming typical problems and normal productivity, and the most probable single value.

Related: Optimistic Estimate, Pessimistic Estimate, Beta Distribution
Pessimistic Estimate

The longest realistic time an activity could take if major problems occur, excluding extreme catastrophes or highly unlikely events.

Related: Optimistic Estimate, Most Likely Estimate
PERT Expected Duration

The weighted average duration calculated as (Optimistic + 4 times Most Likely + Pessimistic) divided by 6, used as the mean activity time in PERT analysis.

Related: Beta Distribution, Three-Point Estimating, Activity Standard Deviation
Beta Distribution

A probability distribution often used in PERT to model activity duration, allowing asymmetry around the most likely value and bounded optimistic and pessimistic limits.

Related: PERT Expected Duration, Triangular Distribution, Pessimistic Estimate
Triangular Distribution

A three-point probability distribution that uses optimistic, most likely, and pessimistic values with simple averaging, producing a less peaked shape than the beta distribution.

Related: Beta Distribution, Three-Point Estimating
Activity Standard Deviation

A measure of duration uncertainty for one activity, calculated as (Pessimistic minus Optimistic) divided by 6 in classic PERT, showing how spread out possible durations are.

Related: Activity Variance, Pessimistic Estimate, Optimistic Estimate
Activity Variance

The square of an activity's standard deviation, representing the spread of its possible durations and used to build project-level schedule variance.

Related: Activity Standard Deviation, Project Variance
Critical Path

The longest-duration path through the network, which determines the shortest possible project completion time and has zero total float when no constraints exist.

Related: Total Float, Forward Pass, Near-Critical Path
Total Float

The amount of time an activity can be delayed without delaying the project completion date, calculated as late start minus early start or late finish minus early finish.

Related: Free Float, Critical Path, Backward Pass
Free Float

The amount of time an activity can be delayed without delaying the early start of any immediate successor activity in the network.

Related: Total Float, Successor, Early Start
Forward Pass

A calculation that moves from network start to finish, assigning early start and early finish dates based on predecessor durations and dependencies.

Related: Backward Pass, Early Start, Early Finish
Backward Pass

A calculation that moves from network finish to start, assigning late finish and late start dates and revealing where float exists.

Related: Forward Pass, Late Finish, Late Start
Early Start

The earliest possible date an activity can begin, given the finish dates of its predecessors and the project start date.

Related: Early Finish, Forward Pass, Predecessor
Early Finish

The earliest possible date an activity can complete in the schedule, equal to its early start plus its estimated duration.

Related: Early Start, Forward Pass
Late Start

The latest date an activity can begin without delaying the project completion date, found by subtracting its duration from its late finish.

Related: Late Finish, Backward Pass, Total Float
Late Finish

The latest date an activity can complete without delaying the project completion date, determined from successors' late starts during the backward pass.

Related: Late Start, Backward Pass, Successor
Near-Critical Path

A network path whose total float is very small, so modest duration slippage could make it critical and change the project finish date.

Related: Critical Path, Total Float, Schedule Risk Analysis
PERT Probability Calculation

A method that converts the difference between a target date and expected project duration into a Z-score, then uses the normal distribution to estimate on-time probability.

Related: Z-Score, Standard Normal Distribution, Target Completion Date
Z-Score

The number of standard deviations a target completion date lies above or below the expected project duration, used to look up completion probability.

Related: Standard Normal Distribution, PERT Probability Calculation, Project Variance
Standard Normal Distribution

A bell-shaped probability curve with mean zero and standard deviation one, used with Z-scores to find the chance of finishing by a given date.

Related: Z-Score, Confidence Level
Target Completion Date

A specified deadline or desired project finish date that is compared with the expected duration to compute the probability of finishing on time.

Related: PERT Probability Calculation, Confidence Level
Confidence Level

The probability, expressed as a percentage, that the project will finish by a particular date or within a particular duration.

Related: Target Completion Date, Standard Normal Distribution, PERT Probability Calculation
Project Variance

The sum of the variances of activities on the critical path, used as the measure of uncertainty for the overall project duration.

Related: Activity Variance, Path Variance, Critical Path
Path Variance

The combined variance of all activities along a particular network path, indicating how much that path's duration may vary.

Related: Project Variance, Activity Variance, Near-Critical Path
Monte Carlo Simulation

A computer-based technique that repeatedly samples activity durations from probability distributions to build a distribution of possible project completion dates.

Related: Three-Point Estimating, Schedule Risk Analysis, Confidence Level
Schedule Risk Analysis

The process of examining uncertainty in activity durations and dependencies to understand the likelihood of meeting schedule targets and identify risky paths.

Related: Monte Carlo Simulation, Near-Critical Path, Confidence Level