Northwind Foods has a three-year carriage agreement with ColdChain Logistics at a fixed USD 0.42 per pallet-mile, with a volume commitment of 8,000 pallets a month and a 70% take-or-pay floor. Clause 14 (force majeure) lists 'acts of government, epidemics, war and strikes'. Clause 22 bars oral modification; clause 19 is an entire-agreement clause. New York law governs. Fuel has risen 55% and a new state regulation limits refrigerated trailer idling to two hours, lengthening routes by about 18% on Northwind's lanes. ColdChain demands a 30% rate increase and says it will stop serving Northwind unless a signed amendment is returned by Friday. Northwind sells to a retailer on fixed pricing and has been quoted substitute capacity at 22% more, available in three weeks.

1. Is ColdChain entitled to relief under clause 14? Work through the elements rather than stopping at the words 'acts of government'.

Read the worked answer

Step 1 - characterise the event. Two events: fuel price movement (market) and a regulation (state action). Only the second is even arguably within clause 14's list.

Step 2 - test the clause's own terms. Force majeure generally requires that the event be beyond reasonable control, unforeseeable at contracting, and that it prevent performance - not merely make it less profitable. An 18% route-length increase does not stop ColdChain from driving. Fuel volatility is the paradigm of a foreseeable commercial risk priced into a fixed-rate contract.

Step 3 - test the default law. Under New York law, impracticability requires extreme and unreasonable difficulty, not a squeeze on margin. Price increases, even large ones, are ordinarily not a defence. Frustration of purpose is worse: Northwind's purpose is still achievable.

Conclusion: clause 14 is a weak argument and would at most suspend obligations, not reprice them. ColdChain's demand is a commercial renegotiation dressed as a legal right. Northwind should say so - in writing, without conceding - while keeping the relationship workable.

Watch the trap: the force majeure clause does not say 'economic hardship', and reading one in would rewrite the contract.

2. Evaluate the duress risk if Northwind signs the amendment on Friday, and design the response.

Read the worked answer

Duress analysis. A threat to breach an existing contract can be economic duress, but only where the threat is wrongful and leaves the victim no practical alternative. Northwind has a 22% substitute at three weeks' lead time and perishable goods exposure. That is a real alternative (expensive and inconvenient, not 'no choice'), which weakens a duress claim considerably. Signing under protest is therefore legally weaker on duress than on reservation of rights.

Practical weaknesses if it signs a bare 30% amendment:

  • Clause 22 requires written modification - fine - but clause 19 (entire agreement) means any side letter promising later adjustment may be excluded.
  • A blanket 30% sets a precedent for every other carrier and may breach parity clauses elsewhere.
  • It is a 30% uplift on a fixed-price downstream sale - direct margin loss.

Design of the response:

  1. Written holding response before Friday: the obligation continues, the demand is not accepted, no waiver.
  2. Offer a narrow, indexed, symmetric fuel surcharge tied to a published index, with a floor and ceiling and a sunset, plus a documented productivity adjustment for the idling rule.
  3. Express reservation of all rights, including for past shortfalls and any service failure during the dispute.
  4. Internal sign-off: procurement plus finance plus legal; check delegated authority before anyone signs.
  5. Parallel market engagement with the alternative carrier to preserve the option, not as a threat.

Key judgement: the deadline is pressure, not a legal doctrine. Nothing in the contract converts Friday into a legal event.

3. If ColdChain stops serving Northwind next week, what are Northwind's remedies and what should it do in the first 48 hours?

Read the worked answer

First 48 hours:

  • Written notice of breach and demand for continued performance; preserve evidence of volumes tendered (the take-or-pay floor cuts both ways - Northwind should be able to show it tendered its commitment, so no shortfall liability arises).
  • Activate the substitute carrier immediately; quantify the delta per pallet-mile against USD 0.42.
  • Protect the downstream relationship: notify the retailer per the supply terms, invoke any agreed continuity plan.

Remedies:

  • Cover damages: the difference between the contract rate and the cost of substitute carriage, over the remaining term and within the committed or reasonably anticipated volumes.
  • Consequential loss: only if foreseeable at contracting; Northwind's fixed-price resale and service credits are the likely heads. Check for an exclusion of consequential loss and any cap in the contract.
  • Specific performance: unlikely for a service contract of this kind; injunctions to restrain a threatened breach are also difficult to obtain.
  • Suspension and set-off: confirm the contract permits it before withholding payment - unilateral set-off can itself be a breach.

Mitigation duty governs everything: a court will not award the delta on volumes Northwind could have avoided at no extra cost.

Strategic note: the best outcome is a two-track posture - litigate the delta, negotiate the surcharge - and the negotiating leverage comes from proving the substitute is not a bluff.