Scaffolding Works NC II · Build recall with a focused review session.

33 cards. Read the term and the definition here. The deck at the top of this page is optional.

Fall-arrest anchor height
A personal fall-arrest lanyard should be anchored at or above shoulder level so the free-fall distance stays short and the deceleration device can arrest the fall safely.
Guardrail height requirement
A toprail is fitted between 0.9 m and 1.15 m above the platform, with a midrail at about half that height and toe boards at least 150 mm high.
Toe board purpose
Toe boards at least 150 mm high along platform edges prevent tools, materials, and debris from being kicked or blown off and striking workers below.
Electrical clearance rule
Keep scaffolds and long materials at least 3.0 m clear of energized lines up to 50 kV, and increase the distance for higher voltages unless the line is de-energized and locked out.
Manual handling limit
One person should not lift more than roughly 25 kg at waist height; use two-person lifts, hoists, or rope-and-pulley systems for heavier scaffold components.
Suspension trauma risk
A worker left hanging in a harness after a fall can lose consciousness within minutes, so the rescue plan must allow retrieval almost immediately, not after a long wait.
Coupler torque value
Right-angle and swivel couplers are tightened to the manufacturer's specified torque, commonly about 40 to 50 N·m, and checked periodically with a torque wrench.
Scaffold tube dimensions
Common steel scaffold tube has an outside diameter of 48.3 mm with a wall thickness of 3.2 mm or 4.0 mm; reject tubes that are bent, cracked, or badly corroded.
Inspection tag color code
A green tag means the component or scaffold has been inspected and is safe to use; a red tag means defective or unsafe and the item must be quarantined.
Wire rope discard criterion
A wire rope sling is removed from service when broken wires reach about 10 percent of the total wires in one lay, or when there is distortion or severe corrosion.
Sole board specification
Sole boards under scaffold standards are at least 35 mm thick and 220 mm wide, laid flat on firm ground to spread the load and prevent settlement.
Plank defect rejection
Reject scaffold planks that have splits through the thickness, rot, large loose knots, or heavy warping, because these defects reduce the plank's load-carrying capacity.
RCD protection for tools
Portable electric tools on site must be protected by a residual current device and have undamaged cords and guards; damaged tools are tagged and removed from service.
Standard bay dimensions
For tube-and-coupler independent scaffolds, bay length is typically 1.8 to 2.1 m, lift height about 2.0 m, and platform width at least 0.6 m.
Tie pattern 2:2
A common tie pattern for independent scaffolds ties every alternate standard at every alternate lift, but the design drawing always governs the actual pattern.
Scaffold load classes
Light duty allows up to 150 kg per bay, medium duty up to 250 kg per bay, and heavy duty up to 450 kg per bay; classes must not be mixed without design approval.
Base jack function
Adjustable base jacks sit on sole boards under each standard to level the scaffold and spread the load, and must be checked for bearing on firm ground.
Façade brace angle
Façade bracing is fixed at roughly 45 to 60 degrees in both directions and must never be removed to create access; ledger bracing is added at alternate lifts.
Plumb tolerance for standards
Scaffold standards must be plumb within 1 in 500, and joints in standards are staggered so no more than one joint occurs at the same level in one standard.
Platform plank gap limit
Planks are laid with gaps no greater than 25 mm, butt-jointed over a transom with each end supported, and secured so they cannot move or lift.
Ladder extension above landing
An access ladder must extend at least 1.0 m above the landing platform and be secured against displacement; climbing on braces is prohibited.
Free-standing height limit
An untied tube-and-coupler scaffold is generally limited to about four times its minimum base dimension in height before ties to the structure are required.
Coupler position rule
Couplers are fitted with the bolt on the outside and kept at least 150 mm from the end of a tube so the tube end is not crushed or split.
Inspection interval
A scaffold in use is inspected before first use, after alteration or bad weather, and at intervals not exceeding seven days, with each inspection recorded and tagged.
Handover certificate content
The handover certificate records the scaffold location, dimensions, load class, inspection date, inspector's name, and a statement that it is safe to use.
Dismantling sequence
Dismantle top down: remove platforms and guardrails first, then transoms, ledgers, ties, and finally standards, lowering components by rope and never dropping them.
Exclusion zone before dismantling
Before dismantling, barricade the area below, post warning signs, and confirm no one is working underneath, because falling tubes and couplers can be fatal.
Post-weather re-inspection
A scaffold struck by high wind, heavy rain, or a vehicle, or one that has been partly dismantled, is treated as new and must be re-inspected before further use.
Toolbox talk record
A toolbox talk record captures the topic, date, hazards discussed, and the names and signatures of attendees, and is kept on site for audit purposes.
Scaffold register purpose
The scaffold register links each scaffold to its tag number, erection date, inspection dates, and responsible person so its status can be verified at any time.
Crane hand signal stop
A raised hand with the palm facing the operator means stop; only the designated banksman should give signals when the operator's view is blocked.
Standard count formula
For a straight run, the number of standards equals the number of bays plus one, and ledger length per lift equals bay length multiplied by the number of bays.
Load per bay calculation
Divide the total mass of persons, tools, and materials by the number of bays, then compare the result with the rated class of 150, 250, or 450 kg per bay.