Forty-One Features, Nine That Anyone Uses

Aster's retail platform team has shipped 41 features in twelve months. Analytics show 9 are used weekly by more than 20% of customers, 19 are used by fewer than 2%, and the rest sit in between. The 220-item backlog was assembled at a roadshow where each regional director contributed their wish list; the product owner's top 20 items are all large (13-21 points) and none has customer evidence behind it. Meanwhile the checkout area has a persistent 6% payment failure rate on one card network, generating roughly 400 support tickets a month. Next quarter's capacity is about 300 points. The steering committee wants the feature-parity checklist completed 'before we invest in optimization'.

1. What should the product owner do with the 220-item backlog given this usage data?

Read the worked answer

Treat the usage data as evidence and let it reorder the backlog, rather than treating the backlog as a contract.

The portfolio is not delivering value: 19 of 41 features reach under 2% of customers. That is not a prioritisation problem to be fixed next quarter, it is the current cost of building on opinion. Two immediate consequences:

  • Prune and separate. Split the 220 items into three buckets: contractual/regulatory obligations (non-negotiable, ranked by date), items with an evidenced customer or revenue hypothesis, and unvalidated director requests. The third bucket does not get built until it produces evidence.
  • Slice the large items. All top-20 items at 13-21 points means the team cannot learn anything until late. Cut each into a first slice that can ship in a sprint and be measured.
  • Compare cost of delay, not size. The 6% payment failure costs revenue on every affected transaction plus ~400 tickets a month; put a number on both and compare it with the expected value of the next-largest feature. In most retail contexts the defect wins decisively, and having the arithmetic makes it a business decision rather than an engineering preference.

The parity checklist should be re-read as a list of candidate hypotheses, not a definition of done. Feature parity is a competitor's shape, not a customer's need.

2. How should the product owner respond to the steering committee's demand to finish the parity checklist first?

Read the worked answer

Reframe from outputs to outcomes, and make the trade-off explicit rather than argumentative.

The steering committee is not being unreasonable; they have been shown a checklist, not a value case. Give them one:

  1. Show the current return. Usage across the 41 shipped features - nine features above 20%, nineteen below 2% - with the capacity that went into the low-use group.
  2. Show the cost of the status quo. The 6% failure rate, 400 tickets a month, and the revenue at risk, expressed in the same units as the feature benefits.
  3. Offer two plans for the 300 points: parity-first versus defect-first, each with a forecast benefit and a forecast risk. Then recommend one.
  4. Ask for a decision, not permission. The product owner's accountability is to maximise value; the committee's is to accept the consequence of the choice. If they still choose parity, that is legitimate - but it gets recorded, with what it displaces.

Two supporting moves matter: invite a regional director to a sprint review to see usage against the wish list, and agree with the committee a small set of value measures the team will report each quarter. Requests that never face their own results keep coming back.

3. How can the team keep value visible sprint to sprint so this does not recur?

Read the worked answer

Instrument value before building, and review it on a predictable cadence.

  • Every backlog item carries a stated hypothesis before it is built: which customer, which behaviour should change, and what the team expects to see. An item that cannot state one is a candidate for deletion.
  • Instrument on release. Analytics for each new capability go out with it, not retrofitted after a year. The reason the current picture took twelve months to see is that no one was looking.
  • Review usage at the sprint review and in a monthly value review, alongside the demo. The sprint review is where stakeholders should confront actual behaviour rather than opinions about it.
  • Limit work in progress at the feature level. Nine used features out of 41 suggests too many things opened and not enough finished and taken up.
  • Keep the backlog short and fresh: detailed for two to three months, pruned quarterly. A 220-item backlog is a storage facility, and storage facilities hide the fact that nobody has decided anything.

One caution: 2% usage is not automatically failure - internal, seasonal or niche features can be valuable. The measure is the expected outcome stated in advance, not an arbitrary threshold applied after the fact.