PMI-CP study materials
PMI-CP study resources

PMI-CP cheat sheet

PMI-CP · Keep the key ideas within reach.

Quick reference

Construction Project Management Fundamentals

  • Construction lifecycle phases typically run initiation/feasibility, design, procurement, construction, commissioning and handover, then closeout; each phase ends with a gate or approval before the next begins.

  • The scope-schedule-cost triangle is constrained by quality and safety; an approved change to any one dimension requires impact assessment on the others before implementation.

  • A work breakdown structure is deliverable-oriented and follows the 100% rule: child elements must sum to the parent scope, with no scope omitted or added.

  • Earned value formulas: CV = EV - AC; SV = EV - PV; CPI = EV / AC; SPI = EV / PV; when future performance mirrors the past, EAC = BAC / CPI.

  • The critical path is the longest duration path through the network; it determines the minimum project duration and normally has zero total float.

  • Common delivery methods are design-bid-build, design-build, construction manager at risk, and integrated project delivery; each allocates design and construction risk differently.

  • Change control requires a documented request, cost and schedule impact assessment, authorized approval, and only then execution and baseline update.

  • Quality assurance focuses on process prevention, while quality control focuses on inspection and testing; an inspection and test plan defines hold points and acceptance criteria.

  • The hierarchy of controls for construction safety is elimination, substitution, engineering controls, administrative controls, and personal protective equipment, in that order of preference.

Quick reference

Stakeholder and Team Management

  • Power-interest grid decision rule: high power and high interest are managed closely; high power and low interest are kept satisfied; low power and high interest are kept informed; low power and low interest are monitored.

  • Communication channel count among n stakeholders equals n(n - 1) / 2; adding stakeholders increases complexity non-linearly.

  • RACI rule: exactly one person is accountable for each deliverable; responsible people do the work; consulted parties give input before decisions; informed parties receive updates after.

  • Tuckman team development stages are forming, storming, norming, performing, and adjourning; leadership style should shift as the team matures.

  • Conflict modes are collaborating, compromising, accommodating, competing, and avoiding; collaborating fits important issues when time and trust allow.

  • Escalation rule: resolve issues at the lowest competent level; escalate when the issue exceeds the local authority, resource, or scope threshold.

  • Organization structure affects project manager authority: functional is lowest, weak matrix is low, balanced matrix is moderate, strong matrix is high, and projectized is highest.

  • Interface management tracks design-to-construction and trade-to-trade dependencies in a matrix so gaps, clashes, and handoff delays are visible and owned.

  • A stakeholder engagement plan records stakeholder interests, current and desired engagement level, key messages, channels, frequency, and responsible owner.

Quick reference

Contract and Commercial Management

  • Lump-sum or fixed-price contracts place cost and quantity risk on the contractor, so complete and unambiguous drawings and specifications are essential.

  • Cost-plus contracts reimburse allowable actual cost plus an agreed fee; the owner bears cost risk and needs audit rights and cost controls.

  • Guaranteed maximum price contracts are cost-reimbursable with a ceiling; costs above the GMP belong to the contractor unless the owner approves a change.

  • Time and materials contracts pay agreed labor rates and material costs; they suit uncertain quantities, with the owner bearing quantity risk.

  • Risk allocation principle: assign each risk to the party best able to manage or absorb it, and state that allocation explicitly in the contract.

  • Progress payments are based on measured work; retention is withheld to protect the owner and released according to completion and defects-liability terms.

  • Bid, performance, and payment bonds are surety instruments, not insurance; performance bonds protect the owner if the contractor defaults.

  • Notice provisions are conditions precedent in many contracts; a claim may be time-barred if written notice is not given within the stated period.

  • A change order is a bilateral price-and-time agreement; a construction change directive is an owner-directed instruction to proceed before pricing is settled.

Quick reference

Risk and Schedule Management

  • Risk management process: plan risk management, identify risks, perform qualitative and quantitative analysis, plan responses, implement responses, and monitor and control.

  • Expected monetary value equals probability times impact; the sum of risk EMVs provides a basis for contingency reserves.

  • Qualitative analysis uses a probability-impact matrix or heat map; a risk score is commonly probability multiplied by impact.

  • Threat responses are avoid, transfer, mitigate, and accept; opportunity responses are exploit, share, enhance, and accept.

  • Monte Carlo simulation runs many probabilistic iterations of cost or schedule inputs to produce a distribution and confidence levels such as P50 or P80.

  • Critical path method uses a forward pass for early dates and a backward pass for late dates; total float equals late start minus early start or late finish minus early finish.

  • Crashing adds resources or overtime to critical-path activities to shorten duration, usually increasing cost and risk.

  • Fast tracking overlaps activities that would normally be sequential, increasing coordination, rework, and quality risk.

  • Resource leveling resolves over-allocation and may extend duration or change the critical path; resource smoothing stays within existing float.