WBS 100% rule
The work breakdown structure must include all project scope and nothing outside it; child elements sum to the parent's full scope.
Work package
The lowest-level WBS element, scoped so one person can estimate, schedule, and control its cost and duration.
Earned value management
A technique integrating scope, schedule, and cost by comparing budgeted value of work performed with actual cost and planned value.
Cost performance index
CPI equals earned value divided by actual cost. A CPI below 1.0 means work is costing more than budgeted.
Schedule performance index
SPI equals earned value divided by planned value. An SPI below 1.0 means work is behind the planned schedule.
Critical path
The longest duration path through the project network; it sets the shortest possible project duration and normally has zero total float.
Design-bid-build
A sequential delivery method where the owner contracts separately with designer then contractor; complete design precedes competitive bidding and construction.
Punch list
A closeout record of minor incomplete or defective work identified during inspection that must be corrected before final acceptance.
Power-interest grid
A stakeholder classification tool plotting influence against interest; quadrants guide engagement intensity from manage closely to monitor.
RACI matrix
A responsibility assignment chart: Responsible performs work, Accountable owns outcome, Consulted gives input, Informed receives updates.
Communication channels formula
The number of communication paths among n stakeholders equals n times n minus one, divided by two.
Tuckman team stages
A model of team development: forming, storming, norming, performing, and adjourning, each with distinct leadership needs.
Collaborating conflict mode
A conflict approach seeking a win-win solution through open discussion; useful when the issue is important and time permits.
Projectized organization
An organizational structure where staff report primarily to project managers; the project manager has high authority over resources and priorities.
Stakeholder engagement plan
A document defining stakeholders, their interests, engagement level, messages, channels, frequency, and responsible owners.
Interface management
Coordinating technical and schedule dependencies between trades, packages, or organizations to prevent gaps, clashes, and delay.
Lump-sum contract
A fixed-price agreement for defined scope; the contractor bears cost and quantity risk, so clear drawings and specifications are essential.
Cost-plus contract
The owner reimburses allowable actual costs plus an agreed fee; the owner bears cost risk and needs strong cost controls.
Guaranteed maximum price
A cost-reimbursable contract with a ceiling; costs above the GMP are the contractor's responsibility unless the owner approves a change.
Time and materials contract
Payment by agreed labor rates and material costs for work of uncertain quantity; the owner bears quantity risk.
Performance bond
A surety guarantee that compensates the owner if the contractor fails to perform; it is not the same as insurance.
Retention
A percentage withheld from progress payments to protect the owner until completion and correction of defects, released per contract terms.
Notice of claim
A contractual communication giving timely written notice of an event that may lead to additional cost or time; late notice may bar recovery.
Construction change directive
A written owner-directed instruction to proceed with changed work before price and time are agreed; pricing follows later.
Risk register
A living log of identified risks with owners, causes, impacts, probability, response plans, triggers, and status.
Expected monetary value
EMV equals probability times impact; summing EMVs across risks estimates contingency for the risk portfolio.
Monte Carlo simulation
A probabilistic technique running many random iterations of cost or schedule inputs to produce a distribution of possible outcomes.
Total float
The amount an activity can slip without delaying the project finish; calculated as late start minus early start.
Crashing
A schedule compression technique adding resources or overtime to critical-path activities, usually increasing cost and risk.
Fast tracking
A schedule compression technique overlapping activities that would normally be sequential, increasing coordination and rework risk.
Resource leveling
Adjusting activity start and finish dates to resolve resource over-allocation; it may change the critical path and extend duration.
Risk transfer
Shifting financial consequence of a risk to another party, such as through insurance, bonds, or contract clauses; the risk itself remains.