PMI-PBA: Evaluation: Did the Solution Solve the Problem?

PMI-PBA · Work through your exam, one topic at a time.

All guide sections

Evaluation: Did the Solution Solve the Problem?

Did the solution solve the problem?

Evaluation closes the loop opened in Needs Assessment. It assesses the delivered or partial solution against acceptance criteria and against the original business objectives, determines whether benefits are being realized, and recommends acceptance, corrective action, or retirement.

Know these concepts: solution acceptance and sign-off, user acceptance testing and defect triage, transition and readiness assessment (training, data, support, rollback), pilot and phased rollout, baseline versus post-implementation metrics, KPI and benefit realization, post-implementation review, lessons learned, residual defect and issue analysis, and the decision to maintain, replace, or retire a solution. Evaluation is not only technical verification; it explicitly checks whether the operating environment supports the intended use.

Hold this distinction: verification asks whether the solution was built to the requirements; validation asks whether it meets the stakeholder's actual need; evaluation asks whether it delivers the expected business outcome. Passing every test proves only the first.

Traps. Equating a green test dashboard with success. Measuring outputs (reports delivered, users trained) instead of outcomes (cycle time, error rate, revenue). Evaluating with no pre-project baseline, so no comparison is possible. Stopping at go-live and skipping the post-implementation review.

Rule of thumb: every objective written in Needs Assessment should reappear in Evaluation with a metric, a baseline value, a target, and a measurement date.

Worked example: a CRM deployment passes all 400 test cases on schedule, yet sales cycle time is unchanged. Evaluation finds representatives still keep spreadsheets because the mobile view is unusable in the field. The recommendation is not "project failed" but a corrective release plus follow-up measurement, because the business objective, not the test suite, defines success.