PMPA · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Project Planning and Scope Management & Project Fundamentals and the Project Environment

  • Distinguish project, program, and portfolio governance, and map each PMPA domain to the lifecycle phase where it carries the most weight.

  • Build a scope baseline by decomposing a sample deliverable into a WBS three levels deep with a WBS dictionary entry for every work package.

  • Write scope statements that pass the test of being measurable and exclusive, then rewrite two weak examples to meet that standard.

  • Explain how requirements traceability links business needs to deliverables and acceptance criteria, using a worked example.

Your checkpoint

A one-page scope package for a realistic project: scope statement, three-level WBS, WBS dictionary for at least eight work packages, and a requirements traceability matrix covering at least ten requirements.

Week 2

Schedule and Cost Management

  • Sequence activities using finish-to-start, start-to-start, finish-to-finish, and start-to-finish logic, and justify each dependency as mandatory or discretionary.

  • Estimate durations with three-point (PERT) analysis and compute the expected duration and standard deviation for at least five activities.

  • Perform forward and backward pass on a 15-activity network to derive early start, early finish, late start, late finish, and total float.

  • Identify the critical path and explain how float changes when a predecessor slips by a stated number of days.

  • Distinguish analogous, parametric, bottom-up, and three-point cost estimating and state when each is defensible.

Your checkpoint

A solved 15-activity schedule network showing the full forward/backward pass, the critical path, total and free float per activity, and a cost estimate built three ways with a written comparison of accuracy and effort.

Week 3

Schedule and Cost Management & Risk and Procurement Management

  • Compute cost and schedule variances, CPI, SPI, TCPI, and EAC using earned value formulas on a mid-project dataset.

  • Interpret whether a project is ahead or behind and over or under budget when SPI and CPI disagree, and recommend a corrective action.

  • Build a risk register with probability and impact ratings, then rank risks using expected monetary value and a probability-impact matrix.

  • Select a response strategy (avoid, mitigate, transfer, accept, escalate for threats; exploit, enhance, share, accept for opportunities) for each of six identified risks.

  • Explain how contingency and management reserves differ and which one the cost baseline includes.

Your checkpoint

A combined performance and risk report: earned value table with variance analysis and forecast, plus a ten-risk register with EMV ranking, chosen response strategies, and a reserve justification.

Week 4

Project Initiation and Stakeholder Engagement & Quality, Resource, and Communications Management

  • Draft a stakeholder register and power/interest grid, then assign an engagement strategy to each quadrant.

  • Write a communications management plan that specifies audience, message, channel, frequency, and owner for at least six stakeholder groups.

  • Define quality metrics with acceptance thresholds and design a quality control check that would detect a defect before delivery.

  • Distinguish cost of prevention, appraisal, and failure, and classify five sample quality activities accordingly.

  • Explain how resource calendars, RACI assignments, and team ground rules reduce conflict before it starts.

Your checkpoint

A stakeholder and communications package: register with at least ten stakeholders, power/interest grid, engagement plan, six-row communications matrix, and a quality plan with three metrics, thresholds, and a control check.

Week 5

Risk and Procurement Management & Project Fundamentals and the Project Environment

  • Compare fixed-price, cost-reimbursable, and time-and-materials contracts and match each to a scenario with defined or undefined scope.

  • Identify the procurement documents, selection criteria, and make-or-buy analysis steps that precede a contract award.

  • Explain how the project charter authorizes the project and how the project manager's authority derives from it and from the organizational structure.

  • Contrast functional, matrix, and projectized structures by their effect on resource control, reporting lines, and conflict frequency.

Your checkpoint

A procurement and governance brief: make-or-buy analysis, contract type recommendation with rationale, draft selection criteria, and a comparison table of three organizational structures applied to the same project.

Week 6

Project Execution, Monitoring, and Control & Quality, Resource, and Communications Management

  • Choose the correct control technique (inspection, variance analysis, trend analysis, or earned value) for five monitoring scenarios and justify each choice.

  • Write change requests and assess their impact on scope, schedule, cost, and quality before approval, including who has authority to approve.

  • Describe how to run a team performance assessment and a conflict-resolution conversation using a stated model of conflict handling.

  • Explain configuration management and how it prevents unauthorized changes to baselined deliverables.

  • Diagnose three project health problems from performance data and propose specific corrective actions.

Your checkpoint

A monitoring and control playbook: five-scenario technique selection table, a completed change request with impact analysis and approval path, and three written diagnoses with corrective actions.

Week 7

Project Closure and Professional Responsibility & Project Execution, Monitoring, and Control

  • List the closure activities for scope verification, contract closure, and administrative closure and place them in the correct order.

  • Draft a lessons-learned structure that captures what worked, what failed, and what changes the organization should adopt.

  • Explain how benefits are measured after handover and who owns that measurement.

  • Apply the professional responsibility obligations of accuracy, confidentiality, conflict-of-interest disclosure, and honest reporting to four short scenarios.

  • Identify the ethical response when asked to compress a schedule in a way that hides a known quality risk.

Your checkpoint

A closure and ethics pack: closure checklist in sequence, lessons-learned template with three filled examples, and four scenario responses each citing the obligation and the action taken.

Week 8

Project Fundamentals and the Project Environment & Project Initiation and Stakeholder Engagement & Project Planning and Scope Management & Schedule and Cost Management & Quality, Resource, and Communications Management & Risk and Procurement Management & Project Execution, Monitoring, and Control & Project Closure and Professional Responsibility

  • Complete two full-length timed practice exams and log every missed question by domain and error type (knowledge gap, misread, or calculation error).

  • Re-study the two weakest domains using the error log, focusing on the specific concepts missed rather than whole domains.

  • Rehearse the earned value and network-diagram calculations until each is completed accurately under time pressure.

  • Review formula sheet, key definitions, and process sequences for final recall.

Your checkpoint

An error log from two timed practice exams with domain-level scores, root causes per miss, a targeted re-study list, and a final one-page formula and definitions sheet.

Milestones

Week 2: Complete a 15-activity network forward/backward pass and identify the critical path with no reference material, scoring at least 80% on a self-made calculation check.

Week 4: Score at least 70% on a mixed 40-question set drawn from domains 1 through 5, with earned value questions at 80% or better.

Week 6: Score at least 75% on a full-length timed practice exam, with no domain below 60%.

Week 8: Score at least 80% on a second full-length timed practice exam, with every domain at or above 70% and all calculation items correct.