PRINCE2 Practitioner cheat sheet

PRINCE2 Practitioner · Keep the key ideas within reach.

Quick reference

Business Case

  • The business case is developed at the start of the project, updated at each end stage and at each exception, and confirmed as still viable at each end stage boundary.

  • Business case contents: reasons, business options (do nothing, do minimum, do something), expected benefits, expected dis-benefits, timescale, costs, investment appraisal, major risks.

  • The do-nothing option must always be evaluated and used as the baseline against which the other options are compared.

  • Benefits are expressed in measurable terms in the business case; the senior user is accountable for realising them, and benefit reviews are planned after project closure.

  • Outputs, outcomes and benefits: outputs are produced by the project, outcomes are the result of using the outputs, benefits are the measurable improvement resulting from outcomes.

  • The executive owns the business case and is accountable for it; the business case is part of the PID and is reviewed by the project board at every end stage.

  • The business case is used to decide whether to start, continue or stop the project; if it is no longer viable the project should be stopped or changed.

  • Investment appraisal compares the business options using techniques such as whole-life costs, net benefits, payback period, return on investment and discounted cash flow.

Quick reference

Organization

  • The project board has three roles: executive (owns the business case and is ultimately accountable), senior user (specifies needs and benefits), and senior supplier (provides resources and technical authority).

  • The executive is responsible for the project's single point of accountability and appoints the other project board members; the executive is supported by the project manager for day-to-day management.

  • Project assurance is a project board responsibility and must be independent of the project manager, team manager and project support.

  • The project manager manages the project on a day-to-day basis, prepares plans and reports, and escalates to the project board via exception reports.

  • The team manager manages the work of a team and may be internal or external; the team manager reports to the project manager and not to the project board.

  • Project support provides administrative services such as configuration management, document control and planning support; the role may be combined with other roles.

  • The four levels of organisation in a project: corporate or programme management, project board, project manager, and team manager/team members.

  • A project is a temporary organisation created to deliver one or more business products according to an agreed business case; it is not business as usual.

Quick reference

Quality

  • Quality management in PRINCE2 is based on a quality management system, quality planning, quality control and quality assurance; the project board approves the quality management approach.

  • The quality management approach describes the project's quality standards, procedures, techniques and responsibilities, and is part of the PID.

  • The quality register records all quality activities, including planned reviews and tests, and is updated as quality activities are completed.

  • Product descriptions are created for each product and include purpose, composition, derivation, quality criteria and quality method, plus the quality tolerance.

  • Quality criteria must be measurable; quality tolerance defines the acceptable range for each quality criterion.

  • Quality control comprises quality reviews, quality inspections and testing; a quality review is a structured review of a product against its quality criteria.

  • A quality review has defined roles: chair, presenter, reviewer and administrator; the presenter is usually the author of the product.

  • The quality review process: plan the review, prepare for the review, conduct the review, and follow up on actions and approval.

Quick reference

Plans

  • PRINCE2 has three levels of plan: project plan, stage plans, and team plans; exception plans are created when tolerances are forecast to be exceeded.

  • The project plan shows the major products, activities and resources for the whole project; it is the baseline against which progress is measured.

  • Stage plans cover the work of a single management stage and include the products, activities, resources and tolerances for that stage.

  • Team plans are optional and are prepared by the team manager for the work allocated to the team.

  • Planning steps: design the plan, define and analyse products, identify activities and dependencies, prepare estimates, prepare the schedule, analyse risks, and document the plan.

  • Product-based planning: write the project product description, create the product breakdown structure, write product descriptions, and create the product flow diagram.

  • Estimating techniques include analogous estimating, parametric estimating, three-point estimating and effort-based estimating; estimates should be recorded with their basis and assumptions.

  • Tolerances in plans are time, cost, scope, quality, risk and benefit; the project board sets project-level tolerances, and the project manager sets stage-level tolerances.

Quick reference

Risk

  • Risk is an uncertain event that, if it occurs, will have an effect on the achievement of objectives; risk management is a continual activity throughout the project.

  • Risk management approach describes the risk procedures, techniques, standards and responsibilities; it is part of the PID.

  • The risk management procedure: identify, assess (estimate and evaluate), plan, implement, and communicate.

  • Risk identification considers threats and opportunities; the risk register records each risk's description, cause, effect, owner, probability, impact and proximity.

  • Risk evaluation compares estimated risk against tolerances and prioritises risks for action; risk responses include avoid, reduce, transfer, accept, share, exploit and enhance.

  • The risk owner is accountable for managing a specific risk; the risk actionee implements the response, and the two roles may be combined.

  • The risk budget is a sum of money set aside by the project board to cover the cost of risk responses and is held by the project manager.

  • A risk can be escalated to the project board via an exception report if its impact exceeds the project manager's tolerances.

Quick reference

Change

  • PRINCE2 change control covers changes to baselined products, requests for change, and the management of issues and off-specifications.

  • The change control approach defines how changes are identified, assessed, approved and implemented, and who has authority to approve them; it is part of the PID.

  • The change control procedure: capture, assess, approve or reject, and implement; the change is recorded in the issue register and the change log.

  • The issue register records all issues, including requests for change, off-specifications and problems/concerns; the change log records the status of each change.

  • An off-specification is a product that does not meet its quality criteria; it must be reported as an issue and approved by the project board before being accepted.

  • A request for change is a proposal to change a baselined product, and it must be assessed for impact on time, cost, quality, scope, risk and benefits before approval.

  • Change authority is the person or group delegated by the project board to approve changes; the project board sets the change budget and the authority's limits.

  • Configuration management comprises planning, identification, control, status accounting and verification; the configuration item record tracks each product's version and status.

Quick reference

Progress

  • Progress control compares progress against the plan using the six tolerances: time, cost, scope, quality, risk and benefit.

  • Tolerance is the permissible deviation from the plan without escalating to the next management level; exceeding a tolerance requires an exception report.

  • Progress is reported through checkpoint reports (from team manager to project manager), highlight reports (from project manager to project board) and end stage reports.

  • A highlight report is produced at intervals defined in the communication management approach and covers status, progress, issues, risks and forecast.

  • An exception report is produced when a tolerance is forecast to be exceeded; it includes cause, impact, options and a recommendation, and may lead to an exception plan.

  • An exception plan replaces a stage plan or the project plan when the project board approves it after an exception; it is prepared by the project manager.

  • The end stage assessment is held at the end of each stage, where the project board reviews the end stage report and approves the next stage plan.

  • Lessons are captured in the lessons log throughout the project and reviewed at each end stage and at project closure; the lessons report is produced at the end of the project.