32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Business case owner
The executive is accountable for the business case. It is developed at the start, updated at each end stage and exception, and confirmed as viable at each end stage.
Do-nothing option
A business option that must always be evaluated in the business case and used as the baseline against which the other options are compared.
Benefits versus outcomes
Outputs are produced by the project; outcomes result from using the outputs; benefits are the measurable improvements resulting from the outcomes, expressed in measurable terms.
Investment appraisal techniques
Methods used to compare business options in the business case, such as whole-life costs, net benefits, payback period, return on investment and discounted cash flow.
Executive role
The single point of accountability for the project, owner of the business case, and chair of the project board; supported by the project manager for day-to-day management.
Senior user role
A project board role accountable for specifying the needs of users and for realising the benefits; represents the users' interests and validates the delivered products.
Senior supplier role
A project board role providing resources and technical authority, accountable for the quality of products delivered by the supplier and for feasibility of the plan.
Project assurance
A project board responsibility to monitor the project independently of the project manager, team manager and project support, covering business, user and supplier assurance.
Team manager role
Manages the work of a team, reports to the project manager rather than the project board, and may be internal or external to the organisation.
Quality management approach
Part of the PID describing the project's quality standards, procedures, techniques and responsibilities, approved by the project board and used for quality planning and control.
Product description contents
A document for each product containing purpose, composition, derivation, quality criteria, quality method and quality tolerance, used to plan and control quality.
Quality review roles
Chair, presenter, reviewer and administrator. The presenter is usually the product's author; the review follows plan, prepare, conduct and follow-up steps.
Quality register
A register recording all planned quality activities, such as reviews and tests, and their status, updated as quality activities are completed.
Quality tolerance
The acceptable range for each quality criterion, defined in the product description, allowing measurable assessment of whether a product meets its criteria.
Three plan levels
Project plan, stage plans and team plans; exception plans are created when tolerances are forecast to be exceeded and replace the affected plan.
Product-based planning steps
Write the project product description, create the product breakdown structure, write product descriptions, and create the product flow diagram showing dependencies.
Project plan purpose
Shows the major products, activities and resources for the whole project and provides the baseline against which progress is measured and reported.
Estimation techniques
Analogous, parametric, three-point and effort-based estimating; each estimate should record its basis and assumptions so it can be reviewed and updated.
Six plan tolerances
Time, cost, scope, quality, risk and benefit. The project board sets project-level tolerances and the project manager sets stage-level tolerances.
Risk management procedure
Identify, assess (estimate and evaluate), plan, implement and communicate; risk management is a continual activity across the whole project lifecycle.
Risk owner versus actionee
The risk owner is accountable for managing a specific risk; the risk actionee implements the agreed response. The two roles may be combined.
Risk response types
For threats: avoid, reduce, transfer and accept. For opportunities: exploit, enhance, share and accept. Responses are recorded in the risk register.
Risk budget
A sum of money set aside by the project board to cover the cost of risk responses, held and used by the project manager within agreed tolerances.
Risk register contents
Records each risk's description, cause, effect, owner, probability, impact, proximity and status, and is reviewed throughout the project.
Change control procedure
Capture the change, assess its impact, approve or reject it, and implement it; requests are recorded in the issue register and tracked in the change log.
Off-specification
A product that does not meet its quality criteria; it must be reported as an issue and approved by the project board before being accepted.
Configuration management elements
Planning, identification, control, status accounting and verification; configuration item records track each product's version and status.
Change authority
A person or group delegated by the project board to approve changes within limits set by the change budget and the change control approach.
Tolerance and exception
Tolerance is the permissible deviation from plan without escalation; exceeding it requires an exception report and possibly an exception plan.
Report types
Checkpoint reports from team manager to project manager, highlight reports from project manager to project board, and end stage reports at stage boundaries.
End stage assessment
Held at the end of each stage, where the project board reviews the end stage report and approves the next stage plan before work continues.
Lessons log purpose
Captures lessons throughout the project; lessons are reviewed at each end stage and a lessons report is produced at project closure.