Electricity at Work Regulations 1989

Statutory regulations in Great Britain placing duties on those responsible for electrical systems at work to keep them safe, properly maintained and worked on by competent people. Breaching them is a criminal offence.

Related: BS 7671 (IET Wiring Regulations), Competent person
BS 7671 (IET Wiring Regulations)

The British Standard covering the design, erection, inspection and testing of electrical installations. Following it is the accepted way of showing that legal duties, such as those in the Electricity at Work Regulations, have been met.

Related: Electricity at Work Regulations 1989, Guidance Note 3 (GN3)
Guidance Note 3 (GN3)

An IET publication explaining in detail how to inspect, test and certify installations to BS 7671. It is the standard reference for inspection and testing practice and for completing certificates and reports.

Related: BS 7671 (IET Wiring Regulations)
Part P

The Building Regulations requirement, applying in England and Wales, that electrical installation work in dwellings is safe. Notifiable work must be certified by a registered competent person or by building control.

Related: Competent person
Competent person

Someone with enough technical knowledge, skill and experience to carry out the work safely and prevent danger or injury. Their competence must be appropriate to the particular task being done.

Related: Safe isolation
Safe isolation

A formal sequence of identifying the circuit, switching off, isolating, locking off and proving dead, then confirming the correct circuit was isolated. It protects the worker from electric shock and arc flash.

Related: Prove dead, Lock-off device and caution notice
Prove dead

Using a proven voltage indicator to confirm zero voltage between all live conductors, and between each live conductor and earth, immediately before touching the isolated conductors.

Related: Proving unit, Safe isolation
Proving unit

A known voltage source used to check that a voltage indicator is working correctly before and after proving a circuit dead. Some indicators have a built-in self-test instead.

Related: Prove dead
Lock-off device and caution notice

A lock and warning label fitted to an isolator or protective device so that an isolated circuit cannot be re-energised by someone else while work is in progress.

Related: Safe isolation, Permit to work
Permit to work

A formal written document authorising specific work under stated safety conditions. It is used for high-risk tasks such as live working or work on complex or hazardous installations.

Related: Safe isolation
Periodic inspection and testing

Scheduled inspection and testing of an existing installation at intervals during its life, to assess its condition and compliance with BS 7671. The findings are recorded in an Electrical Installation Condition Report.

Related: Electrical Installation Condition Report (EICR), Sampling
Extent and limitations

The agreed description of which parts of an installation will be inspected and tested and what will be left out, recorded so readers know exactly what the report does and does not cover.

Related: Sampling, Agreed scope of report
Sampling

Inspecting and testing a representative selection of the installation rather than every item, chosen to give reasonable confidence in the condition of the whole. Any parts not sampled must be recorded as limitations.

Related: Extent and limitations
Visual inspection

A careful examination of the installation, without dismantling beyond what is needed, to find damage, deterioration, overheating, incorrect identification, poor workmanship and departures from BS 7671.

Related: Deterioration, Non-compliance
Non-compliance

A departure from BS 7671 or another applicable standard found during inspection. It must be recorded as an observation and classified according to the risk it presents.

Related: Classification code C2, Deterioration
Deterioration

The decline in condition of installation parts through ageing, wear, corrosion, heat or damage, such as cracked insulation or loose connections, which increases the chance of fault or danger.

Related: Visual inspection
Initial verification

Inspection and testing of a new installation, or of new work, carried out before it is put into service, to confirm that it matches its design and complies with BS 7671.

Related: Electrical Installation Certificate (EIC), Periodic inspection and testing
Electrical Installation Certificate (EIC)

The certificate issued after initial verification of a new installation or major alteration, declaring that the work has been designed, constructed, inspected and tested in accordance with BS 7671.

Related: Initial verification, Minor Electrical Installation Works Certificate
Minor Electrical Installation Works Certificate

A certificate used for small additions or alterations that do not add a new circuit, covering the design, construction, inspection and testing of that particular piece of work.

Related: Electrical Installation Certificate (EIC)
Agreed scope of report

The purpose and coverage of the report, agreed with the client before work starts, including the extent, limitations, sampling and any special requirements such as a change of occupancy.

Related: Extent and limitations, Sampling
Continuity testing

Measuring the resistance of protective, bonding and circuit conductors to show they are continuous and correctly connected. Results are compared with expected values calculated from conductor size and length.

Related: R1+R2, Insulation resistance test
R1+R2

The measured resistance of a circuit's line conductor plus its circuit protective conductor, taken with the supply isolated. It is added to the external loop impedance to give the earth fault loop impedance.

Related: Continuity testing, Earth fault loop impedance (Zs)
Ring final circuit test

A test of a ring final circuit using end-to-end resistance readings of line, neutral and protective conductors, then a cross-connected reading. The cross-connected value should be roughly a quarter of the end-to-end line-to-neutral value.

Related: Polarity test
Polarity test

Confirming that line, neutral and protective conductors are connected to the correct terminals throughout, so that switches and single-pole devices are in the line conductor and earthing remains effective.

Related: Ring final circuit test
Insulation resistance test

A dead test applying a DC voltage, usually 500 V for 230/400 V circuits, between live conductors and earth and between live conductors, to confirm the insulation is sound. Results must meet the minimum values in BS 7671.

Related: Continuity testing
Earth fault loop impedance (Zs)

The total impedance of the path taken by fault current from the point of fault, through the protective conductor and back to the supply source. It determines whether the protective device disconnects within the required time.

Related: External earth fault loop impedance (Ze), Prospective fault current (PFC)
External earth fault loop impedance (Ze)

The impedance of the fault path outside the installation, measured at the origin with the main switch off. It is used together with a circuit's R1+R2 to calculate Zs.

Related: Earth fault loop impedance (Zs)
Prospective fault current (PFC)

The current that would flow if a short circuit or earth fault occurred at a particular point, measured or calculated at the origin. It is used to check that protective devices and equipment can withstand it.

Related: Earth fault loop impedance (Zs)
RCD operating time test

Using an RCD tester to confirm that a residual current device trips within the required time at its rated residual operating current and at five times that current.

Related: Functional testing
Functional testing

Operating switches, isolators, RCD test buttons, interlocks, emergency lighting and similar equipment to confirm they work as intended as part of the inspection and testing process.

Related: RCD operating time test
Classification code C1

The observation code for a danger present with risk of injury, where immediate remedial action is required and the installation, or the affected part, must be made safe or isolated straight away.

Related: Classification code C2, Satisfactory or unsatisfactory
Classification code C2

The observation code for a potentially dangerous condition: a defect that could become dangerous and that needs urgent remedial action.

Related: Classification code C1, Classification code C3
Classification code C3

The observation code for an improvement recommended: a departure or non-compliance that is not dangerous but would improve safety if it were put right.

Related: Classification code C2
FI (further investigation)

A code used where a problem has been found but cannot be fully assessed without further investigation, for example where part of the installation is hidden or badly deteriorated.

Related: Classification code C2
Observations

The findings from the inspection and testing, each written up with its location and given a classification code. They form the main body of the condition report and drive the recommendations.

Related: Classification code C2, Electrical Installation Condition Report (EICR)
Electrical Installation Condition Report (EICR)

The report produced after a periodic inspection, recording the extent, limitations, test results and observations, with an overall assessment and the date by which the next inspection is due.

Related: Periodic inspection and testing, Satisfactory or unsatisfactory
Satisfactory or unsatisfactory

The overall assessment on a condition report: satisfactory where no C1 or C2 observations are recorded, and unsatisfactory where any C1 or C2, or an unresolved further investigation, is present.

Related: Classification code C1, Classification code C2
Schedule of Test Results

The form, part of a certificate or condition report, on which measured results such as continuity, insulation resistance, Zs, prospective fault current and RCD operating times are recorded circuit by circuit.

Related: Electrical Installation Condition Report (EICR)