- Electricity at Work Regulations 1989
- Statutory regulations applying to electrical systems at work in Great Britain; they require competent persons, safe systems of work and precautions for work on or near live conductors.
- BS 7671 non-statutory status
- BS 7671 is not law; compliance is accepted as evidence that duties under the Health and Safety at Work etc. Act 1974 and the Electricity at Work Regulations 1989 have been met.
- Part P of Building Regulations
- Applies to fixed electrical installations in dwellings in England and Wales; notifiable work must be certified by a registered competent person or inspected by building control.
- Chapter 61 initial verification
- BS 7671 Chapter 61 requires inspection and testing of new work during erection and on completion, before the installation is put into service.
- Guidance Note 3
- IET Guidance Note 3: Inspection and Testing is the non-statutory companion to BS 7671 Part 6, covering test methods, expected values, sampling and forms.
- Three-point proving procedure
- Prove the voltage indicator on a proving unit, test all live conductors at the point of work, then prove the indicator again to confirm it still works.
- GS38 voltage detector requirements
- HSE Guidance Note GS38 specifies two-pole detectors with fused leads, finger barriers, no more than 4 mm exposed tip, rated for the installation's overvoltage category.
- Supply characteristics before testing
- Establish the earthing system, nominal voltage, external loop impedance or electrode resistance, and prospective fault current before starting inspection and testing.
- Instrument calibration and proving
- Test instruments need a current calibration certificate, typically within 12 months, and should be proved against a known source before and after use.
- EAWR Regulation 14 live work
- Work on or near live conductors is permitted only where it is unreasonable in all circumstances to work dead and suitable precautions are taken.
- Overvoltage category of instruments
- Instruments and leads must be rated for the location, for example CAT III at distribution boards and CAT IV at the origin of an installation.
- Purpose of initial verification
- Initial verification confirms by inspection and testing that an installation complies with the design and BS 7671 before it is energised for use.
- Schedule of Inspections
- A BS 7671 Appendix 6 form listing the items to be visually inspected, ticked where satisfactory, with any departures or limitations recorded.
- Ring final circuit R1+R2
- After cross-connecting line and protective conductor of opposite legs, the resistance measured at each socket should be about one quarter of r1 plus r2.
- Nulling continuity test leads
- The resistance of the test leads is measured and either nulled on the instrument or subtracted from readings so results are not falsely high.
- Insulation resistance pass values
- For circuits up to 500 V apply 500 V DC with a minimum of 1 MΩ; for SELV and PELV apply 250 V DC with a minimum of 0.5 MΩ.
- Equipment disconnected for IR test
- Dimmers, electronic devices, surge protective devices and similar equipment are removed or isolated before insulation resistance testing to prevent damage and false readings.
- Investigating low insulation resistance
- A result below 1 MΩ fails BS 7671; subdivide the circuit and retest to locate moisture, damaged insulation or a connected load causing the low reading.
- 80% rule for maximum Zs
- Tabulated maximum Zs values assume conductors at 70 °C; measured values at ambient temperature are compared with 80% of the tabulated figure.
- Fall of potential electrode test
- Two stakes are driven in line with the electrode; the potential stake sits at 62% of the distance to the current stake, and readings are repeated at moved positions.
- TT system maximum RA
- Earth electrode resistance must not exceed 50 V divided by the RCD rated residual current: 1667 Ω for 30 mA and 500 Ω for 100 mA.
- RCD five times test
- At five times rated residual current a general RCD to BS EN 61008 or 61009 must operate within 40 ms; the test is repeated at 0° and 180°.
- RCD half rated current test
- Applying half the rated residual operating current should not operate the RCD; operation at this level indicates an over-sensitive or faulty device.
- Type S RCD operating times
- Time-delayed Type S RCDs must operate between 130 ms and 500 ms at rated residual current, and between 50 ms and 150 ms at five times that current.
- EICR observation codes
- C1 means danger present and immediate action required; C2 potentially dangerous and urgent action needed; C3 improvement recommended; FI further investigation required.
- Satisfactory condition report
- An EICR is satisfactory only when it records no C1, C2 or FI observations; any one of these makes the report unsatisfactory.
- Minimum periodic sampling
- Periodic inspection typically samples at least 10% of circuits, including all circuits showing defects, and the sample is increased where the installation is poor.
- Minor Electrical Installation Works Certificate
- Used for minor work that does not extend or alter a circuit; it records the work, test results and the signatures of the designer, installer and tester.
- EIC declaration signatures
- An Electrical Installation Certificate requires declarations from the designer, constructor and the person responsible for inspection and testing, who may be the same competent person.
- High Zs interpretation
- A measured Zs above the 80% tabulated maximum suggests a loose termination, long circuit, undersized protective conductor or high external impedance; investigate before condemning.
- Communicating a C1 defect
- A C1 observation means danger is present; the client must be told immediately and the affected part isolated or otherwise made safe without delay.
- Effect of limitations on conclusion
- Limitations that prevent inspection of part of the installation must be recorded, and the report must state whether the overall conclusion is affected.