C&G 2391-52 study materials
C&G 2391-52 study resources

C&G 2391-52 study plan

C&G 2391-52 · Give each week a clear focus.

8 weeks · About 6 hours per week

Week 1

Statutory and non-statutory requirements, BS 7671 and associated guidance & Safe isolation, preparation for inspection and testing, safe working practices

  • Map every stage of the verification and periodic process to its legal and standard source (HSWA, EAWR, BS 7671 Parts 6 and 7, associated guidance notes) in a single reference table you write yourself

  • Write out and rehearse a full safe isolation procedure from origin to final circuit, including identifying the point of isolation, locking off, proving the voltage indicator on a known source before and after the test, and applying a warning notice

  • List the documents and information you must obtain and check before starting work (previous certificates, schedules, extent and limitations, authorisation to isolate) and state who authorises isolation and re-energisation

  • Distinguish, with three worked examples, what falls inside initial verification versus periodic inspection, and where the boundary of a periodic scope can legitimately stop

Your checkpoint

A one-page safe isolation procedure plus a completed isolation record and tester-proving log for a simulated single-phase board change

Week 2

Inspection (initial verification and periodic inspection)

  • Work through every heading of the schedule of inspections and state the specific checks required under each for a domestic consumer unit replacement

  • Order the inspection activities so that all dead inspection is completed before any live testing begins, and justify each ordering decision

  • Identify the 10 most common non-compliances found on a domestic installation and state where each is cited in BS 7671

  • Decide, for eight given site findings, whether each is a departure, a non-compliance, or acceptable, and write the reason in one sentence

Your checkpoint

A completed schedule of inspections for a sample installation with every item marked inspected/not applicable and a written note on each limitation

Week 3

Continuity and resistance testing of protective and bonding conductors & Insulation resistance testing

  • Carry out and record the continuity tests: protective conductor continuity, main and supplementary protective bonding continuity, ring final circuit continuity (all three steps), and radial r1 and r2

  • Calculate expected R1+R2 from conductor resistance tables before measuring, then compare the calculated and measured values and explain any difference greater than 0.05 ohm

  • Perform insulation resistance tests at 500 V DC on a whole installation and on a single circuit, applying the correct procedure where SPDs, surge protection or voltage-sensitive equipment are present

  • Judge insulation resistance results against the 1 megohm minimum and the permitted reduced test voltage case, recording test voltage, duration and any disconnections

Your checkpoint

A completed continuity and insulation resistance section of a schedule of test results for a sample installation, with all expected values calculated and shown alongside measured values

Week 4

Earth fault loop impedance and earth electrode resistance testing & RCD testing and functional verification

  • Determine earth fault loop impedance by direct measurement and by calculation from Ze plus R1+R2, and reconcile the two figures

  • Measure or establish Ze and earth electrode resistance, selecting the correct method (three-point, clamp, or calculated) for the electrode arrangement given

  • Verify measured or calculated Zs against the disconnection times in the relevant tables for the protective device fitted, including the 0.8 rule for conductor operating temperature

  • Carry out a full RCD test sequence on a 30 mA Type A device: half rated current, rated current, five times rated current, and the correct test for DC sensitivity, then record every operating time and pass/fail verdict

  • Confirm the functional test of the RCD test button and state what it does and does not prove

Your checkpoint

A results table comparing measured and calculated Zs for six circuits, plus a complete RCD test schedule showing operating times at each multiplier with pass/fail against BS 7671 limits

Week 5

Periodic inspection, sampling and condition reporting (EICR) & Inspection (initial verification and periodic inspection)

  • Justify a sample size for a periodic inspection of a given multi-board premises using the applicable sampling guidance, and state what you would do if the sample reveals a widespread defect

  • Write an extent of works and limitations statement for a periodic inspection where no previous records exist and some areas are inaccessible

  • Assign C1, C2, C3 or FI to fifteen given observations with a written justification for each code

  • Re-run the schedule of inspections against an existing installation with no prior certification and note where the checks differ from a new installation

Your checkpoint

A complete draft condition report for a sample premises, including extent and limitations, summary of condition, and a justified coded observations list

Week 6

Certification, schedules and reporting documentation & Interpretation of test results, defect classification and client communication

  • Complete a full electrical installation certificate, a minor works certificate and a schedule of test results for a sample job, with no section left blank or marked not applicable without reason

  • Cross-check recorded results against expected values and flag every anomaly that would require re-testing before the certificate is issued

  • Classify ten supplied observations into codes and rank them into a prioritised remedial action list with indicative timescales

  • Write a plain-English client letter explaining a C2 observation, the danger it presents, and the required remedial action, without jargon

Your checkpoint

A completed electrical installation certificate and schedule of test results for one sample job, plus a one-page client-facing summary letter

Week 7

Continuity and resistance testing of protective and bonding conductors & Earth fault loop impedance and earth electrode resistance testing & RCD testing and functional verification & Periodic inspection, sampling and condition reporting (EICR)

  • Sit a full-length timed mock covering the four highest-weighted testing and reporting domains and mark it against the answers

  • Re-study every question missed, writing the correct reasoning in your own words rather than copying the answer

  • Re-perform, on the rig or in simulation, the two test procedures you scored lowest on in the mock

  • Build a personal one-page formula and limits sheet for Zs, RCD times and insulation resistance values and check it against source text

Your checkpoint

A marked mock paper scoring at least 80 percent, plus a written remediation log listing every missed question with the corrected reasoning

Week 8

Statutory and non-statutory requirements, BS 7671 and associated guidance & Safe isolation, preparation for inspection and testing, safe working practices & Certification, schedules and reporting documentation & Interpretation of test results, defect classification and client communication

  • Sit a second full-length timed mock under exam conditions and compare the score profile against week 7

  • Rehearse the safe isolation sequence and the inspection-before-test sequence from memory, out loud, without prompts

  • Complete two full certificates from blank templates within a strict time limit

  • List your five weakest remaining topics and write a one-paragraph accurate summary of each from memory

Your checkpoint

A final mock scoring at least 85 percent and two timed, fully completed certificates produced without reference material

Milestones

Week 2: You can state the legal and BS 7671 basis for each test you perform, and you have produced a signed-off safe isolation record and a complete schedule of inspections for a sample installation

Week 4: You have produced complete continuity, insulation resistance, loop impedance and RCD result sheets, and you can justify every measured value against a calculated expectation without notes

Week 6: You have issued a complete condition report with correctly coded observations and a full installation certificate, and a mock paper on domains 1 to 10 scores at least 75 percent

Week 8: Two timed full-length mocks both score at least 85 percent, and you can complete an installation certificate and a condition report from blank templates within the exam time allowance