AZ ROC A (KA) Dual Engineering study materials
AZ ROC A (KA) Dual Engineering study resources

AZ ROC A (KA) Dual Engineering key terms

AZ ROC A (KA) Dual Engineering · Get comfortable with the vocabulary.

Lien waiver

A written statement, usually signed by a subcontractor or supplier, giving up the right to file a mechanics lien for work or materials already furnished, often exchanged for progress or final payment.

Related: Mechanics lien, Retainage, Substantial completion
Mechanics lien

A statutory claim against real property that secures payment for labor, services, or materials provided to improve it. Contractors and suppliers must follow strict notice and filing deadlines to preserve it.

Related: Lien waiver, Preliminary notice, Retainage
Preliminary notice

A formal written warning, required in some states, telling a property owner that a party supplying labor or materials may later claim a mechanics lien if it is not paid.

Related: Mechanics lien, Lien waiver
Retainage

A percentage of each progress payment withheld by the owner or general contractor until the work is substantially or fully complete, protecting against incomplete or defective work and unpaid lower-tier parties.

Related: Substantial completion, Lien waiver, Schedule of values
Substantial completion

The stage when the work is sufficiently finished that the owner can use the project for its intended purpose, even though minor punch-list items remain. It often starts warranty periods and releases retainage.

Related: Punch list, Retainage
Change order

A written, signed amendment to the contract that modifies scope, price, or schedule. Without written authorization, extra work may not be compensable.

Related: Schedule of values, Punch list
Schedule of values

A line-item breakdown of the contract sum allocated to portions of the work, used as the basis for progress payment requests and for tracking earned value against completed work.

Related: Retainage, Change order
Punch list

A compiled record of incomplete or defective items identified during a walkthrough near project closeout, which the contractor must correct before final acceptance and final payment.

Related: Substantial completion, Change order
Differing site condition

A subsurface or latent physical condition at the site that differs materially from what the contract documents indicated, potentially entitling the contractor to extra time or money.

Related: Change order, Geotechnical report, Benchmark
Benchmark

A fixed reference point of known elevation or horizontal position used to establish and check grades and alignments during surveying and construction layout.

Related: Cut and fill, Differing site condition
Cut and fill

The earthwork process of removing soil from high areas (cut) and placing it in low areas (fill) to reach a desired grade, ideally balancing volumes on site to minimize hauling.

Related: Benchmark, Soil compaction, Swell factor
Swell factor

The percentage by which a soil's volume increases when excavated and loosened compared with its compacted in-place volume, used to convert truck loads and stockpile quantities.

Related: Cut and fill, Soil compaction
Soil compaction

Mechanical densification of soil by removing air voids, usually measured as a percentage of maximum dry density and verified in the field with a nuclear gauge or sand cone test.

Related: Cut and fill, Swell factor, Trench shoring
Trench shoring

A system of hydraulic jacks, plates, or sloping used to protect workers from cave-ins while working in excavations, required once a trench reaches five feet deep unless a competent person deems otherwise.

Related: Competent person, Soil compaction
Competent person

An individual capable of identifying existing and predictable hazards and authorized to take prompt corrective action, such as inspecting excavations and fall protection systems before work begins.

Related: Trench shoring, Excavation permit
Excavation permit

Written authorization from a local authority to dig, including requirements to notify utility locating services and confirm no buried lines will be struck before breaking ground.

Related: Competent person, Trench shoring
Water-cement ratio

The ratio of the mass of water to the mass of cementitious material in a concrete mix; lower ratios generally increase strength and durability but reduce workability.

Related: Slump test, Concrete curing
Slump test

A field test measuring how far a fresh concrete sample settles when a standard cone is lifted, giving a quick indication of consistency and workability before placement.

Related: Water-cement ratio, Concrete curing
Concrete curing

Maintaining adequate moisture and temperature in placed concrete so cement hydration can continue, allowing the mix to develop its designed strength and durability over time.

Related: Water-cement ratio, Slump test, Formwork
Formwork

Temporary molds and supporting falsework that hold fresh concrete in the required shape and position until it hardens enough to support itself.

Related: Concrete curing, Rebar cover
Rebar cover

The thickness of concrete between the outer surface of embedded reinforcing steel and the nearest concrete face, protecting the steel from corrosion and providing fire resistance.

Related: Formwork, Welded wire reinforcement
Welded wire reinforcement

A factory-made grid of crossing wires electrically welded at intersections, used in slabs and walls to control cracking and distribute loads.

Related: Rebar cover
Load calculation

A systematic determination of heating and cooling loads for a building based on envelope, occupancy, and climate data, used to size HVAC equipment correctly rather than by rule of thumb.

Related: Ductwork, Voltage drop
Ductwork

A network of sheet-metal or flexible conduits that distributes conditioned air from HVAC equipment to occupied spaces and returns air to the unit.

Related: Load calculation, Damper
Damper

A movable plate inside ductwork or a flue that regulates airflow, used for balancing air distribution or for fire and smoke control in life-safety systems.

Related: Ductwork, Load calculation
Voltage drop

The reduction in voltage along a conductor caused by its resistance and the current flowing through it, which must be limited so equipment receives adequate operating voltage.

Related: Load calculation, Grounding
Grounding

Connecting electrical equipment and systems to earth through a low-resistance path, providing a safe route for fault current and reducing shock and fire hazards.

Related: Voltage drop
Air gap

A physical separation between a potable water supply outlet and the flood level of a receiving fixture or vessel, the most reliable form of backflow prevention.

Related: Backflow preventer, Fixture unit
Backflow preventer

A device or assembly installed in a piping system to stop contaminated water from reversing flow into the potable supply, selected according to the degree of hazard present.

Related: Air gap, Fixture unit
Fixture unit

A dimensionless measure of the probable water demand or drainage load of a plumbing fixture, used to size supply and drain piping for a building.

Related: Air gap, Backflow preventer
Weld procedure specification

A written document giving the detailed welding parameters, materials, and techniques qualified by testing for a particular joint, so welders produce consistent, code-compliant results.

Related: Welder qualification, Nondestructive testing, Weld symbol
Welder qualification

Testing of an individual welder's ability to produce acceptable welds on a specific process and joint configuration, documented to show the welder is certified for that work.

Related: Weld procedure specification, Nondestructive testing
Nondestructive testing

Inspection methods such as ultrasonic, radiographic, magnetic particle, or dye penetrant testing that reveal internal or surface weld defects without damaging the completed weldment.

Related: Weld procedure specification, Welder qualification
Weld symbol

A standard graphical notation on drawings that specifies weld type, size, length, spacing, and location relative to the joint reference line.

Related: Weld procedure specification, Specification
Specification

The written portion of the contract documents describing materials, workmanship, quality standards, and execution requirements that supplement the drawings.

Related: Weld symbol, Addendum, Quantity takeoff
Addendum

A written modification to the bidding or contract documents issued before bid opening to clarify, correct, or change the drawings or specifications.

Related: Specification, Change order
Quantity takeoff

The process of measuring and listing materials and labor from the drawings and specifications to price a project and prepare a bid.

Related: Specification, Schedule of values
Fall protection

Systems and practices, such as guardrails, personal fall arrest, or safety nets, used to prevent or arrest falls from elevations, generally required at six feet or more in construction.

Related: Competent person, Hazard communication
Hazard communication

The OSHA-required program of labeling, safety data sheets, and employee training that informs workers about hazardous chemicals present on the job site.

Related: Fall protection, Competent person
Stormwater pollution prevention plan

A site-specific plan required under clean water regulations that identifies erosion and sediment controls and best management practices to keep construction runoff from polluting waterways.

Related: Excavation permit, Hazard communication