WV General Contractor study materials
WV General Contractor study resources

WV General Contractor flashcards

WV General Contractor · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Critical path
The longest-duration sequence of dependent activities through a project network; any delay on this path delays the project finish by the same amount.
Total float
The amount of time an activity can be delayed without delaying project completion; calculated as late start minus early start or late finish minus early finish.
Substantial completion
The stage when the work is sufficiently complete for its intended use, triggering warranty start, retainage reduction, and often owner occupancy.
Liquidated damages
A contractually fixed sum per day of delay that must be a reasonable forecast of probable loss at contract formation to be enforceable.
Change order
A written modification to the contract scope, price, or schedule signed by authorized parties; work outside it may be uncompensated.
Schedule performance index
Earned value divided by planned value; a value below 1.0 indicates the project is behind the planned schedule.
Cost performance index
Earned value divided by actual cost; a value below 1.0 indicates the project is spending more than the work earned.
Retainage
A percentage withheld from each progress payment until completion; commonly 5% on West Virginia public improvement contracts.
Mechanic's lien
A statutory claim against real property by a party who furnished labor or materials; in West Virginia a notice of lien is generally required within 100 days.
Quantity takeoff
A measured listing of all materials and work items required by the drawings and specifications, forming the basis of the estimate.
Extended cost
The product of a unit price and its quantity; summed across items to produce the direct cost subtotal of the estimate.
Contingency
An allowance added to the estimate for known unknowns and risk; it is separate from overhead and profit.
Labor burden
The additional cost above base wages for taxes, insurance, benefits, and workers' compensation, expressed as a percentage or hourly add-on.
Bid bond
A surety instrument assuring the owner that the bidder will enter the contract if awarded; typically 5-10% of the bid amount.
Performance bond
A surety guarantee that the contractor will complete the contract work per its terms; typically covers 100% of the contract price.
Unbalanced bid
A bid that shifts prices between line items to improve cash flow or exploit quantity errors; may be rejected as nonresponsive.
Addendum
A written modification to bidding documents issued before bid opening that becomes part of the contract documents.
Concrete 28-day strength
The compressive strength used to specify structural concrete, measured on standard cylinders cured 28 days after placement.
Water-cement ratio
The mass of water divided by the mass of cementitious material; lower ratios increase strength and reduce permeability.
Nominal lumber size
The labeled dimension of dressed lumber; a nominal 2x4 measures 1-1/2 in by 3-1/2 in after surfacing.
Rebar lap splice
The overlap length where two reinforcing bars transfer force; depends on bar size, concrete strength, and required development length.
Type X gypsum board
Gypsum board with a specially reinforced core that provides a one-hour fire rating in tested rated assemblies.
Footing sizing
Required footing area equals total load divided by the allowable soil bearing pressure; governs footing width and length.
Vapor retarder placement
Installed on the warm side of the assembly in cold climates to limit moisture migration into the insulation and framing.
Cold weather concreting
Placement and curing practices that maintain adequate temperature and moisture when ambient conditions fall below 40 F, per ACI 306.
OSHA fall protection threshold
Construction fall protection is required at 6 ft above a lower level; general industry uses a 4 ft threshold.
Excavation protective system
Required for trenches 5 ft or deeper unless entirely in stable rock; includes sloping, shoring, or trench boxes.
Excavation egress
Trenches 4 ft or deeper must have a ladder, stairway, or ramp within 25 ft of lateral travel for each worker.
Competent person
An individual capable of identifying hazards and authorized to take prompt corrective action; must inspect excavations daily before entry.
Scaffold guardrail height
Guardrails are required on scaffolds 10 ft or higher, with toprails, midrails, and toe boards per OSHA requirements.
WV contractor license threshold
West Virginia requires a contractor license for projects of $2,500 or more in combined labor and materials.
Safety data sheet
A standardized document listing hazards, handling, and first aid for a chemical; must be accessible to workers under hazard communication.