Refrigerant Retrofit Decision on a Chiller

A 300 kW air-cooled chiller runs on R-22 and has developed a slow leak at a flare joint. The owner wants to 'top it up and keep going' because a replacement is expensive. A contractor proposes dropping in an R-22 'replacement blend' without changing the mineral oil or the expansion valve, claiming it is 'a direct drop-in'. The system has a liquid-line filter drier, a thermostatic expansion valve set for R-22, and a low-pressure cut-out. Ambient design is 35 °C; condensing pressure is already near the high-pressure trip on hot days.

1. Evaluate the 'top up and keep going' and 'direct drop-in' proposals against good practice.

Read the worked answer

Both proposals are unsound:

  • 'Top up and keep going' ignores that R-22 is an ozone-depleting HCFC subject to phase-out and leak-repair obligations. A known leak must be located and repaired, not masked by topping up. Repeated top-ups also hide the leak rate and risk running the system low on charge.
  • 'Direct drop-in' is a marketing claim, not an engineering one. Most R-22 replacement blends are not true drop-ins: they have different glide, different capacity, different mass flow, and often require a different lubricant (e.g. POE instead of mineral oil) and different seals/elastomers.
  • Leaving the R-22 TXV and mineral oil in place with a blend can cause poor superheat control, oil return problems and reduced capacity.
  • The system is already near its high-pressure trip at 35 °C ambient; a blend with different pressure/temperature characteristics could push it over on hot days.

Correct approach: repair the leak, pressure-test, evacuate and dehydrate, then decide retrofit vs replacement on a proper engineering basis.

2. Describe the engineering checks you would complete before any refrigerant change, and the conditions under which you would refuse the retrofit.

Read the worked answer

Checks before change:

  1. Repair and leak-test the flare joint; confirm the system holds under test.
  2. Identify the existing oil, TXV, seals and any pressure switches; obtain the blend manufacturer's retrofit guidance.
  3. Compare the blend's glide, capacity and mass flow with R-22; check whether a TXV/orifice change and oil change are required.
  4. Check condenser capacity against the new refrigerant at 35 °C design ambient and confirm the high-pressure trip has margin.
  5. Check the low-pressure cut-out setting against the new charge and expected suction pressures.
  6. Confirm component compatibility (elastomers, drier type) and that the new refrigerant is legally permitted.

Refuse the retrofit if:

  • The blend requires an oil change the owner will not fund, or the compressor is not approved for the new lubricant.
  • The condenser cannot reject the load at design ambient without tripping.
  • The TXV and controls cannot be re-set for the new refrigerant.
  • The leak cannot be repaired first. In those cases recommend replacement or a properly engineered conversion with new components.