Bid Price Analysis and Unbalanced Bidding Detection

AACE CEP Certified Estimating Professional · Put your knowledge to work in context.

All case studies

Bid Price Analysis and Unbalanced Bidding Detection

You are evaluating bids for a design‑build project. The engineer’s estimate is $10M, broken down as follows: mobilization $1M, earthworks $2M, concrete $3M, steel $3M, and closeout $1M. Bidder A submits a total price of $9.8M with the following breakdown: mobilization $1.5M, earthworks $1.8M, concrete $2.8M, steel $2.7M, and closeout $1.0M. Bidder B submits $10.2M with a balanced breakdown proportional to the engineer’s estimate. The project schedule shows that mobilization occurs in the first month, earthworks in months 2‑4, concrete in months 3‑6, steel in months 5‑8, and closeout in month 9. The owner’s payment terms are monthly progress payments based on work completed, with 10% retention. The owner is concerned about bidder A’s price and asks for your analysis.

1. Analyze bidder A’s breakdown for unbalanced bidding. What are the potential risks to the owner?

Read the worked answer

Bidder A’s breakdown is unbalanced: mobilization is 50% higher than the engineer’s estimate ($1.5M vs $1M), while earthworks, concrete, and steel are lower. This is a front‑end loaded bid, where the bidder increases prices for early work to improve cash flow. The total price is lower than the engineer’s estimate, but the owner may pay more early. Risks: if the bidder defaults early, the owner may have overpaid for mobilization; the owner’s cash flow is negatively impacted; and the bidder may claim that later work is underfunded, leading to change orders. Also, the lower prices for later work may indicate a lack of understanding or a strategy to win the bid and then seek changes. The owner should require a detailed cost breakdown and verify that prices are reasonable.

2. Calculate the approximate cash flow impact to the owner in the first three months under bidder A’s schedule compared to a balanced bid. What actions can the owner take to mitigate the risk?

Read the worked answer

Assuming work progresses linearly within each activity, in the first three months: mobilization (month 1) = $1.5M; earthworks (months 2‑4) = $1.8M over 3 months, so months 2 and 3 each $0.6M; concrete (months 3‑6) = $2.8M over 4 months, so month 3 $0.7M. Total for months 1‑3 = $1.5M + $0.6M + $0.6M + $0.7M = $3.4M. For a balanced bid proportional to engineer’s estimate with total $10M, the same percentages: mobilization $1M, earthworks $2M over 3 months = $0.667M per month, concrete $3M over 4 months = $0.75M per month. Total months 1‑3 = $1M + $0.667M + $0.667M + $0.75M = $3.084M. So bidder A is paid about $316k more in the first three months. Mitigation: require a balanced breakdown, negotiate a cap on mobilization, use a cost‑reimbursable or unit‑price contract for early work, or require a performance bond. The owner could also reject the bid if it is materially unbalanced.