AACE CEP Certified Estimating Professional study materials
AACE CEP Certified Estimating Professional study resources

AACE CEP Certified Estimating Professional cheat sheet

AACE CEP Certified Estimating Professional · Keep the key ideas within reach.

Quick reference

Estimating Fundamentals and Concepts

  • A cost estimate is a prediction of the probable cost of a project at a given point in time, based on defined scope and available information.

  • Estimate accuracy range narrows as project definition matures: conceptual estimates may vary by -30%/+50% or wider, while definitive estimates typically fall within -5%/+10%.

  • AACE estimate classes (Class 5 through Class 1) map to increasing project definition maturity, from 0-2% defined (Class 5) to 65-100% defined (Class 1).

  • Estimate input is scope plus pricing basis; estimate output is cost plus basis of estimate (BOE) documentation.

  • Direct costs attach to specific work items; indirect costs are shared across the project (e.g., supervision, temporary facilities, home office support).

  • Cost vs. price: cost is the expenditure to deliver scope; price includes cost plus markup for profit, risk, and commercial factors.

  • WBS decomposition drives estimate structure - costs are captured at the lowest practical level and rolled up through the hierarchy.

  • Estimate terminology distinguishes accuracy (closeness to actual) from precision (level of detail/rounding); a precise estimate can still be inaccurate.

Quick reference

Estimating Methods and Techniques

  • Order-of-magnitude/conceptual methods include capacity factoring (Lang factor), scale-of-operations (six-tenths rule: C2 = C1 × (Q2/Q1)^n, n ≈ 0.6), and parametric/unit-cost models.

  • Parametric estimating uses statistical relationships between cost and measurable drivers (e.g., cost per kW, per m², per ton) and is most reliable with calibrated historical data.

  • Deterministic methods (detailed takeoff, bottom-up, activity-based) build cost from quantities × unit rates and require mature scope definition.

  • Lang factor estimating derives total plant cost as a multiplier applied to delivered equipment cost; factors vary by plant type (solids, fluids, mixed).

  • Factored/ratio estimating applies multipliers to a known base cost (e.g., piping as a ratio of equipment cost) and is intermediate in accuracy.

  • Unit-rate estimating requires a defined quantity and a rate composed of labor, material, equipment, and indirect components.

  • Method selection is driven by project definition maturity, available data, required accuracy, and time/cost to prepare the estimate.

  • Range estimating and probabilistic methods (Monte Carlo, three-point) apply where deterministic point values are insufficient to represent uncertainty.

Quick reference

Cost and Price Analysis

  • Cost analysis evaluates the reasonableness of individual cost elements (labor, material, equipment, indirects); price analysis evaluates total price reasonableness without examining elements.

  • Price analysis techniques include comparison to competitive bids, catalog/price lists, historical prices, and parametric benchmarks.

  • Cost analysis techniques include should-cost models, learning-curve analysis, cost breakdown review, and rate/quantity verification.

  • Learning curve: each doubling of cumulative production reduces unit labor hours by a constant percentage (e.g., 80% curve); Y = aX^b where b = log(learning rate)/log 2.

  • Cost index escalation: C2 = C1 × (I2/I1), using published indices (e.g., CEPCI, ENR) to adjust historical costs to a new time base.

  • Location factors adjust cost from a base location to a new location (labor, material, and productivity components vary).

  • Variance analysis compares estimate vs. actual or bid vs. estimate; unexplained variances indicate either scope change or estimating bias.

  • Currency and tax treatment (exchange rates, duties, VAT) must be normalized before comparing costs across sources or regions.

Quick reference

Estimating Processes and Deliverables

  • The estimating process: scope/definition → estimate plan → quantity takeoff → pricing → indirect/contingency → review → approval → BOE delivery.

  • Basis of Estimate (BOE) documents scope, methodology, assumptions, exclusions, pricing basis, accuracy range, and risks - it is the estimate's contract with the reader.

  • Estimate plan defines class, method, WBS, coding, schedule basis, review cycle, and roles before work begins.

  • Quantity takeoff converts design documents into measurable quantities; pricing applies unit rates to those quantities.

  • Estimate reviews (check estimates, peer reviews, gate reviews) validate completeness, methodology, and reasonableness before approval.

  • Deliverables typically include the detailed estimate, summary/roll-up reports, BOE narrative, quantity reports, and cash-flow or schedule-phased outputs.

  • Estimate coding (WBS, CBS, cost codes) enables roll-up, benchmarking, and integration with cost control and accounting.

  • Estimate reconciliation compares successive estimate versions and documents the causes of change between them.

Quick reference

Risk, Contingency, and Escalation

  • Contingency covers known-unknowns (identified risks and estimating uncertainty) within the defined scope; it excludes scope changes and unforeseeable events.

  • Management reserve covers unknown-unknowns and scope changes and is typically held outside the project estimate and controlled above the project manager.

  • Expected value = probability × impact; risk-adjusted estimate = base estimate + sum of expected values of identified risks (plus contingency for uncertainty).

  • Monte Carlo simulation produces a probability distribution of total cost; the P50 value is the median, and P80 is commonly used as the contingency-inclusive target.

  • Contingency is not a flat percentage applied blindly; it should be derived from risk analysis and decrease as project definition matures.

  • Escalation reflects anticipated price change over time due to inflation/market; it is distinct from contingency and from currency effects.

  • Escalation calculation: escalated cost = base cost × (1 + escalation rate)^n, or via published indices applied to the appropriate time periods.

  • Risk register feeds the estimate: each risk is assessed for probability and impact, and risk owners and response strategies are assigned.

  • AACE estimate classes carry typical expected accuracy ranges; contingency sizing should be consistent with the class and definition level.

Quick reference

Estimating Management and Integration

  • Estimating integrates with project controls: the approved estimate becomes the basis for budgets, schedules, commitments, and change control.

  • Estimate version control and document management ensure the current approved estimate is traceable and auditable.

  • Benchmarking compares estimate metrics (e.g., cost per unit capacity, factor ratios) against historical projects to validate reasonableness.

  • Historical data management - collecting actual costs, normalizing, and storing in a database - is the foundation for future estimate accuracy.

  • Estimating productivity and quality are managed through standard procedures, templates, checklists, and defined roles/responsibilities.

  • Change management: scope changes after estimate approval require formal change control and estimate revision, not silent adjustment.

  • Cost/schedule integration (e.g., earned value) links estimate line items to schedule activities for progress and forecast measurement.

  • Stakeholder alignment and estimate communication (BOE, reviews, approvals) reduce the risk of misinterpretation and scope disputes.

Quick reference

Estimating Fundamentals and Concepts

  • A cost estimate is a prediction of the probable cost of a project at a given point in time, based on defined scope and available information.

  • Estimate accuracy range narrows as project definition matures: conceptual estimates may vary by -30%/+50% or wider, while definitive estimates typically fall within -5%/+10%.

  • AACE estimate classes (Class 5 through Class 1) map to increasing project definition maturity, from 0-2% defined (Class 5) to 65-100% defined (Class 1).

  • Estimate input is scope plus pricing basis; estimate output is cost plus basis of estimate (BOE) documentation.

  • Direct costs attach to specific work items; indirect costs are shared across the project (e.g., supervision, temporary facilities, home office support).

  • Cost vs. price: cost is the expenditure to deliver scope; price includes cost plus markup for profit, risk, and commercial factors.

  • WBS decomposition drives estimate structure - costs are captured at the lowest practical level and rolled up through the hierarchy.

  • Estimate terminology distinguishes accuracy (closeness to actual) from precision (level of detail/rounding); a precise estimate can still be inaccurate.

Quick reference

Estimating Methods and Techniques

  • Order-of-magnitude/conceptual methods include capacity factoring (Lang factor), scale-of-operations (six-tenths rule: C2 = C1 × (Q2/Q1)^n, n ≈ 0.6), and parametric/unit-cost models.

  • Parametric estimating uses statistical relationships between cost and measurable drivers (e.g., cost per kW, per m², per ton) and is most reliable with calibrated historical data.

  • Deterministic methods (detailed takeoff, bottom-up, activity-based) build cost from quantities × unit rates and require mature scope definition.

  • Lang factor estimating derives total plant cost as a multiplier applied to delivered equipment cost; factors vary by plant type (solids, fluids, mixed).

  • Factored/ratio estimating applies multipliers to a known base cost (e.g., piping as a ratio of equipment cost) and is intermediate in accuracy.

  • Unit-rate estimating requires a defined quantity and a rate composed of labor, material, equipment, and indirect components.

  • Method selection is driven by project definition maturity, available data, required accuracy, and time/cost to prepare the estimate.

  • Range estimating and probabilistic methods (Monte Carlo, three-point) apply where deterministic point values are insufficient to represent uncertainty.

Quick reference

Cost and Price Analysis

  • Cost analysis evaluates the reasonableness of individual cost elements (labor, material, equipment, indirects); price analysis evaluates total price reasonableness without examining elements.

  • Price analysis techniques include comparison to competitive bids, catalog/price lists, historical prices, and parametric benchmarks.

  • Cost analysis techniques include should-cost models, learning-curve analysis, cost breakdown review, and rate/quantity verification.

  • Learning curve: each doubling of cumulative production reduces unit labor hours by a constant percentage (e.g., 80% curve); Y = aX^b where b = log(learning rate)/log 2.

  • Cost index escalation: C2 = C1 × (I2/I1), using published indices (e.g., CEPCI, ENR) to adjust historical costs to a new time base.

  • Location factors adjust cost from a base location to a new location (labor, material, and productivity components vary).

  • Variance analysis compares estimate vs. actual or bid vs. estimate; unexplained variances indicate either scope change or estimating bias.

  • Currency and tax treatment (exchange rates, duties, VAT) must be normalized before comparing costs across sources or regions.

Quick reference

Estimating Processes and Deliverables

  • The estimating process: scope/definition → estimate plan → quantity takeoff → pricing → indirect/contingency → review → approval → BOE delivery.

  • Basis of Estimate (BOE) documents scope, methodology, assumptions, exclusions, pricing basis, accuracy range, and risks - it is the estimate's contract with the reader.

  • Estimate plan defines class, method, WBS, coding, schedule basis, review cycle, and roles before work begins.

  • Quantity takeoff converts design documents into measurable quantities; pricing applies unit rates to those quantities.

  • Estimate reviews (check estimates, peer reviews, gate reviews) validate completeness, methodology, and reasonableness before approval.

  • Deliverables typically include the detailed estimate, summary/roll-up reports, BOE narrative, quantity reports, and cash-flow or schedule-phased outputs.

  • Estimate coding (WBS, CBS, cost codes) enables roll-up, benchmarking, and integration with cost control and accounting.

  • Estimate reconciliation compares successive estimate versions and documents the causes of change between them.

Quick reference

Risk, Contingency, and Escalation

  • Contingency covers known-unknowns (identified risks and estimating uncertainty) within the defined scope; it excludes scope changes and unforeseeable events.

  • Management reserve covers unknown-unknowns and scope changes and is typically held outside the project estimate and controlled above the project manager.

  • Expected value = probability × impact; risk-adjusted estimate = base estimate + sum of expected values of identified risks (plus contingency for uncertainty).

  • Monte Carlo simulation produces a probability distribution of total cost; the P50 value is the median, and P80 is commonly used as the contingency-inclusive target.

  • Contingency is not a flat percentage applied blindly; it should be derived from risk analysis and decrease as project definition matures.

  • Escalation reflects anticipated price change over time due to inflation/market; it is distinct from contingency and from currency effects.

  • Escalation calculation: escalated cost = base cost × (1 + escalation rate)^n, or via published indices applied to the appropriate time periods.

  • Risk register feeds the estimate: each risk is assessed for probability and impact, and risk owners and response strategies are assigned.

  • AACE estimate classes carry typical expected accuracy ranges; contingency sizing should be consistent with the class and definition level.

Quick reference

Estimating Management and Integration

  • Estimating integrates with project controls: the approved estimate becomes the basis for budgets, schedules, commitments, and change control.

  • Estimate version control and document management ensure the current approved estimate is traceable and auditable.

  • Benchmarking compares estimate metrics (e.g., cost per unit capacity, factor ratios) against historical projects to validate reasonableness.

  • Historical data management - collecting actual costs, normalizing, and storing in a database - is the foundation for future estimate accuracy.

  • Estimating productivity and quality are managed through standard procedures, templates, checklists, and defined roles/responsibilities.

  • Change management: scope changes after estimate approval require formal change control and estimate revision, not silent adjustment.

  • Cost/schedule integration (e.g., earned value) links estimate line items to schedule activities for progress and forecast measurement.

  • Stakeholder alignment and estimate communication (BOE, reviews, approvals) reduce the risk of misinterpretation and scope disputes.