AACE EVP · Keep the key ideas within reach.

Quick reference

Earned Value Management Fundamentals

  • Earned Value (EV) = Budgeted Cost for Work Performed (BCWP); Planned Value (PV) = Budgeted Cost for Work Scheduled (BCWS); Actual Cost (AC) = Actual Cost for Work Performed (ACWP).

  • Cost Variance (CV) = EV - AC; positive CV means under budget.

  • Schedule Variance (SV) = EV - PV; positive SV means ahead of schedule.

  • Cost Performance Index (CPI) = EV / AC; CPI > 1 indicates cost efficiency.

  • Schedule Performance Index (SPI) = EV / PV; SPI > 1 indicates schedule efficiency.

  • Budget at Completion (BAC) is the total authorized budget for the project.

  • Estimate at Completion (EAC) = BAC / CPI when current cost performance is expected to continue.

  • Variance at Completion (VAC) = BAC - EAC; negative VAC indicates a projected overrun.

Quick reference

Planning and Baseline Development

  • The Performance Measurement Baseline (PMB) = sum of all control account budgets plus undistributed budget and management reserve (MR).

  • Control Account (CA) is a management control point where scope, budget, actual cost, and schedule are integrated.

  • Work Package (WP) is a task at the lowest level of the WBS that can be scheduled and budgeted.

  • Planning Package is a WBS element below the control account but above work packages, with budget but no detailed schedule.

  • Management Reserve (MR) is budget for unplanned in-scope work, not part of the PMB, and requires customer approval to use.

  • Undistributed Budget (UB) is budget for authorized work not yet assigned to a control account.

  • The Integrated Master Schedule (IMS) is the network schedule that integrates all project work.

  • A baseline is frozen after approval; changes require formal change control.

Quick reference

Earned Value Measurement and Analysis

  • Earned Value (EV) = percent complete × BAC for the work package.

  • Percent Complete = EV / BAC; Percent Spent = AC / BAC.

  • To-complete Performance Index (TCPI) = (BAC - EV) / (BAC - AC) when target is BAC.

  • TCPI = (BAC - EV) / (EAC - AC) when target is EAC.

  • Earned Schedule (ES) = time when PV equals EV; Schedule Performance Index (SPI) = ES / Actual Time.

  • Variance analysis: CV = EV - AC; SV = EV - PV; VAC = BAC - EAC.

  • Performance indices < 1 indicate unfavorable performance; > 1 favorable.

  • Estimate to Complete (ETC) = EAC - AC; EAC = AC + ETC.

Quick reference

Reporting and Forecasting

  • EAC = AC + Bottom-up ETC when future performance is expected to differ from past.

  • EAC = BAC / CPI when past cost performance is expected to continue.

  • EAC = AC + (BAC - EV) when remaining work is expected to be performed at the budgeted rate.

  • EAC = AC + (BAC - EV) / (CPI × SPI) when both cost and schedule performance are expected to continue.

  • Variance at Completion (VAC) = BAC - EAC; negative VAC indicates overrun.

  • Percent complete = EV / BAC; percent spent = AC / BAC.

  • Forecast reports should include EAC, ETC, VAC, and TCPI.

  • Trend analysis uses CPI and SPI over time to predict future performance.

Quick reference

Change Management and Integrated Baseline Reviews

  • Integrated Baseline Review (IBR) verifies the PMB is realistic and achievable.

  • IBR assesses technical, schedule, cost, and risk integration.

  • Changes to the PMB require a formal change control process.

  • Management Reserve (MR) is used for unplanned in-scope work and is not part of the PMB.

  • Undistributed Budget (UB) is budget for authorized work not yet assigned to control accounts.

  • A change to the PMB must be reflected in the IMS and EVM data.

  • Baseline change proposals should include impact on cost, schedule, and risk.

  • IBR is typically conducted within 6 months of contract award or major modification.