AACE EVP · Get comfortable with the vocabulary.

Earned Value Management (EVM)

A project performance method that compares the value of work completed against the planned value and the actual cost, giving objective indicators of schedule and cost status.

Related: Planned Value (PV), Earned Value (EV), Actual Cost (AC)
Planned Value (PV)

The authorized budget assigned to scheduled work at a given point in time; it represents what the project should have accomplished and spent by that date.

Related: Earned Value (EV), Budget at Completion (BAC)
Earned Value (EV)

The budgeted value of work actually completed by a given date, calculated from the baseline budget for those activities rather than from what was spent on them.

Related: Planned Value (PV), Actual Cost (AC), Percent Complete
Actual Cost (AC)

The total cost actually incurred and recorded for work performed during a given period, including direct labor, materials, and other charges posted to the project.

Related: Earned Value (EV), Cost Variance (CV)
Budget at Completion (BAC)

The sum of all authorized budgets established for the total scope of work on a project; the baseline total against which final performance will be judged.

Related: Planned Value (PV), Estimate at Completion (EAC)
Cost Variance (CV)

The difference between earned value and actual cost. A positive result means work is costing less than budgeted; a negative result means it is costing more.

Related: Cost Performance Index (CPI), Earned Value (EV)
Schedule Variance (SV)

The difference between earned value and planned value, expressed in budget currency. A negative result indicates less work was completed than scheduled.

Related: Schedule Performance Index (SPI), Planned Value (PV)
Cost Performance Index (CPI)

Earned value divided by actual cost. A value below 1.0 means each unit of currency spent is buying less than one unit of planned work.

Related: Cost Variance (CV), To-Complete Performance Index (TCPI)
Schedule Performance Index (SPI)

Earned value divided by planned value. A value below 1.0 means work is progressing more slowly than the baseline schedule assumed.

Related: Schedule Variance (SV), Earned Schedule
Estimate at Completion (EAC)

A forecast of the total cost the project will have incurred when all work is finished, typically derived by adjusting the budget at completion for expected performance.

Related: Estimate to Complete (ETC), Variance at Completion (VAC)
Estimate to Complete (ETC)

The expected cost of the remaining work, calculated as the forecast total cost at completion minus costs already incurred to date.

Related: Estimate at Completion (EAC), Budget at Completion (BAC)
Variance at Completion (VAC)

The projected final cost difference, calculated as the budget at completion minus the estimate at completion. A negative value signals an expected overrun.

Related: Estimate at Completion (EAC), Budget at Completion (BAC)
To-Complete Performance Index (TCPI)

The cost efficiency the remaining work must achieve to hit a specified target, calculated as remaining budget divided by remaining work.

Related: Cost Performance Index (CPI), Estimate at Completion (EAC)
Work Breakdown Structure (WBS)

A hierarchical decomposition of total project scope into progressively smaller deliverables and work packages that can be estimated, scheduled, and controlled.

Related: Control Account, Work Package
Control Account

A management point in the work breakdown structure where scope, budget, actual cost, and schedule are integrated and compared against baseline for performance measurement.

Related: Work Package, Work Breakdown Structure (WBS)
Work Package

The lowest level of the work breakdown structure at which work is estimated, scheduled, and tracked; it sits beneath a control account and has defined scope, dates, and budget.

Related: Control Account, Planning Package
Planning Package

A work breakdown structure element below a control account that holds budget and scope for future work not yet detailed into individual work packages.

Related: Work Package, Control Account
Performance Measurement Baseline (PMB)

The time-phased budget plan for all authorized work, against which project execution is measured; it excludes management reserve and undistributed budget.

Related: Management Reserve, Undistributed Budget
Management Reserve

A budget held outside the performance measurement baseline by management for unanticipated scope within the project's authorized work; its use requires formal approval.

Related: Performance Measurement Baseline (PMB), Contingency Reserve
Undistributed Budget

Authorized budget for work that has been identified in scope but not yet assigned to a control account or planning package for performance measurement.

Related: Performance Measurement Baseline (PMB), Management Reserve
Contingency Reserve

Budget set aside inside the baseline for known risks and uncertainties with identified causes, used to absorb impacts without changing the performance measurement baseline.

Related: Management Reserve, Performance Measurement Baseline (PMB)
Earned Value Measurement Method

The rule chosen for each work package to quantify physical progress objectively, such as weighted milestones, percent complete, or units completed.

Related: Percent Complete, Milestone Method, Units Completed Method
Weighted Milestone Method

A measurement technique in which a work package is divided into milestones, each assigned a budget value, and earned value is claimed as each milestone is formally achieved.

Related: Milestone Method, Earned Value Measurement Method
Percent Complete Method

A measurement approach where earned value equals the estimated fraction of a work package finished multiplied by its budget; best used for long-duration tasks with measurable progress.

Related: Earned Value Measurement Method, Units Completed Method
Units Completed Method

A measurement technique that credits earned value in proportion to the number of identical or similar units produced, using a fixed budget per unit.

Related: Percent Complete Method, Earned Value Measurement Method
Earned Schedule

A time-based extension of earned value that converts earned value into the schedule period in which it was planned to be achieved, yielding schedule variance and index in time units.

Related: Schedule Performance Index (SPI), Schedule Variance (SV)
Baseline

An approved, time-phased plan for scope, schedule, and cost against which actual performance is compared; changes to it require formal control.

Related: Performance Measurement Baseline (PMB), Integrated Baseline Review (IBR)
Integrated Baseline Review (IBR)

A joint review by customer and contractor of the performance measurement baseline to confirm it is realistic, complete, and technically sound before or during execution.

Related: Baseline, Performance Measurement Baseline (PMB)
Change Control

The formal process for identifying, evaluating, approving or rejecting, and documenting changes to project scope, schedule, or cost baselines.

Related: Baseline, Management Reserve
Scope Change

Any addition, deletion, or modification to the agreed project scope; when approved, it typically requires a corresponding adjustment to budget and schedule baselines.

Related: Change Control, Baseline
Internal Replanning

A reallocation of budget and schedule among remaining work within the existing baseline, used when execution deviates but total scope and budget remain unchanged.

Related: Change Control, Performance Measurement Baseline (PMB)
Budgeted Cost for Work Scheduled (BCWS)

The traditional name for planned value: the budget assigned to work that was scheduled to be accomplished by a given reporting date.

Related: Planned Value (PV), Budgeted Cost for Work Performed (BCWP)
Budgeted Cost for Work Performed (BCWP)

The traditional name for earned value: the budget assigned to work that has actually been completed by a given reporting date.

Related: Earned Value (EV), Budgeted Cost for Work Scheduled (BCWS)
Actual Cost of Work Performed (ACWP)

The traditional name for actual cost: the costs actually incurred for work completed during a given reporting period.

Related: Actual Cost (AC), Budgeted Cost for Work Performed (BCWP)
Variance Analysis

The practice of comparing planned, earned, and actual results, explaining the causes of significant deviations, and deciding what corrective action is warranted.

Related: Cost Variance (CV), Schedule Variance (SV), Earned Value Management (EVM)
Performance Reporting

The periodic communication of planned versus actual cost and schedule performance, variances, and forecasts to stakeholders in a consistent, agreed format.

Related: Variance Analysis, Estimate at Completion (EAC)
Forecasting

The process of projecting future cost and schedule outcomes using current performance indices, trends, and known risks to support management decisions.

Related: Estimate at Completion (EAC), To-Complete Performance Index (TCPI)