AACE EVP · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Earned Value (EV)
The budgeted cost of work performed (BCWP); it quantifies the value of completed work in terms of the approved budget.
Planned Value (PV)
The authorized budget assigned to scheduled work (BCWS); it represents the planned cost of work scheduled up to a given date.
Actual Cost (AC)
The actual cost incurred for work performed (ACWP); it includes direct and indirect costs but excludes management reserve.
Cost Variance (CV)
CV = EV - AC; a positive value indicates cost underrun, while a negative value indicates cost overrun.
Schedule Variance (SV)
SV = EV - PV; a positive value indicates ahead of schedule, while a negative value indicates behind schedule.
Cost Performance Index (CPI)
CPI = EV / AC; a value greater than 1 indicates cost efficiency, while less than 1 indicates cost inefficiency.
Schedule Performance Index (SPI)
SPI = EV / PV; a value greater than 1 indicates schedule efficiency, while less than 1 indicates schedule inefficiency.
Budget at Completion (BAC)
The total authorized budget for the project, excluding management reserve; it is the sum of all control account budgets and undistributed budget.
Performance Measurement Baseline (PMB)
The time-phased budget plan against which project performance is measured; it includes control account budgets and undistributed budget but excludes management reserve.
Control Account (CA)
A management control point where scope, budget, actual cost, and schedule are integrated and compared to earned value for performance measurement.
Work Package (WP)
A task at the lowest level of the WBS that can be scheduled, budgeted, and controlled; it has a defined scope and duration.
Planning Package
A WBS element below the control account but above work packages; it has budget but its work is not yet detailed into work packages.
Management Reserve (MR)
Budget for unplanned in-scope work, not part of the PMB, and requires customer approval to use.
Undistributed Budget (UB)
Budget for authorized work not yet assigned to a control account; it is part of the PMB until distributed.
Integrated Master Schedule (IMS)
A network schedule that integrates all project work and is used to plan, schedule, and track progress.
Earned Value (EV) Calculation
EV = percent complete × BAC for a work package; it represents the budgeted value of completed work.
To-Complete Performance Index (TCPI)
TCPI = (BAC - EV) / (BAC - AC) when target is BAC; it measures the cost efficiency needed to meet the remaining budget.
Estimate to Complete (ETC)
The expected cost to finish all remaining project work; ETC = EAC - AC.
Variance at Completion (VAC)
VAC = BAC - EAC; a negative value indicates a projected cost overrun at completion.
Earned Schedule (ES)
The time at which PV equals EV; it provides a time-based measure of schedule performance.
Schedule Performance Index (SPI) Time-Based
SPI = ES / Actual Time; a value less than 1 indicates the project is behind schedule in time.
Percent Complete
Percent Complete = EV / BAC; it indicates the proportion of the total budget earned to date.
Percent Spent
Percent Spent = AC / BAC; it indicates the proportion of the total budget consumed to date.
EAC with CPI
EAC = BAC / CPI; this forecast assumes that current cost performance will continue for the remaining work.
EAC with Bottom-Up ETC
EAC = AC + Bottom-up ETC; this forecast is used when future performance is expected to differ from past performance.
EAC with Budgeted Rate
EAC = AC + (BAC - EV); this forecast assumes remaining work will be performed at the budgeted rate.
EAC with CPI and SPI
EAC = AC + (BAC - EV) / (CPI × SPI); this forecast assumes both cost and schedule performance will continue.
Trend Analysis
Analysis of CPI and SPI over time to predict future performance and identify unfavorable trends.
Forecast Report
A report that includes EAC, ETC, VAC, and TCPI to communicate projected cost and schedule outcomes.
Integrated Baseline Review (IBR)
A review that verifies the PMB is realistic and achievable, assessing technical, schedule, cost, and risk integration.
Change Control Process
A formal process for approving and incorporating changes to the PMB; changes must be reflected in the IMS and EVM data.
Baseline Change Proposal
A proposal to change the PMB that includes impact analysis on cost, schedule, and risk.