WBS work package
The lowest-level WBS element that can be estimated, scheduled, and assigned to a single owner; typically sized 8 to 80 labor hours.
PERT expected duration
Weighted average of optimistic, most likely, and pessimistic estimates computed as (O + 4M + P) / 6, used to model duration uncertainty.
PERT standard deviation
Measure of duration uncertainty for an activity, computed as (P - O) / 6; path variance is the sum of activity variances along the path.
Analogous estimating
Top-down duration or cost estimate based on historical similarity to a comparable past project; fast but less accurate than bottom-up.
Parametric estimating
Estimate derived from a unit rate multiplied by a quantity, such as hours per square meter times area; accuracy depends on rate validity.
Finish-to-start dependency
Logical relationship where a successor cannot start until its predecessor finishes; the most common dependency type in construction schedules.
Rolling wave planning
Progressive elaboration in which near-term work is planned in detail while far-term work remains at summary level and is refined later.
Project calendar
Defines working days, shifts, and holidays used to convert activity durations in working days into calendar dates on the schedule.
Forward pass
CPM calculation moving left to right: early start equals the maximum early finish of predecessors plus lag; early finish equals early start plus duration.
Backward pass
CPM calculation moving right to left: late finish equals the minimum late start of successors minus lag; late start equals late finish minus duration.
Total float
Amount of time an activity can be delayed without delaying the project finish; equals late start minus early start or late finish minus early finish.
Free float
Time an activity can slip without delaying the early start of any successor; equals the minimum successor early start minus the activity's early finish.
Critical path
The longest continuous path through the network; its activities have the least total float, commonly zero, and determine the project duration.
Negative total float
Condition where the computed late dates precede early dates, meaning the logic cannot satisfy an imposed finish date without compression or rework.
Resource leveling
Resolving resource over-allocation by shifting activity start and finish dates; it may extend the critical path and project finish date.
Resource smoothing
Time-limited resource adjustment that uses available float to reduce peaks without moving the project finish date or critical path.
Lag and lead
Lag adds wait time between linked activities; lead overlaps them with negative time. Both modify logic and should be used sparingly.
Schedule constraint
A date restriction such as start-no-earlier-than or finish-no-later-than that overrides network logic and can distort float calculations.
Data date
The status date to which progress is recorded; work before it is actual and work after it is forecast in the update schedule.
Out-of-sequence progress
Condition where an activity starts before its predecessor finishes; must be resolved with logic or constraints before the update is valid.
Remaining duration
Estimated working time still needed to complete an in-progress activity; combined with actual duration it drives percent complete by duration.
Finish variance
Difference between the current forecast finish date and the baseline finish date; negative values indicate the project is ahead of baseline.
Earned schedule
Time-based extension of earned value where earned schedule is the baseline date at which planned value equals current earned value.
SPI(t)
Schedule performance index for time, computed as earned schedule divided by actual time; values below 1.0 indicate the project is behind schedule.
Baseline schedule
The approved, frozen version of the schedule against which progress and change are measured; changes require formal change control.
Schedule health check
Audit of logic and structure: no open ends, no negative lags, minimal constraints, reasonable float, and a valid critical path.
Monte Carlo schedule simulation
Probabilistic analysis that samples duration distributions across many iterations to produce a distribution of possible project finish dates.
P80 finish date
The finish date with an 80 percent probability of being met or beaten in a schedule risk analysis; often used to set contingency.
Joint confidence level
Probability that a project will complete at or below a specified cost and schedule target simultaneously, from combined cost-schedule simulation.
Near-critical path
A path whose total float is small, often defined as ten days or less, that could become critical if its activities slip.
Schedule crashing
Shortening critical-path activity durations by adding resources or overtime, trading increased cost for reduced project duration.
Fast-tracking
Compressing the schedule by overlapping activities that were planned in sequence, which increases coordination risk and rework exposure.