Justifying an Automation Project With Uncertain Savings

CIE · Put your knowledge to work in context.

All case studies

Justifying an Automation Project With Uncertain Savings

A manual assembly station uses 3 operators at $38/h fully loaded, 2,000 h/year each. A $420,000 robot cell would replace 2 operators, leaving 1 for load/unload and monitoring. Maintenance is $18,000/year, power $6,000/year, and the cell has a 10-year life with $40,000 salvage. The firm uses MARR = 12%. The vendor's savings estimate assumes 95% uptime; the plant's similar cells average 88% uptime. Labor is expected to rise 4%/year; maintenance 3%/year. Working capital of $25,000 is required. The plant is capital-constrained and has a competing project with a 22% IRR.

1. Compute annual labor savings at 95% and at 88% uptime, and the simple payback for each.

Read the worked answer

Labor saved: 2 operators × 2,000 h × $38 = $152,000/year at full utilization.

At 95% uptime: savings = 152,000 × 0.95 = $144,400. Net annual benefit before tax = 144,400 − 18,000 − 6,000 = $120,400. Payback = 420,000/120,400 ≈ 3.5 years.

At 88% uptime: savings = 152,000 × 0.88 = $133,760. Net = 133,760 − 24,000 = $109,760. Payback = 420,000/109,760 ≈ 3.8 years.

Note: the 7-point uptime gap costs ~$10,600/year - material over 10 years, and it grows with escalating labor.

2. Compute NPV at the realistic 88% uptime, including escalation and working capital, and recommend a decision.

Read the worked answer

Build annual net cash flow with escalation. Labor savings grow 4%/yr; maintenance grows 3%/yr; power flat.

Year 1: labor 133,760; maint 18,000; power 6,000 → net 109,760. Approximate NPV using a growing-annuity shortcut with average escalation: labor savings at 4% over 10 yr, discounted at 12%, factor ≈ [1−(1.04/1.12)^10]/(0.12−0.04) ≈ 7.0. PV labor ≈ 133,760 × 7.0 ≈ $936,000. Maintenance at 3%: factor ≈ [1−(1.03/1.12)^10]/0.09 ≈ 7.6; PV ≈ 18,000 × 7.6 ≈ $137,000. Power: PV annuity factor 5.65 × 6,000 ≈ $34,000. Salvage PV = 40,000/1.12^10 ≈ $12,900.

NPV ≈ 936,000 − 137,000 − 34,000 + 12,900 − 420,000 − 25,000 (WC, recovered at end ≈ +8,000 PV) ≈ $341,000 positive. IRR comfortably exceeds 12%.

Decision: financially attractive even at 88% uptime, but the competing project returns 22%. Under capital constraint, fund the 22% project first; the robot cell is a strong second if capital frees up.

3. Identify the two assumptions most likely to break the analysis and how to test them.

Read the worked answer
  1. Uptime and labor redeployment: the model assumes the 2 displaced operators are truly removed, not redeployed. If they are absorbed elsewhere, savings vanish. Test: confirm with plant management that headcount falls, and track actual uptime for 6 months before full commitment.
  2. Escalation and discount rate: a 4% labor escalation compounds; at 2% the NPV drops materially. Test: sensitivity analysis on escalation (2%/4%/6%) and MARR (12%/15%).

Also stress-test maintenance (vendor estimates often low) and salvage. Present NPV as a range, not a point - and stage the investment (pilot cell) to buy information before the full $420,000.