ACI Tilt-Up Technician flashcards
ACI Tilt-Up Technician · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Panel weight formula
- Panel weight equals panel volume multiplied by concrete unit weight; normal-weight concrete is about 150 pounds per cubic foot.
- Control point layout
- Control points are fixed survey references used to locate panel edges, openings, and embeds; all layout dimensions are measured from them to avoid cumulative error.
- Square corner check
- A 3-4-5 triangle or equal diagonal measurements confirm a form corner is square; unequal diagonals indicate the rectangle is skewed and must be adjusted.
- Casting surface preparation
- The casting surface is cleaned, checked for level, and kept free of standing water; surface defects can transfer to the panel face or change panel thickness.
- Crane access planning
- Crane access planning fixes the crane position, pick radius, outrigger footprint, and travel path before casting so panel orientation and lift inserts match the lift plan.
- Panel identification mark
- A panel identification mark is a unique label placed on the casting surface or form that links each panel to its erection drawing, orientation, and location.
- Opening blockout layout
- Opening and blockout layout uses the same control lines as the panel perimeter; consistent layout prevents openings from shifting relative to edges and inserts.
- Form release agent
- Form release agent is a coating applied in a thin uniform film to forms and the casting surface to prevent concrete adhesion; puddling or overspray can contaminate reinforcement or inserts.
- Form joint sealing
- Form joints and corners are sealed to stop grout loss; escaping mortar creates voids, honeycomb, and dimensional variation at panel edges and openings.
- Chamfer strip function
- A chamfer strip forms a beveled edge on the panel; the bevel reduces chipping and spalling when the panel is lifted, handled, and erected.
- Blockout anchoring
- Blockouts and reveals are anchored to forms or the casting surface so fresh concrete cannot float or shift them during placement.
- Form line and grade
- Form line and grade are the horizontal position and elevation of the formwork; they are checked before concrete placement because movement changes panel geometry.
- Fresh concrete pressure
- Fresh concrete exerts lateral pressure on forms; pressure increases with placement rate, concrete temperature, and depth of the concrete lift.
- Form removal strength
- Forms are removed only after concrete has gained enough strength to resist damage from form removal and to carry handling stresses.
- Lift insert placement
- Lift inserts are placed at the lift points shown on panel drawings and oriented to accept the rigging hardware without eccentric loading.
- Reinforcement cover
- Reinforcement cover is the distance from the concrete surface to the nearest bar or wire; chairs and spacers maintain cover during concrete placement.
- Embed plate alignment
- Embed plates are fixed to forms or supporting steel so their face, elevation, and alignment match the erection drawings and connecting steel.
- Rebar chair function
- Rebar chairs support reinforcement at the specified elevation; displaced or missing chairs reduce cover and can change panel strength.
- Insert capacity check
- Lift insert capacity must exceed the load from panel weight, rigging angle, and dynamic lift effects; the controlling load is the highest insert demand.
- Sleeve coordination
- Sleeves and blockouts are coordinated with reinforcement so bars are not cut and inserts are not moved from their design locations.
- Concrete consolidation
- Internal vibration consolidates concrete around reinforcement and inserts; over-vibration causes segregation and can displace embeds or blockouts.
- Bleed water finishing
- Bleed water is water that rises to the concrete surface after placement; finishing while bleed water is present can cause weak, blistered surfaces.
- Curing compound coverage
- Curing compound is sprayed or rolled over exposed concrete to slow moisture loss; coverage must be continuous at the rate specified for the product.
- Screed panel thickness
- Screeding levels and compacts fresh concrete to the form height; screed rails and grade stakes control panel thickness and surface elevation.
- Cold joint prevention
- A cold joint forms when fresh concrete is placed against concrete that has already set; continuous placement between planned joints prevents unintended cold joints.
- Test cylinder sampling
- Concrete test cylinders are sampled from the delivered concrete and cured under controlled conditions; they estimate strength for form removal, lifting, and acceptance.
- Sling tension formula
- For two symmetric slings, tension per sling equals panel weight divided by two times the cosine of the sling angle from vertical.
- Center of gravity lift
- The panel center of gravity is the point where its weight balances; lift inserts are arranged so the panel hangs level and does not rotate unexpectedly.
- Pre-lift inspection
- A pre-lift inspection verifies lift inserts, rigging hardware, crane setup, panel condition, and bracing before the panel is raised.
- Exclusion zone
- The exclusion zone is the area under and around a suspended panel where personnel are kept clear during lifting and erection.
- Temporary bracing
- Temporary bracing supports an erected panel until permanent connections carry design loads; bracing is installed immediately after the panel is set.
- Rigging hardware rating
- Rigging hardware is selected by rated capacity; slings, shackles, and hooks are inspected for damage before each lift.