Carrying out a full calculation in the wrong unit system, mixing SI (kN, kPa, mm) with imperial or mixing mm and m within the same formula, and reporting an answer that is off by a factor of 1000.
Exam stems often present data in mixed units (e.g., load in kN, span in mm, modulus in GPa) and candidates plug numbers directly into memorised formulas without converting to a consistent base first.
What to do instead
Before substituting numbers, write the target unit beside each symbol in the formula and convert every input to that unit in one explicit step (e.g., 200 GPa = 200,000 N/mm^2). Do a magnitude sanity check on the final answer.
Applying a formula from memory without checking its validity conditions (e.g., using simple bending theory for a section that is not slender, or using a small-strain formula where deformation is large).
Under time pressure candidates pattern-match the problem to a familiar formula rather than reading the assumptions embedded in the stem, such as slenderness, elastic range, or steady-state conditions.
What to do instead
For each formula you plan to use, state its two or three key assumptions in the margin and tick them against the given data. If an assumption fails, look for the alternative method the stem is hinting at.
Choosing the wrong design value from a code table because the exposure class, importance factor, or occupancy category was misread from the project description.
Code tables are indexed by classification, and candidates skim the descriptive text and jump to the table, skipping the step of classifying the structure or element first.
What to do instead
Write out the classification explicitly (e.g., 'exposure class X because the element is external and coastal') before opening the table, and cite the clause number you used.
Treating a code's minimum requirement as the design target and ignoring stricter project-specific or client-specified criteria stated in the stem.
Candidates default to 'what the code says' and overlook that the question describes additional contractual or owner requirements that govern.
What to do instead
Underline every requirement in the stem (code, client, site) and design to the most stringent one, noting in the answer why that one governs.
Selecting equipment or a section based only on the primary strength or capacity check and omitting serviceability, deflection, or fatigue checks.
Strength checks feel like 'the answer', and serviceability limits are often buried in a separate clause or a footnote in the stem.
What to do instead
Keep a standard checklist for every design question: strength, stability, serviceability, durability, fire, and constructability. Run all of them and report the governing case.
Missing the controlling load combination because only the dead-plus-live case was evaluated, ignoring wind, seismic, or uplift combinations that reverse the sign of the effect.
The most familiar combination is evaluated first, and once a number is obtained candidates stop rather than comparing all applicable combinations.
What to do instead
List all applicable combinations for the structure type, compute the effect for each, and explicitly state which combination produces the maximum and minimum (including reversal).
Answering a safety question with the mitigation measure but not identifying the hazard, the risk, and the hierarchy-of-controls level applied.
Candidates recall a control (e.g., 'provide PPE') and write it down without structuring the answer as hazard identification, risk assessment, and control selection.
What to do instead
Use a fixed structure: hazard, who is exposed, likelihood and severity, then control chosen with its position in the hierarchy (elimination, substitution, engineering, administrative, PPE), and note residual risk.
Confusing permit-to-work, isolation, and lock-out/tag-out requirements, or omitting the verification step that proves isolation is effective before work starts.
These procedures overlap in everyday speech, and candidates describe the paperwork rather than the physical verification of energy isolation.
What to do instead
Describe the sequence: identify all energy sources, isolate, lock and tag, prove dead or verify zero energy, then authorise work; state who signs and who verifies.
Computing net present value, payback, or equivalent annual cost without aligning the discount rate period and cash-flow timing, or comparing alternatives with unequal lives directly.
Candidates apply the formula mechanically and forget that annual and monthly rates, or one-off and recurring costs, must be brought to a common basis.
What to do instead
Draw a simple timeline of cash flows, convert the discount rate to match the period, and for unequal lives convert to equivalent annual cost before comparing.
Answering an ethics scenario by describing the technically correct action but not stating the professional obligation, the reporting route, and the consequence of inaction.
Candidates treat ethics questions as technical ones and give a solution rather than identifying the duty, the affected parties, and the escalation path.
What to do instead
Structure the answer: the obligation (public safety and welfare first), the facts and affected parties, the action to take, whom to notify and in what order, and what to do if the concern is not addressed.