Factor of Safety

The ratio of a material's or structure's ultimate capacity to the maximum load or stress it is expected to carry in service, providing margin against uncertainty, overload, and material variability.

Related: Allowable Stress Design, Ultimate Limit State
Allowable Stress Design

A design method in which computed service stresses are kept below a permissible fraction of the material strength, with the reduction set by a safety factor rather than by statistical load factors.

Related: Factor of Safety, Ultimate Limit State
Ultimate Limit State

A design condition concerning collapse, loss of equilibrium, or structural failure under factored loads, checked to ensure the structure retains adequate strength and stability throughout its intended life.

Related: Factor of Safety, Serviceability Limit State
Serviceability Limit State

A design condition addressing fitness for normal use, such as excessive deflection, vibration, or cracking, which affects function and appearance rather than structural safety or collapse resistance.

Related: Ultimate Limit State, Factor of Safety
Load Factor

A multiplier applied to nominal loads in limit-state design to account for the possibility that actual loads exceed calculated values, reflecting uncertainty in load estimation and combination effects.

Related: Ultimate Limit State, Load Combination
Load Combination

A defined arrangement of simultaneous nominal loads, such as dead plus live plus wind, multiplied by prescribed factors, used to verify that a structure resists the most adverse credible loading scenario.

Related: Load Factor, Ultimate Limit State
Shear Stress

Internal stress acting parallel to a cross-section, arising where forces tend to slide one part of a body past another, calculated as shear force divided by resisting area.

Related: Bending Moment, Von Mises Stress
Bending Moment

The internal moment at a section of a beam equal to the sum of moments of all forces on one side of that section, governing normal stress distribution and deflection along the member.

Related: Shear Stress, Moment of Inertia
Moment of Inertia

A geometric property of a cross-section expressing its resistance to bending, equal to the integral of area times the square of distance from the neutral axis.

Related: Bending Moment, Section Modulus
Section Modulus

The ratio of a section's moment of inertia to the distance from its neutral axis to the extreme fibre, used to convert bending moment directly into maximum bending stress.

Related: Moment of Inertia, Bending Moment
Von Mises Stress

An equivalent scalar stress combining multiaxial stress components, used to compare complex stress states against a single yield strength for ductile materials under combined loading.

Related: Shear Stress, Factor of Safety
Reynolds Number

A dimensionless ratio of inertial to viscous forces in fluid flow, used to predict whether flow is laminar, transitional, or turbulent in pipes and around bodies.

Related: Darcy-Weisbach Equation, Hydraulic Grade Line
Darcy-Weisbach Equation

A formula expressing head loss in pipe flow as a function of friction factor, pipe length and diameter, and velocity head, applicable across laminar and turbulent regimes.

Related: Reynolds Number, Hydraulic Grade Line
Hydraulic Grade Line

A plotted profile of piezometric head along a pipeline, showing pressure head plus elevation and dropping in the direction of flow by the amount of friction and minor losses.

Related: Darcy-Weisbach Equation, Reynolds Number
Thermal Conductivity

A material property quantifying the rate at which heat passes through unit thickness for unit temperature difference, central to sizing insulation and predicting heat transfer in building envelopes and equipment.

Related: U-Value, Heat Exchanger Effectiveness
U-Value

The overall heat transfer coefficient of an assembly, expressing steady-state heat flow per unit area per unit temperature difference, calculated from the resistances of each layer.

Related: Thermal Conductivity, Building Envelope
Heat Exchanger Effectiveness

The ratio of actual heat transfer in a heat exchanger to the maximum thermodynamically possible transfer for the given inlet conditions and flow rates, ranging from zero to one.

Related: Thermal Conductivity
Three-Phase Power

An electrical supply arrangement using three alternating voltages displaced by 120 degrees, giving constant power delivery and enabling smaller conductors and rotating-field motors.

Related: Power Factor, Earthing System
Power Factor

The ratio of real power to apparent power in an AC circuit, indicating how effectively current is converted into useful work; low values increase current and losses.

Related: Three-Phase Power, Load Factor
Earthing System

A network of conductors connecting exposed metalwork and neutral points to the ground, providing a low-impedance fault path and limiting touch voltages for personnel protection.

Related: Residual Current Device, Lockout-Tagout
Residual Current Device

A protective device that continuously compares live and neutral currents and trips the circuit when imbalance indicates leakage to earth, reducing electric shock risk.

Related: Earthing System, Lockout-Tagout
Lockout-Tagout

A formal procedure isolating energy sources and attaching personal locks and tags before maintenance, ensuring equipment cannot be re-energised while workers are exposed.

Related: Permit to Work, Risk Assessment Matrix
Permit to Work

A documented authorisation controlling high-risk activity by specifying the work scope, hazards, precautions, and validity period, and requiring sign-off before and after the task.

Related: Lockout-Tagout, Job Safety Analysis
Job Safety Analysis

A structured method breaking a task into sequential steps, identifying hazards at each step, and recording controls before work begins, often used to brief the crew.

Related: Permit to Work, Risk Assessment Matrix
Risk Assessment Matrix

A grid combining likelihood and consequence ratings to rank hazards by risk level, guiding prioritisation of controls and decisions on whether work may proceed.

Related: Hierarchy of Controls, Job Safety Analysis
Hierarchy of Controls

A ranked order of hazard controls from most to least effective: elimination, substitution, engineering controls, administrative controls, and personal protective equipment.

Related: Risk Assessment Matrix, Job Safety Analysis
Confined Space Entry

Entry into an enclosed or partially enclosed area with restricted access and potential for hazardous atmosphere, requiring atmospheric testing, standby personnel, and rescue arrangements.

Related: Permit to Work, Risk Assessment Matrix
Building Envelope

The boundary separating conditioned interior space from the outdoor environment, including walls, roof, windows, and doors, whose performance governs energy use and moisture control.

Related: U-Value, Thermal Conductivity
Fire Compartmentation

Division of a building into fire-resisting zones by rated walls, floors, and doors to limit fire and smoke spread, protect escape routes, and allow safe evacuation.

Related: Means of Escape, Building Envelope
Means of Escape

Continuous protected routes from any point in a building to a place of safety, sized and protected so occupants can evacuate without obstruction during a fire.

Related: Fire Compartmentation, Occupant Load
Occupant Load

The calculated maximum number of people a space is designed to hold, derived from floor area and use classification, used to size exits and escape routes.

Related: Means of Escape, Fire Compartmentation
Building Information Modelling

A digital process producing a coordinated three-dimensional model of a facility with attached data, supporting clash detection, quantity take-off, and lifecycle information management.

Related: Clash Detection, Value Engineering
Clash Detection

Automated review of federated design models to identify physical or spatial conflicts between disciplines, such as ducts intersecting structural beams, before construction begins.

Related: Building Information Modelling
Value Engineering

A structured review that seeks to deliver required function at lowest whole-life cost by examining alternatives without reducing performance, quality, or safety.

Related: Whole Life Cost, Earned Value Management
Whole Life Cost

The total cost of an asset over its life, including acquisition, operation, maintenance, renewal, and disposal, used to compare design options on an economic basis.

Related: Value Engineering, Net Present Value
Net Present Value

The sum of discounted future cash flows minus initial investment, indicating whether a project adds value at a chosen discount rate; positive values favour acceptance.

Related: Discount Rate, Payback Period
Discount Rate

The rate used to convert future cash flows to present value, reflecting the time value of money and the risk or cost of capital for the investor.

Related: Net Present Value, Payback Period
Payback Period

The time required for cumulative savings or revenues to recover an initial investment, a simple screening measure that ignores cash flows occurring after recovery.

Related: Net Present Value, Discount Rate
Earned Value Management

A project control technique comparing budgeted cost of work performed against actual cost and planned schedule, yielding cost and schedule variance indices for forecasting.

Related: Critical Path Method, Value Engineering
Critical Path Method

A scheduling technique identifying the longest sequence of dependent activities that fixes project duration, so delay on any critical activity delays completion.

Related: Earned Value Management, Float
Float

The amount of time an activity can be delayed without delaying the project finish, distinguishing critical activities with zero float from those with schedule flexibility.

Related: Critical Path Method
Professional Negligence

Failure to exercise the reasonable skill and care expected of a competent practitioner in the same field, breaching the duty of care owed to clients and affected parties.

Related: Duty of Care, Conflict of Interest
Duty of Care

A legal and ethical obligation to avoid acts or omissions that could foreseeably cause harm to those who may reasonably be affected by one's professional work.

Related: Professional Negligence, Public Safety Paramountcy
Conflict of Interest

A situation where personal, financial, or other interests could improperly influence professional judgement, requiring prompt disclosure and management or withdrawal from the decision.

Related: Professional Negligence, Whistleblowing
Public Safety Paramountcy

The principle that the health, safety, and welfare of the public take precedence over obligations to clients or employers when professional judgements conflict.

Related: Duty of Care, Whistleblowing
Whistleblowing

Reporting suspected wrongdoing, unsafe practice, or regulatory breach to an appropriate authority, protected in many jurisdictions when made in good faith through proper channels.