AL General Contractor study materials
AL General Contractor study resources

AL General Contractor cheat sheet

AL General Contractor · Keep the key ideas within reach.

Quick reference

Business, Finance, and Project Administration

  • Retainage is commonly 5–10% withheld from each progress payment and released per contract terms at substantial completion or final acceptance.

  • Critical path method (CPM): the critical path is the longest continuous path through the schedule network and has total float equal to zero.

  • A change order is a written modification to contract scope, price, or time; it should be signed by owner and contractor before changed work proceeds.

  • Bid bonds are typically 5–10% of the bid amount; performance and payment bonds are typically 100% of the contract amount.

  • Lien deadlines are set by state statute and run from last furnishing of labor or materials or from recording a notice; a missed deadline extinguishes the lien right.

  • The schedule of values allocates the contract sum by work item, and progress payments are calculated as percent complete against those line items.

  • Cost variance = budgeted cost − actual cost; a negative variance indicates a cost overrun.

  • Workers' compensation insurance covers employee on-the-job injury; commercial general liability excludes employee bodily injury.

  • Liquidated damages are a fixed per-day amount stated in the contract; actual damages are proven losses and are not fixed in advance.

Quick reference

Site Work, Excavation, and Foundations

  • OSHA requires a protective system for trenches 5 ft (1.5 m) or deeper; a ladder, ramp, or stairs is required for egress at 4 ft depth.

  • Maximum allowable excavation slopes: Type A soil 0.75H:1V, Type B soil 1H:1V, Type C soil 1.5H:1V.

  • Spoil piles and heavy equipment must be kept at least 2 ft back from the trench edge.

  • Exterior footings must bear below the local frost depth to prevent frost heave.

  • Backfill is commonly compacted to 95% of maximum dry density as determined by ASTM D698 Standard Proctor.

  • Allowable soil bearing capacity is reported in psf by the geotechnical engineer and governs footing size.

  • Dewatering must lower groundwater below the excavation bottom before excavation and maintain it during work.

  • A competent person must inspect excavations daily and after rain or other hazard-increasing events before workers enter.

  • Benching, sloping, shoring, and shielding are the four OSHA protective system options for excavations.

Quick reference

Concrete and Masonry Construction

  • Concrete design strength f'c is the 28-day compressive strength used as the basis for structural design and acceptance.

  • A lower water-cement ratio increases compressive strength and reduces permeability; typical structural ranges are about 0.40–0.50.

  • The slump test (ASTM C143) measures concrete consistency and workability and is performed at the point of discharge.

  • Moist curing maintains moisture and temperature; 7 days is typical and longer periods are used for high-early-strength or severe exposure.

  • Formwork for soffits is removed only after concrete reaches the strength assumed in the shoring design; side forms may be removed earlier.

  • Specified rebar cover varies with exposure: 3 in for concrete cast against earth and 2 in for surfaces exposed to weather, unless the code requires otherwise.

  • Mortar types in descending strength are M, S, N, O, and K; Type N is common for above-grade moderate-load masonry.

  • CMU cores are filled with grout, consolidated with a vibrator, and verified by masonry prism tests when required.

  • Cold-weather concrete must be protected from freezing until it reaches about 500 psi.

Quick reference

Structural Steel, Metals, and Rough Carpentry

  • ASTM A992 is the common wide-flange structural steel grade with a minimum yield strength Fy = 50 ksi.

  • A325 and A490 are high-strength structural bolts used in pretensioned or slip-critical connections.

  • Shear studs welded through metal deck transfer horizontal shear between steel beams and the concrete slab, producing composite action.

  • Structural welding is governed by AWS D1.1; inspection includes visual examination and nondestructive testing such as ultrasonic or radiographic.

  • Steel joists and metal deck require temporary bracing until permanent bracing and deck attachment are complete.

  • Rough carpentry lumber must be grade-stamped and have moisture content suitable for its use, commonly kiln-dried (KD) framing.

  • Sprayed fireproofing on structural steel provides the fire-resistance rating specified for the building assembly.

  • Erection tolerances and responsibilities for structural steel follow the AISC Code of Standard Practice.

  • Joist hangers and metal connectors must be installed in accordance with the manufacturer's published instructions and approved submittals.

Quick reference

Thermal and Moisture Protection, Roofing, and Waterproofing

  • A vapor retarder is placed on the warm side of insulation to limit vapor diffusion and prevent condensation within the assembly.

  • Low-slope roofs have a slope less than 3:12; steep-slope roofs exceed 3:12.

  • Base flashing and counterflashing overlap at roof-to-wall junctions to shed water; counterflashing is anchored into a reglet or wall.

  • Below-grade waterproofing membrane is applied to the positive (water) side of the wall.

  • Insulation thermal resistance is stated as R-value; higher R-value means greater resistance to heat flow.

  • A typical low-slope roof assembly from bottom up is deck, vapor barrier, insulation, cover board, membrane, and flashing.

  • Positive drainage requires slope to drains or scuppers, commonly 1/4 in per ft on low-slope roofs.

  • A weather-resistant barrier is installed behind cladding and lapped shingle fashion so upper layers shed over lower layers.

Quick reference

Doors, Windows, and Finishes

  • A fire door rating is determined by the fire-resistance rating of the wall opening it protects, such as 20, 45, 60, or 90 minutes.

  • Egress doors require a minimum clear width of 32 in, with 36 in typical for the door leaf.

  • Tempered safety glazing is required in hazardous locations including doors, sidelights, and glazing close to the floor.

  • Gypsum board finish levels range from 1 to 5; Level 5 adds a skim coat for glossy paint or critical lighting.

  • NFRC ratings for windows include U-factor (heat loss) and SHGC (solar heat gain).

  • Panic hardware is required on egress doors serving high occupant loads and must release with a single motion.

  • Interior egress doors may not exceed 5 lb opening force under ADA, excluding fire-rated doors.

  • Storefront systems are non-load-bearing exterior framing, while curtain walls are designed to accommodate building movement and are often unitized.

Quick reference

Mechanical, Electrical, and Plumbing Coordination / Specialty Construction

  • Clash detection in a BIM model identifies conflicts among structural, mechanical, electrical, and plumbing systems before fabrication.

  • Sleeves and openings must be coordinated with structural drawings; cutting reinforcing steel requires structural engineer approval.

  • Sanitary drain pipe slope is commonly 1/4 in per ft for pipe 2 in and smaller, with lesser slopes permitted for larger pipe.

  • Duct hanger spacing and support methods follow SMACNA standards and the project specifications.

  • Plumbing systems are pressure-tested before concealment to verify joints are leak-free at the specified test pressure.

  • Fire sprinkler head spacing, coverage, and clearance below deflectors must comply with NFPA 13 and the approved shop drawings.

  • Conduit fill, box sizing, and conductor ampacity are governed by NFPA 70 (National Electrical Code).

  • Commissioning verifies that installed systems perform in accordance with the design intent and owner's project requirements.

Quick reference

Safety, Code Compliance, and Plan Reading

  • OSHA requires fall protection for construction workers exposed to falls of 6 ft or more, and 10 ft on scaffolds.

  • Guardrail top rails must be 42 in above the walking surface, plus or minus 3 in, with a midrail.

  • The IBC occupancy classification is based on building use and determines egress, fire separation, and construction type requirements.

  • Plan scale expresses drawing dimension to actual dimension, such as 1/4 in = 1 ft, and is used to measure distances.

  • Section markers on plans identify the drawing sheet and detail where a cut section is shown.

  • Elevation callouts show the height of a feature relative to a stated datum, commonly mean sea level or project zero.

  • GFCI protection is required for temporary receptacles on construction sites per OSHA and the NEC.

  • Fire extinguishers must be spaced according to hazard class and rated travel distance, and be mounted and accessible.

  • Door and window schedules list type marks, sizes, hardware sets, fire ratings, and glazing requirements for each opening.