AL General Contractor study plan
AL General Contractor · Give each week a clear focus.
8 weeks · About 6 hours per week
Business, Finance, and Project Administration (contracts, bidding, scheduling, cost control, insurance, liens)
Build a one-page matrix comparing lump-sum, cost-plus, cost-plus-with-GMP, and unit-price contracts, listing who carries quantity risk, who carries price risk, and how retainage is typically applied
Write, from memory, a 15-item checklist of bid-day requirements (bid bond, addenda acknowledgment, unit prices, alternates, withdrawal/revocation window) and then verify each item against a reference text
Draw a 15-activity precedence network by hand and compute earliest start, latest finish, total float, and the critical path for every activity
List the notice, recording, and foreclosure deadlines for mechanic's liens and state in one sentence how a lien waiver differs from a lien release
Your checkpoint
A six-page Domain 1 notebook section containing the contract matrix, the completed 15-activity CPM diagram with float values for each activity, and a dated lien-deadline sheet signed as verified
Business, Finance, and Project Administration (contracts, bidding, scheduling, cost control, insurance, liens) & Safety, Code Compliance, and Plan Reading
Solve five earned-value problems computing CPI, SPI, EAC, and VAC from given PV/EV/AC figures and explain in writing what each result signals to the owner
Tabulate builder's risk, general liability, workers' compensation, and umbrella coverage by what each pays for, typical limits, and who is the named insured
Identify on a set of construction drawings the scale of each sheet, the drawing index, the section and detail callouts, and the finish schedule reference
Convert five scale measurements from architectural to engineering scale and check each against a stated dimension string
Your checkpoint
A graded problem set of five earned-value calculations (all arithmetic shown) plus an annotated drawing set with 20 plan-reading callouts identified and labeled by type
Site Work, Excavation, and Foundations & Concrete and Masonry Construction
Classify five soil samples using a sieve analysis and Atterberg limits, and state the bearing capacity assumption each would support
Compute the active earth pressure and required shoring depth for a 12-foot-deep excavation in a given soil profile
Differentiate shallow spread footings, mat foundations, and deep pile/caisson systems by loading condition, settlement behavior, and dewatering needs
Sequence a concrete placement from subgrade prep through curing, naming the inspection hold points and the tests (slump, air content, cylinder breaks) taken at each stage
Your checkpoint
A one-page excavation-and-shoring plan plus a concrete placement sequence chart with all inspection hold points and required field tests marked
Concrete and Masonry Construction & Structural Steel, Metals, and Rough Carpentry
Specify mortar type (M, S, N, O) and grout for six given masonry conditions and justify each choice by compressive strength and exposure
Detail the reinforcement, grouting, and flashing requirements for a reinforced CMU retaining wall in a two-page sketch
Match five steel connection types (bolted shear, bolted slip-critical, welded moment, etc.) to their inspection method and acceptance criteria
Lay out floor, wall, and roof framing for a simple rectangular structure and identify the load path from roof sheathing to foundation
Your checkpoint
A two-page masonry detail set (reinforced wall section with flashing and grout notes) plus a framing plan with the complete vertical load path traced in color
Thermal and Moisture Protection, Roofing, and Waterproofing
Compare low-slope roof assemblies (built-up, modified bitumen, single-ply TPO/EPDM) by membrane type, seam method, slope range, and typical warranty term
Detail the flashing conditions at a roof penetration, a parapet, and a wall base for both roofing and below-grade waterproofing
Explain the purpose and placement of vapor retarders, air barriers, and drainage planes, and identify in a wall section which layer performs which function
Diagnose five common water-intrusion failure modes and prescribe the corrected detail for each
Your checkpoint
A five-detail waterproofing and roofing sketch portfolio (penetration, parapet, wall base, below-grade, plaza deck) each annotated with membrane, flashing, and drainage notes
Doors, Windows, and Finishes & Mechanical, Electrical, and Plumbing Coordination / Specialty Construction
Write the fire-rating, hardware, and egress requirements for door assemblies in a rated corridor and verify each against a code citation
Sequence the finish trades for a typical room (drywall, tape, prime, ceiling grid, flooring, paint, trim) and identify the inspection and lead-time gates between them
Produce a coordination drawing showing how a duct main, sprinkler main, plumbing waste line, and cable tray share a ceiling plenum without violating required clearances
List the rough-in inspections and pressure/leak tests required before concealment for plumbing, electrical, mechanical, and fire protection systems
Your checkpoint
A composite MEP/ceiling plenum coordination sketch with clearances dimensioned, plus a finish-trade sequence bar chart showing inspection hold points
Safety, Code Compliance, and Plan Reading
Build a site-specific safety plan outline covering the six focus areas (falls, struck-by, caught-in/between, electrical, excavations, cranes) with the control hierarchy for each
Identify the OSHA trigger thresholds for fall protection, trench shoring, scaffold erection, and confined-space entry and state the required response at each threshold
Perform a full takeoff of quantities (concrete volume, masonry units, drywall area) from a small plan set and compare results to a provided answer key
Cross-check a set of drawings against the written specifications and log every discrepancy found
Your checkpoint
A site-specific safety plan outline with all trigger thresholds cited, plus a completed quantity takeoff with a discrepancy log of at least five drawing-versus-spec conflicts
Business, Finance, and Project Administration (contracts, bidding, scheduling, cost control, insurance, liens) & Site Work, Excavation, and Foundations & Concrete and Masonry Construction & Structural Steel, Metals, and Rough Carpentry & Thermal and Moisture Protection, Roofing, and Waterproofing & Doors, Windows, and Finishes & Mechanical, Electrical, and Plumbing Coordination / Specialty Construction & Safety, Code Compliance, and Plan Reading
Complete three full-length timed practice exams and record the score by domain after each attempt
Re-teach the two lowest-scoring domains by writing a one-page summary of each from memory without notes
Rebuild the flashcard set for every domain, keeping only cards missed on the practice exams
Rehearse the calculation types most often missed (earned value, earth pressure, concrete volume, load path) until each is solved correctly twice in a row
Your checkpoint
A score-tracking sheet for three timed practice exams showing per-domain results and improvement, plus a final one-page summary sheet per weak domain
Milestones
Week 2: Score 80% or better on a self-written 25-question quiz covering contracts, bidding, scheduling, cost control, insurance, and liens
Week 4: Explain the structural load path and the concrete placement hold points aloud in under five minutes without notes, and score 75% or better on the Domain 2-4 question set
Week 6: Produce the MEP coordination sketch and finish sequence chart unaided, and correctly answer 8 of 10 flashcard prompts on roofing, waterproofing, doors, and finishes
Week 8: Average 80% or better across three full-length timed practice exams with no single domain below 70%