AMPP ICS: Alternative Design and Monitoring Options

AMPP ICS · Work through your exam, one topic at a time.

All guide sections

Alternative Design and Monitoring Options

What the exam expects

When conventional mitigation is impractical, alternative design and monitoring options apply. Candidates must know the options and their trade-offs:

  • Design alternatives: corrosion allowance, material upgrade, internal coating, chemical injection points, pigging facilities, and layout changes to avoid stagnant zones.
  • Monitoring alternatives: non-intrusive UT, guided-wave, acoustic emission, and remote monitoring where intrusive access is limited.
  • Risk-based inspection (RBI): prioritize inspection by likelihood and consequence.
  • Data integration: combine monitoring with process and inspection data.

Traps in questions

  • Treating non-intrusive methods as equivalent to intrusive probes; each has sensitivity and coverage limits.
  • Forgetting that design changes require re-evaluation of the corrosion control program.
  • Assuming RBI replaces monitoring; it prioritizes inspection, not chemical control.

Worked example

A line cannot be pigged and has no probe access. The correct alternative is non-intrusive UT plus guided-wave screening, with RBI prioritization, not simply accepting the risk. Rule of thumb: if you cannot measure intrusively, measure non-intrusively and prioritize by risk; never leave a line unmonitored without a documented rationale.