API 1169 · Keep the key ideas within reach.

Quick reference

Pre-Construction and Design Considerations

  • API 1169 establishes minimum inspection requirements for onshore pipeline construction from preconstruction through restoration.

  • Before construction, verify approved drawings, specifications, permits, landowner agreements, and environmental constraints match the work area.

  • The construction inspection plan defines inspection scope, hold points, witness points, frequencies, and documentation requirements.

  • Hold points require inspector acceptance before work proceeds; witness points require notification but not necessarily stoppage.

  • Verify contractor quality procedures, welding procedures, coating procedures, and testing plans are approved before mobilization.

  • Confirm the chief inspector and craft inspectors have qualifications and authority consistent with API 1169 and project requirements.

  • Preconstruction meetings should establish communication, document control, nonconformance reporting, and inspection coverage for all shifts.

  • Check that survey control, alignment sheets, and as-built recording methods are established before clearing or grading.

Quick reference

Materials and Equipment

  • Verify pipe and components carry specified markings, heat numbers, size, grade, wall thickness, and specification.

  • Match mill test reports to heat numbers and confirm chemistry and mechanical properties meet project requirements.

  • Reject pipe with dents, gouges, ovality, coating damage, or out-of-tolerance dimensions unless repair is approved.

  • Store pipe on supports that prevent rolling, ground contact, and coating damage; cap ends to keep out water and debris.

  • Inspect lifting equipment, slings, and padding to prevent coating and pipe wall damage during handling.

  • Confirm inspection and test equipment has current calibration traceable to recognized standards.

  • Verify consumables such as electrodes and coating materials are stored, handled, and used per manufacturer requirements.

  • Check that equipment used for excavation, bending, welding, coating, and testing is suitable and maintained.

Quick reference

Excavation, Trenching, and Backfill

  • Classify soil and rock before excavation; use protective systems where required by OSHA or project safety plans.

  • Keep spoil, equipment, and materials back from trench edges to reduce surcharge and prevent cave-ins.

  • Provide safe access and egress within 25 feet of travel for workers in trenches 4 feet or deeper, per OSHA.

  • Inspect excavations daily and after rain or other hazard-increasing events before workers enter.

  • Trench width and depth must allow pipe installation, bedding, coating protection, and safe worker access.

  • Bedding must provide uniform support and protect coating; backfill must be free of debris, frozen material, and excessive rock.

  • Control water with pumps, ditches, or diversions to keep trench bottom stable and dry.

  • Verify crossings, utilities, and foreign pipelines are located, exposed, supported, and protected before excavation.

Quick reference

Pipe Installation, Bending, and Alignment

  • Check pipe grade, wall thickness, and heat number before installation to confirm the correct material is used.

  • Field bends must meet specified radius, ovality, and wrinkle limits; reject bends with cracking or coating damage.

  • Use internal line-up clamps to align pipe ends, maintain root gap, and control high-low misalignment.

  • Verify alignment and elevation against drawings before welding; correct unsupported spans and sags.

  • Lowering-in must use padding and multiple slings to prevent coating damage and excessive pipe stress.

  • Verify pipe ends are clean and free of damage before fit-up; remove contaminants that could affect weld quality.

  • Confirm crossing spans, casings, and supports are installed at required locations and clearances.

  • Record bend locations and angles for as-built documentation and future excavation safety.

Quick reference

Welding and Weld Inspection

  • Welding must follow an approved Welding Procedure Specification supported by a qualified Procedure Qualification Record.

  • Welders and welding operators must be qualified for the process, position, and material they will weld.

  • Verify preheat, interpass temperature, filler metal, and joint preparation meet the WPS before welding.

  • Visual inspection checks for cracks, undercut, porosity, incomplete fusion, high-low, and cap profile.

  • Nondestructive examination methods, coverage, and acceptance criteria must follow project specifications and referenced standards.

  • Repair welds require approved procedures and re-inspection; remove or repair unacceptable defects before coating.

  • Record weld locations, welder identification, inspection results, and repairs in weld logs.

  • Protect completed welds from moisture and rapid cooling when required by the WPS.

Quick reference

Coating, Corrosion Control, and Lowering-In

  • Verify coating surface preparation meets the specified cleanliness and profile before application.

  • Measure dry film thickness after curing and compare with specification minimum and maximum limits.

  • Perform holiday detection on coatings where required to find pinholes, voids, and thin areas.

  • Field joint coating must match the mainline coating system and be applied per approved procedure.

  • Repair coating damage before lowering-in; recheck repaired areas for thickness and holidays.

  • Inspect lowering-in operations for coating damage and pipe stress; use padded slings and rollers.

  • Cathodic protection tests verify pipe-to-soil potential and electrical isolation meet design criteria.

  • Backfill material adjacent to coated pipe must be free of sharp rock and debris that could damage coating.

Quick reference

Pressure Testing, Commissioning, and Restoration

  • Hydrostatic testing verifies strength and leak tightness by filling the section with water and holding specified test pressure.

  • Test pressure and hold time must follow design, code, and project requirements; monitor and record pressure and temperature.

  • Test water must meet project limits for chlorides, solids, corrosivity, and biological content.

  • Air or gas testing is limited by code and project requirements; water is preferred for hydrostatic strength testing.

  • Dewater and dry the pipeline after testing as required to prevent corrosion and hydrate formation.

  • Commissioning verifies valves, launchers, receivers, instrumentation, and controls operate as designed.

  • Restoration includes regrading, erosion control, revegetation, drainage repair, and removal of temporary facilities.

  • Final inspection confirms as-built records, test records, and restoration acceptance are complete.

Quick reference

Safety, Environmental, and Regulatory Compliance

  • Excavations 5 feet or deeper require protective systems unless the competent person determines stable rock or an acceptable slope.

  • Atmospheric testing is required before entry into confined spaces and must continue while workers are inside.

  • Spill prevention, containment, and response plans must cover fuel, oil, chemicals, and hazardous materials on site.

  • Erosion and sediment controls must be installed before ground disturbance and maintained until stabilization.

  • Wetland, waterbody, and cultural resource restrictions must be verified against permits before crossing or clearing.

  • Traffic control, flagger, and work zone plans must protect workers and the public during construction.

  • Hazard communication, PPE, and emergency response requirements apply to all construction activities.

  • Report environmental releases, permit deviations, and safety incidents promptly to the required authorities.