API 1169 study materials
API 1169 study resources

API 1169 flashcards

API 1169 · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

API 1169
API Recommended Practice 1169 sets minimum inspection requirements for onshore pipeline construction, covering preconstruction through restoration.
Construction inspection plan
A project-specific document defining inspection scope, hold points, frequencies, documentation, and responsibilities before pipeline construction begins.
Hold point
A defined stage in construction where work must stop and inspector acceptance is required before the activity may proceed.
Right-of-way verification
Preconstruction check confirming landowner agreements, permits, access, boundaries, and environmental constraints match approved construction drawings before clearing.
Heat number traceability
A unique identifier linking pipe or components to their mill test report, enabling verification of chemistry and mechanical properties.
Mill test report
Documentation from the manufacturer reporting chemical composition and mechanical test results for a specific heat or lot of pipe.
Equipment calibration records
Current documentation showing inspection and test equipment readings are traceable to recognized standards within the required calibration interval.
Pipe storage inspection
Checks that pipe is supported, restrained, protected from damage, and kept clean while stored before installation.
Trench spoil setback
Excavated material and equipment must be placed away from trench edges per project requirements to reduce surcharge and prevent cave-in.
Competent person
An individual capable of identifying existing and predictable excavation hazards and authorized to take prompt corrective action.
Bedding requirement
Specified material and thickness placed under and around pipe to provide uniform support and protect coating from damage.
Trench water control
Use of pumps, ditches, or diversions to keep the trench bottom dry and stable during excavation and pipe installation.
Bend radius check
Verification that field bends do not exceed specified radius and that pipe wall wrinkling or ovality remains within allowable limits.
Internal line-up clamp
Device inserted inside pipe ends to align the joint, maintain root gap, and reduce misalignment before welding.
Pipe sag inspection
Check that supported pipe has no unsupported spans or sags exceeding project limits before backfill.
Cold field bend
Field bending performed without heating, using a bending machine that controls curvature and avoids excessive ovality or coating damage.
Welding Procedure Specification
A qualified document specifying welding variables, filler metal, preheat, and technique required to produce sound pipeline welds.
Procedure Qualification Record
Record documenting the test weld and destructive results that qualified a welding procedure specification for its intended use.
Welder qualification test
Performance test demonstrating a welder can produce welds meeting specified visual and nondestructive examination acceptance criteria.
Weld visual inspection
Examination of completed welds for defects such as cracks, undercut, porosity, high-low misalignment, and inadequate cap profile.
Surface preparation grade
Cleanliness level required before coating application, commonly defined by standards such as near-white or commercial blast cleaning.
Dry film thickness
Cured coating thickness measured after application and compared with specification minimum and maximum limits.
Holiday detection
Electrical test used to locate pinholes, voids, or thin spots in a protective pipeline coating.
Cathodic protection
System that applies electrical current to buried pipe to reduce corrosion by making the pipe surface cathodic.
Hydrostatic test
Pressure test in which the completed pipeline section is filled with water and held at specified pressure to verify strength and leak tightness.
Test pressure hold time
Specified duration that a pipeline test section must remain at test pressure without pressure loss before acceptance.
Pressure test water quality
Water used for hydrostatic testing must meet project limits for corrosivity, solids, chlorides, and biological content.
Restoration inspection
Verification that disturbed land is regraded, stabilized, revegetated, and drainage restored according to permits and project plans.
Excavation protective system
Sloping, benching, shoring, or shielding used to protect workers from cave-ins in trenches and excavations.
Spill prevention plan
Site-specific plan identifying fuel and chemical storage, containment, inspection, and response procedures to prevent environmental releases.
Confined space entry permit
Written authorization required before entering a confined space, documenting hazards, atmospheric testing, attendants, and rescue arrangements.
Environmental permit compliance
Inspector verifies construction activities stay within wetland, waterway, erosion, noise, and land-use conditions stated in project permits.