API 1169 · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Pre-Construction and Design Considerations

  • List the document set required before mobilization (alignment sheets, P&ID, specifications, permits, crossing agreements) and state the purpose of each

  • Explain how a pre-construction survey, right-of-way limits, and environmental/cultural clearances drive the construction work plan

  • Trace the permit and notification workflow for a road, railroad, or waterbody crossing and identify who signs off at each step

  • Convert alignment sheet data into a written list of constructability risks for a hypothetical 5-mile spread

Your checkpoint

A one-page written constructability review of a self-chosen scenario (terrain, two crossings, one residential segment) listing at least 10 pre-construction risks with the governing document for each

Week 2

Materials and Equipment

  • Classify line pipe by grade, wall thickness, seam type, and spec, and state what each designation controls on the job

  • Describe the receiving inspection sequence for pipe and fittings and the disposition options for damaged or out-of-spec material

  • Explain storage, stacking, and handling requirements that protect the pipe and its coating before installation

  • Identify the inspection and documentation requirements for lifting equipment, slings, and pipe-handling gear used on a spread

  • Compare welding consumable, valve, and fitting handling requirements and explain why each differs

Your checkpoint

A 25-card flashcard deck covering pipe/fitting identification, receiving acceptance criteria, and equipment inspection points, with a 10-question self-quiz scored at 80% or better

Week 3

Excavation, Trenching, and Backfill

  • Determine trench width, depth of cover, and minimum clearance requirements for a stated pipe size and class of location

  • Classify soils and select the correct sloping, benching, or shoring approach for a described excavation

  • Sequence a trenching operation end to end: spoil placement, dewatering, access/egress, and protection of exposed utilities

  • Specify bedding, padding, and backfill compaction requirements and explain how each protects the coating and the pipe

  • Explain the competent-person duties and daily inspection record for trenching work

Your checkpoint

A written trench plan for three scenarios (stable clay, saturated sand, existing utility crossing) including dimensions, protective system, bedding, and backfill method, checked against your reference notes

Week 4

Pipe Installation, Bending, and Alignment & Excavation, Trenching, and Backfill

  • Calculate allowable bend angle, radius, and resulting offset for given pipe size and specified minimum bend radius

  • Differentiate field bends, cold bends, and wrinkle bends, and state the acceptance limits for each

  • Describe stringing, alignment, and tie-in sequencing, including how cold springing and grade changes are controlled

  • Identify alignment tolerances, ditch line deviation limits, and the inspection points that must be signed off before lowering-in

  • Re-work the three trench plans from week 3 to fit the bend and alignment limits of a curved alignment

Your checkpoint

A bend-and-alignment worksheet with worked calculations for four pipe sizes and a written list of hold points from stringing through tie-in

Week 5

Welding and Weld Inspection

  • Explain how a WPS and supporting PQR are qualified, and identify the essential variables a field inspector verifies on the spread

  • State welder qualification and requalification requirements and describe what the inspector checks before a production weld starts

  • Compare visual, radiographic, ultrasonic, magnetic particle, and liquid penetrant inspection for what each detects and when it is used

  • Classify common weld defects and state the acceptance or rejection disposition and repair/retest logic

  • Explain preheat, weather protection, and repair-rate tracking and how each affects weld acceptance

Your checkpoint

A weld inspection checklist covering pre-weld, in-process, and post-weld verification, plus a written decision tree for a rejected weld through repair and retest

Week 6

Coating, Corrosion Control, and Lowering-In & Welding and Weld Inspection

  • Compare plant-applied and field-applied coating systems and state where each is used and how each is inspected

  • Describe surface preparation, application, and cure requirements, and identify the conditions that stop coating work

  • Explain holiday detection, coating inspection before lowering-in, and documentation of repaired coating

  • Describe cathodic protection fundamentals and how coating condition, soil resistivity, and test stations interact

  • Plan a lowering-in sequence: equipment spacing, sling type and placement, buoyancy control, and sag protection, and reconcile it with the weld hold points from week 5

Your checkpoint

A lowering-in plan for a 1,000-foot section naming equipment, spacing, and sling placement, plus a coating defect log with at least 8 defect types and their repair method

Week 7

Pressure Testing, Commissioning, and Restoration & Safety, Environmental, and Regulatory Compliance

  • Plan a hydrostatic strength and leak test: test section limits, water source and disposal, pressure hold, temperature effects, and acceptance criteria

  • Sequence commissioning activities including purging, drying, tie-in, and startup documentation

  • Build a restoration plan covering cleanup, backfill stabilization, erosion control, and revegetation, with the inspection that closes each item

  • Identify the safety and environmental requirements that apply across all phases: excavation, confined space, hydrostatic test water handling, spill response, and waste disposal

  • Map each major activity in the plan to the regulatory notification, permit, or record that governs it

Your checkpoint

A combined pressure-test and restoration plan for one test section, including test parameters, water handling, restoration steps, and a permit/notification matrix with at least 12 entries

Week 8

Pre-Construction and Design Considerations & Materials and Equipment & Excavation, Trenching, and Backfill & Pipe Installation, Bending, and Alignment & Welding and Weld Inspection & Coating, Corrosion Control, and Lowering-In & Pressure Testing, Commissioning, and Restoration & Safety, Environmental, and Regulatory Compliance

  • Write and answer 60 original practice questions distributed by domain weighting and score 85% or better overall

  • Re-teach any domain scoring below 80% by rewriting its key limits and decision rules from memory

  • Recite from memory the numeric thresholds you are least sure of, flagging each as confirmed or needs-review

  • Build a one-page pre-exam reference sheet limited to items you have personally verified

Your checkpoint

A scored 60-question self-authored practice exam with an error log listing every missed item, its domain, the correct rule, and the correction made

Milestones

Week 2: Score 80% or higher on the 10-question self-quiz and explain, without notes, the difference between a material rejection and a material concession

Week 4: Complete the bend-and-alignment worksheet with all four calculations correct and list every hold point from stringing through tie-in with no omissions

Week 6: Walk through a rejected weld and a coating defect end to end - detection, disposition, repair, retest, and documentation - in under five minutes each without notes

Week 8: Score 85% or higher on the 60-question practice exam with no domain below 80%, and hold a reference sheet containing only verified items