Pharma Logistics Dispensing Rollout - inspection instead of quality, and a rubber-stamp change board
Pharma Logistics is rolling out a new dispensing and label-printing system across 40 sites in 10 months. There is no quality plan. At each go-live the project manager personally checks 20 randomly selected prescriptions and signs a sheet reading "system working" - the same wording used as the acceptance criteria. Nothing checks whether the rollout method itself is being applied consistently from site to site. Twenty-three change requests have been raised since the baseline was agreed; all were approved by the project manager by email, typically within a day, none has a recorded impact assessment, and scope has grown by roughly 18%. One approved change - integrating a third-party label printer - features in the post-incident review at site 12, where 60 prescriptions were printed with the wrong dosage. The risk "third-party printer incompatibility" had sat on the register for four months with no owner assigned.
1. Explain the difference between quality planning, quality assurance and quality control, and identify which are missing or being misapplied here.
Read the worked answer
Quality planning decides what quality means and how it will be achieved: the standards to be applied, acceptance criteria per deliverable, the quality activities and who performs them, and the review/approval gates. Missing entirely at Pharma Logistics - the only criteria are the words "system working", which are not measurable and cannot be tested.
Quality assurance (QA) is process-focused and preventive: it confirms that the agreed method is being followed consistently - audits, method statements, checklists, peer review of the rollout pack, verification that site 27 is doing what site 4 did. Missing: nothing checks consistency between sites, so variation goes undetected until an incident.
Quality control (QC) is product-focused and detective: inspecting, testing or measuring the output against the acceptance criteria - the 20-prescription check the project manager performs.
What is happening: the project manager is doing QC personally, and only QC. Three consequences:
- There is nothing to control against - no criteria, so the check cannot fail and therefore proves nothing.
- The project manager is marking their own work. QC should be independent of the person who built or installed the deliverable; self-inspection at go-live is assurance in name only.
- Sampling 20 prescriptions at one moment checks the output but not the process, so a printer-integration fault introduced at design can pass site acceptance and surface later.
Fix: write a quality plan with measurable acceptance criteria per site, define QA activities (rollout audits, standard installation checklist, independent reviewer), and separate QC from the person accountable for delivery.
2. Evaluate the current change control process and recommend what it should be, keeping it proportionate to a 40-site rollout.
Read the worked answer
Evaluation. Twenty-three changes, all approved by the project manager, by email, within a day, with no impact assessment, and 18% scope growth. This is not change control; it is a change log. Three specific defects:
- No impact assessment. Without analysis of effect on cost, schedule, quality, risk and benefits, approval is an opinion. The third-party printer integration is the direct consequence - nobody weighed the integration risk before saying yes.
- Wrong decision-maker. The project manager is accountable for delivering the baseline; allowing them to move that baseline unilaterally means there is no control at all. The authority to approve must sit with whoever owns the funds and the business case - the sponsor - above a defined threshold.
- No baseline discipline. With 18% growth, the original estimates and the business case are now meaningless, and nobody knows the true cost or date.
A proportionate process for 40 sites:
- Single front door: one change request form - what, why, who, urgency.
- Tiered thresholds: minor changes (below, say, £5k and no schedule impact, no safety or regulatory effect) approved by the project manager and logged; anything above, or touching patient safety, regulatory compliance or go-live dates, escalated to the sponsor with a written impact assessment.
- Mandatory impact assessment across scope, time, cost, quality, risk and benefits - one page is enough.
- Decision within a stated turnaround (e.g. 5 working days), so control does not become paralysis across 40 sites.
- Rebaseline and re-communicate after approval, and re-issue the baseline at a defined point so the 18% drift stops growing unnoticed.
- Change board need only be the sponsor plus the operations lead; a full board for a 40-site rollout would be disproportionate if thresholds are set sensibly.
3. The site-12 dosage error: distinguish risk from issue here, explain how it should have been handled, and state what must happen now.
Read the worked answer
Risk vs issue. A risk is an uncertain future event that might occur and would affect objectives if it did; an issue is something that has happened and is now affecting the project, requiring management action rather than analysis. "Third-party printer incompatibility" was a risk for four months. It became an issue the moment 60 prescriptions printed with the wrong dosage.
How it should have been handled as a risk. Registration is not management. A live risk needs: a named owner who is accountable for the response (here, the integration lead - not the project manager by default), an assessed probability and impact (impact clearly at the patient-safety end of the scale), a defined response (e.g. a compatibility test before any site goes live with the third party, plus a fallback to the incumbent printer), and a trigger - a supplier confirmation, a test result, a first site go-live. A risk with no owner has no response; it is a wish.
What must happen now:
- Containment first. Site 12 dispensing suspended or reverted to the approved fallback; identify and contact every patient affected; check all 39 other sites for the same printer configuration. Safety outranks schedule.
- Transfer to the issue log - assigned owner, actions, target resolution, escalation.
- Escalate to the sponsor and beyond - a dosage error is a regulatory matter; the clinical/governance route must be triggered, not just the project route.
- Treat as evidence, not an accident: review every approved change for similar unassessed integration risk, and check whether the missing quality plan allowed a design fault to pass site acceptance.
- Update the risk register - the risk was real, was logged, and was ignored. That is the finding the post-incident review should lead with.