APM PFQ study materials
APM PFQ study resources

APM PFQ study plan

APM PFQ · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Risk and issue management

  • Distinguish between risk, issue, assumption, and dependency by writing one worked example of each from a project you have seen

  • Construct a risk register template with columns for risk description, cause, effect, probability, impact, proximity, owner, and response

  • Apply the four risk responses (avoid, reduce, transfer, accept) to six short scenarios and justify each choice in one sentence

  • Explain how issue management differs from risk management in timing, ownership, and escalation path

  • Describe the escalation route a risk or issue takes through a governance structure, from team to sponsor

Your checkpoint

A completed one-page risk register for a project you know, containing at least 8 risks scored for probability and impact, each with an owner and a chosen response

Week 2

Quality and change control

  • Separate quality planning, quality assurance, and quality control, and state which life cycle stage each is most active in

  • Map a change control process end to end: request, impact assessment, decision, implementation, communication, closure

  • Explain configuration management and why it underpins effective change control

  • Describe how tolerance limits and change thresholds determine who can approve a change

  • Answer 25 practice questions covering risk, issue, quality, and change, then classify every error by root cause

Your checkpoint

A text-based flow diagram of a change control process with approval thresholds marked, plus an error log from 25 questions sorted by cause

Week 3

Project life cycles

  • Compare linear, iterative, incremental, and hybrid life cycles and state the project conditions that favour each

  • Map the phases of a project (concept, definition, implementation, handover and closure) to the activities and decisions occurring in each

  • Explain how gate or stage boundary reviews control progression between phases

  • Relate the extended project life cycle to benefits realisation after handover

  • Identify which life cycle type would suit four contrasting project scenarios and defend each recommendation

Your checkpoint

A one-page comparison table of four life cycle types scored against at least five criteria including uncertainty, stakeholder involvement, and frequency of deliverables

Week 4

Success and benefits management

  • Distinguish project success criteria from success factors and give three examples of each

  • Convert three project outputs into measurable outcomes and benefits with units, baselines, and target dates

  • Explain the benefits management process from identification through definition, planning, realisation, and review

  • Draft a short business case including a simple options appraisal and a justification section

  • Explain why benefits ownership sits outside the project team in most governance models

Your checkpoint

A benefits profile for three benefits, each with a measure, baseline, target, owner, and expected realisation date

Week 5

Governance and project roles

  • Explain the four purposes of governance: direction setting, decision-making, assurance, and escalation

  • Describe the responsibilities of sponsor, project manager, team members, steering group, and PMO

  • Differentiate project assurance from project support and identify who provides each

  • Explain how governance structures scale with project size, risk, and organisational context

  • Trace a decision from the team level up to the steering group and identify who could overrule it

Your checkpoint

A responsibility matrix mapping six roles against eight decisions or activities, marking who is responsible, accountable, consulted, and informed

Week 6

Stakeholder and communication management

  • Plot at least ten stakeholders on a power and interest grid and tailor an engagement approach to each quadrant

  • Write a stakeholder engagement plan specifying approach, frequency, and owner for each key stakeholder

  • Select appropriate communication channels and formats for different audiences, including sponsor, end users, and suppliers

  • Explain the components of a communication plan: what, when, how, to whom, and how feedback is captured

  • Identify three likely causes of communication breakdown on a project and a mitigation for each

Your checkpoint

A stakeholder grid with at least ten named stakeholders plus a communication plan table covering audience, message, channel, frequency, and owner

Week 7

Planning and scheduling

  • Decompose a sample project scope into a work breakdown structure with at least three levels

  • Sequence activities and identify dependencies, then derive the critical path through the network

  • Calculate total float for non-critical activities and explain the schedule implication of float being consumed

  • Compare estimating approaches including analogous, parametric, three-point, and bottom-up, and select one for a given situation

  • Explain how the schedule baseline links to resource planning and cost baseline development

Your checkpoint

A mini schedule for a sample project with at least twelve tasks, dependencies, durations, the identified critical path, and a short resource and cost outline

Week 8

Risk and issue management & Quality and change control

  • Re-attempt every question in your error log and confirm each cause of error is now resolved

  • Complete two full timed practice papers under exam conditions and record domain-level scores

  • Compile a one-page recall sheet of definitions, process steps, and role boundaries across all seven domains

  • Target the two weakest domains from your mock scores with a focused two-hour revision block each

  • Rehearse the distinction between risk and issue, and between quality assurance and quality control, until both can be explained in under thirty seconds

Your checkpoint

A completed mock exam scoresheet showing percentage per domain, an updated error log, and a dated three-item remediation list for any domain still below 70 percent

Milestones

Week 2: Score at least 70 percent on a closed-book 20-question set covering risk, issue, quality, and change, and have a populated error log by cause

Week 4: Explain the difference between outputs, outcomes, and benefits without notes, and score at least 70 percent on a 20-question set covering risk, quality, life cycles, and benefits

Week 6: Produce a stakeholder grid and communication plan from a blank sheet in under 30 minutes, and score at least 70 percent on a 25-question set covering governance, roles, and stakeholders

Week 8: Achieve at least 75 percent overall on each of two full timed mock papers, with no single domain below 65 percent