APM PFQ study plan
APM PFQ · Give each week a clear focus.
8 weeks · About 7 hours per week
Risk and issue management
Distinguish between risk, issue, assumption, and dependency by writing one worked example of each from a project you have seen
Construct a risk register template with columns for risk description, cause, effect, probability, impact, proximity, owner, and response
Apply the four risk responses (avoid, reduce, transfer, accept) to six short scenarios and justify each choice in one sentence
Explain how issue management differs from risk management in timing, ownership, and escalation path
Describe the escalation route a risk or issue takes through a governance structure, from team to sponsor
Your checkpoint
A completed one-page risk register for a project you know, containing at least 8 risks scored for probability and impact, each with an owner and a chosen response
Quality and change control
Separate quality planning, quality assurance, and quality control, and state which life cycle stage each is most active in
Map a change control process end to end: request, impact assessment, decision, implementation, communication, closure
Explain configuration management and why it underpins effective change control
Describe how tolerance limits and change thresholds determine who can approve a change
Answer 25 practice questions covering risk, issue, quality, and change, then classify every error by root cause
Your checkpoint
A text-based flow diagram of a change control process with approval thresholds marked, plus an error log from 25 questions sorted by cause
Project life cycles
Compare linear, iterative, incremental, and hybrid life cycles and state the project conditions that favour each
Map the phases of a project (concept, definition, implementation, handover and closure) to the activities and decisions occurring in each
Explain how gate or stage boundary reviews control progression between phases
Relate the extended project life cycle to benefits realisation after handover
Identify which life cycle type would suit four contrasting project scenarios and defend each recommendation
Your checkpoint
A one-page comparison table of four life cycle types scored against at least five criteria including uncertainty, stakeholder involvement, and frequency of deliverables
Success and benefits management
Distinguish project success criteria from success factors and give three examples of each
Convert three project outputs into measurable outcomes and benefits with units, baselines, and target dates
Explain the benefits management process from identification through definition, planning, realisation, and review
Draft a short business case including a simple options appraisal and a justification section
Explain why benefits ownership sits outside the project team in most governance models
Your checkpoint
A benefits profile for three benefits, each with a measure, baseline, target, owner, and expected realisation date
Governance and project roles
Explain the four purposes of governance: direction setting, decision-making, assurance, and escalation
Describe the responsibilities of sponsor, project manager, team members, steering group, and PMO
Differentiate project assurance from project support and identify who provides each
Explain how governance structures scale with project size, risk, and organisational context
Trace a decision from the team level up to the steering group and identify who could overrule it
Your checkpoint
A responsibility matrix mapping six roles against eight decisions or activities, marking who is responsible, accountable, consulted, and informed
Stakeholder and communication management
Plot at least ten stakeholders on a power and interest grid and tailor an engagement approach to each quadrant
Write a stakeholder engagement plan specifying approach, frequency, and owner for each key stakeholder
Select appropriate communication channels and formats for different audiences, including sponsor, end users, and suppliers
Explain the components of a communication plan: what, when, how, to whom, and how feedback is captured
Identify three likely causes of communication breakdown on a project and a mitigation for each
Your checkpoint
A stakeholder grid with at least ten named stakeholders plus a communication plan table covering audience, message, channel, frequency, and owner
Planning and scheduling
Decompose a sample project scope into a work breakdown structure with at least three levels
Sequence activities and identify dependencies, then derive the critical path through the network
Calculate total float for non-critical activities and explain the schedule implication of float being consumed
Compare estimating approaches including analogous, parametric, three-point, and bottom-up, and select one for a given situation
Explain how the schedule baseline links to resource planning and cost baseline development
Your checkpoint
A mini schedule for a sample project with at least twelve tasks, dependencies, durations, the identified critical path, and a short resource and cost outline
Risk and issue management & Quality and change control
Re-attempt every question in your error log and confirm each cause of error is now resolved
Complete two full timed practice papers under exam conditions and record domain-level scores
Compile a one-page recall sheet of definitions, process steps, and role boundaries across all seven domains
Target the two weakest domains from your mock scores with a focused two-hour revision block each
Rehearse the distinction between risk and issue, and between quality assurance and quality control, until both can be explained in under thirty seconds
Your checkpoint
A completed mock exam scoresheet showing percentage per domain, an updated error log, and a dated three-item remediation list for any domain still below 70 percent
Milestones
Week 2: Score at least 70 percent on a closed-book 20-question set covering risk, issue, quality, and change, and have a populated error log by cause
Week 4: Explain the difference between outputs, outcomes, and benefits without notes, and score at least 70 percent on a 20-question set covering risk, quality, life cycles, and benefits
Week 6: Produce a stakeholder grid and communication plan from a blank sheet in under 30 minutes, and score at least 70 percent on a 25-question set covering governance, roles, and stakeholders
Week 8: Achieve at least 75 percent overall on each of two full timed mock papers, with no single domain below 65 percent