APM PFQ · Keep the key ideas within reach.

Quick reference

Project life cycles

  • A generic project life cycle has phases: concept, definition, deployment, transition and benefits realisation.

  • A phase gate or stage gate is a decision point at a phase boundary; outcomes are go, no-go or conditional go.

  • Linear life cycles complete phases largely sequentially and suit stable, well-understood requirements.

  • Iterative life cycles repeat develop-review cycles and suit evolving requirements and higher uncertainty.

  • Hybrid life cycles combine linear and iterative elements, such as predictive planning with iterative delivery.

  • A project is a temporary endeavour to create a unique product, service or result; business as usual is ongoing.

  • Outputs are produced by the project; outcomes are changed states; benefits are measurable advantages from outcomes.

  • The project life cycle is shorter than and sits within the product life cycle.

Quick reference

Success and benefits management

  • Success criteria are measures used to judge success; success factors are conditions that increase the chance of success.

  • Typical success criteria include time, cost, quality, scope, stakeholder satisfaction and benefits achieved.

  • Benefits are measurable improvements perceived as positive by stakeholders; dis-benefits are negative effects.

  • Output to outcome to benefit: outputs enable outcomes, and outcomes enable benefits.

  • A benefit profile records benefit owner, metric, baseline, target, timing and measurement method.

  • Benefits realisation often continues after project closure and requires a named benefit owner.

  • The business case should justify the project on expected benefits versus costs and risks.

  • Benefit dependency networks or maps show how outputs and changes lead to benefits.

Quick reference

Governance and project roles

  • Governance defines decision rights, accountability, oversight and escalation for a project.

  • The sponsor is accountable for the business case and project success; the project manager manages day-to-day delivery.

  • A project board or steering group provides senior direction and key approvals; common roles are sponsor, senior user and senior supplier.

  • The PMO provides standards, templates, reporting, assurance and coordination; its authority can be supportive, controlling or directive.

  • RACI: Responsible does the work, Accountable owns the outcome, Consulted gives input, Informed is updated.

  • Single point of accountability means each deliverable or decision has one accountable owner.

  • Stage-gate approval is a governance control that authorises work and release of funds.

  • Project assurance independently checks that governance, risk and quality requirements are being met.

Quick reference

Stakeholder and communication management

  • Stakeholders are individuals or groups that affect, are affected by, or perceive themselves to be affected by the project.

  • Power-interest grid: high power and high interest means manage closely; high power and low interest means keep satisfied; low power and high interest means keep informed; low power and low interest means monitor.

  • Engagement levels are unaware, resistant, neutral, supportive and leading.

  • Communication channels among n people = n(n-1)/2; for 8 people this gives 28 channels.

  • A communication plan specifies audience, message, frequency, method, owner and feedback mechanism.

  • Communication methods include push such as email or reports, pull such as portals, and interactive such as meetings or workshops.

  • Stakeholder analysis records interest, influence, attitude, expectations and engagement strategy.

  • Effective communication requires two-way feedback, not only broadcast of information.

Quick reference

Planning and scheduling

  • A WBS decomposes scope into deliverables and work packages; work packages can be estimated and scheduled.

  • A network diagram shows activity dependencies; a Gantt chart shows activities against a time scale.

  • The critical path is the longest dependent path through the network and determines the minimum project duration.

  • Float = LS - ES = LF - EF; critical activities have zero or negative float.

  • Dependency types are finish-to-start, start-to-start, finish-to-finish and start-to-finish.

  • PERT expected duration = (optimistic + 4 x most likely + pessimistic) / 6.

  • A milestone has zero duration and marks a significant event or approval point.

  • Resource levelling may extend duration to resolve over-allocation; smoothing reduces peaks without deliberately changing the critical path.

  • A baseline is the approved version of scope, schedule and cost against which performance is measured.

Quick reference

Risk and issue management

  • A risk is an uncertain event that may affect objectives; an issue has already occurred and is certain.

  • Risk process: identify, assess probability and impact, plan responses, implement responses, then monitor and review.

  • Risk score = probability x impact; higher scores are prioritised.

  • Threat responses are avoid, transfer, mitigate and accept; opportunity responses are exploit, share, enhance and accept.

  • The risk owner is accountable for managing a risk; an action owner implements a specific response.

  • Risk appetite is willingness to accept risk; risk tolerance is the allowable variation around objectives.

  • A RAID log records risks, assumptions, issues and dependencies.

  • Contingency reserves cover known risks; management reserves cover unknown risks.

  • Issues are recorded in an issue log with owner, impact, priority, actions and status.

Quick reference

Quality and change control

  • Quality planning defines standards and acceptance criteria; assurance checks processes; control checks products.

  • Quality control uses inspection and testing against acceptance criteria; quality assurance uses audits and process reviews.

  • The PDCA cycle is Plan, Do, Check, Act and supports continuous improvement.

  • Change control steps: request, assess impact, decide approve or reject, implement, then review and close.

  • A change control board or delegated authority approves changes to baselined scope, cost, schedule or quality.

  • Configuration management identifies, controls, records and reports products and their versions.

  • Cost of quality includes prevention, appraisal and failure costs; prevention is generally cheaper than failure.

  • A change log records change requests, decisions, owners and status.