Quick reference

Strategic case

  • Five Case Model: strategic, economic, commercial, financial and management cases; the strategic case is prepared first and sets the case for change.

  • Strategic case contents: strategic context, case for change, investment objectives, business scope, benefits, risks, constraints, dependencies and stakeholder views.

  • Decision rule: if the proposal lacks strategic fit or a compelling case for change, it stops before economic appraisal.

  • Investment objectives should be SMART and each objective should trace to at least one benefit and one appraisal criterion.

  • Business scope records what is in and out of scope, including boundaries, interfaces, dependencies and excluded activities.

  • Strategic fit means alignment with organisational, departmental and government priorities and published strategies.

  • Benefits in the strategic case are outcome statements, not outputs, and are linked to objectives and measures.

  • Stakeholder analysis maps interest and influence; high-influence, high-interest parties require active engagement.

  • Constraints and dependencies are recorded in the strategic case and carried into delivery planning.

Quick reference

Economic case

  • The economic case selects the option offering best public value using Green Book appraisal methods.

  • Options process: long list, short list, preferred option; the short list includes a do-minimum baseline.

  • Do minimum keeps current arrangements with essential maintenance only; it is the comparator, not a do-nothing option.

  • NPV = Σ (benefits − costs) / (1 + r)^t over the appraisal period.

  • BCR = present value of benefits ÷ present value of costs; BCR above 1 means benefits exceed costs.

  • Green Book social discount rate is 3.5% for years 0–30, then declines in later periods.

  • Optimism bias uplifts are applied to capital costs and schedules, with evidence-based values by project type.

  • Sensitivity analysis varies costs, benefits and timing; switching values identify where the preferred option changes.

  • Non-monetised benefits and risks are recorded alongside monetised results and weighed in the option decision.

Quick reference

Commercial case

  • The commercial case demonstrates a viable deal: route to market, supplier capability, risk allocation, contract terms and payment.

  • Procurement routes include open competition, restricted procedure, framework agreement and negotiated procedure; choice depends on value, market and urgency.

  • Risk is allocated to the party best able to manage it; retained risks remain in the economic appraisal.

  • Payment mechanisms link payment to outputs or service performance and include deductions, incentives and measurement rules.

  • Market sounding tests supplier capacity, appetite, likely costs and innovation before the route is fixed.

  • Contract management arrangements must be defined before award: performance measures, governance, variations and dispute resolution.

  • Single-source procurement requires a documented justification where competition is absent or impractical.

  • Deal structure covers contract length, pricing basis, risk transfer, termination rights and change provisions.

Quick reference

Financial case

  • The financial case tests affordability: whole-life costs must fit approved budgets and confirmed funding.

  • Funding gap = total required funding − confirmed available funding; a positive gap means unaffordable as described.

  • Whole-life cost includes capital, operating, maintenance, replacement and disposal costs over the asset or service life.

  • Cash flow profile checks funding availability in each year; timing mismatches are affordability risks.

  • Accounting treatment determines capital or revenue classification, asset recognition and liability recognition.

  • Affordability is separate from economic value: an option may have a positive NPV but be unaffordable.

  • The financial case reconciles costs and funding to budget holders and accounting statements, including inflation assumptions.

  • Both capital and revenue budgets are tested; revenue consequences of capital investment must be funded.

Quick reference

Management case

  • The management case sets out delivery, governance, assurance, risk management, change control and benefits realisation.

  • Governance roles: the Senior Responsible Owner is accountable; the project board provides direction; the project manager delivers.

  • Assurance plan uses independent reviews, gate checks and audits at key decision points.

  • Delivery plan includes milestones, dependencies, resources, critical path and contingency.

  • Benefits realisation plan names each benefit, owner, baseline, measure and review point.

  • Change control assesses impacts on scope, cost, schedule and benefits before approval.

  • Risk management cycle: identify, assess, allocate, mitigate and monitor; the risk register is reviewed by the project board.

  • Post-implementation review compares actual outcomes, costs and benefits with the approved business case and records lessons.

  • Management case must evidence capability and capacity to deliver, including supplier and client resources.