AR Electrician study plan
AR Electrician · Give each week a clear focus.
8 weeks · About 7 hours per week
Wiring Methods and Materials & Conductors, Boxes, Raceways, and Cable Systems
Classify at least 12 common wiring methods (NM-B, AC, MC, EMT, IMC, RMC, PVC, LFMC, LFNC, ENT, etc.) by permitted use, wet/damp/dry location, and corrosion resistance.
Calculate required support and securement spacing for each wiring method from memory, then verify against the code book and correct your errors.
Compute conductor ampacity with ambient-temperature correction and conduit-fill adjustment on 15 practice problems, showing each table lookup.
Size pull/junction boxes and device boxes for given conductor counts, including equipment grounding conductors and device fill allowances, across 10 scenarios.
Match cable and raceway types to structural conditions (concealed, exposed, underground, in concrete, in hazardous areas) on a 30-item sorting drill.
Your checkpoint
A one-page wiring-method comparison matrix (method / permitted locations / support spacing / conductor types allowed) plus a scored 40-question quiz at 80% or better.
Services, Feeders, and Branch Circuits & Electrical Theory, Principles, and General Knowledge
Trace a 200 A single-family service from the utility point of connection to the panelboard, labeling the code requirement that governs each component.
Size service-entrance conductors and the service disconnecting means for a 200 A dwelling, writing out every step of the calculation.
Differentiate branch-circuit requirements for small-appliance, laundry, bathroom, kitchen, garage, and outdoor receptacles, and state where GFCI and AFCI protection apply.
Solve 10 series, parallel, and combination circuit problems for voltage, current, resistance, and power, including voltage-drop checks on two long branch circuits.
Your checkpoint
A worked service-sizing sheet for one 200 A dwelling with article citations for each decision, plus a 20-problem circuit-math set scored with corrections.
Grounding and Bonding & Overcurrent Protection and Short-Circuit/Coordination Concepts
Identify each component of a grounding electrode system and size the grounding electrode conductor for 8 given service sizes.
Distinguish grounding from bonding and correctly size main bonding jumpers and supply-side bonding jumpers in 6 written scenarios.
Select overcurrent devices and verify conductor protection for 6 branch-circuit and feeder scenarios, including tap rules and next-size-up allowances.
Explain in writing how series-rated systems, interrupting rating, and selective coordination affect device selection.
Locate and bond metal water piping, gas piping, structural steel, and intersystem bonding termination in a described building.
Your checkpoint
A grounding-and-bonding sizing worksheet covering 8 scenarios with conductor sizes shown, plus a 35-question mixed quiz at 80% or better.
Load Calculations and Demand Factors & Electrical Theory, Principles, and General Knowledge
Perform a complete standard-method dwelling load calculation for a 2,400 sq ft house covering general lighting, small-appliance and laundry circuits, appliances, range, dryer, and heating versus cooling.
Apply demand factors to appliance, range, dryer, and neutral calculations and justify each factor used.
Repeat the same dwelling using the optional method and reconcile the difference between the two results.
Re-study the theory topics you missed on earlier quizzes (Ohm's law, power factor, AC impedance, three-phase relationships) until you can solve them without notes.
Your checkpoint
A finished dwelling load-calculation worksheet showing both standard and optional methods side by side, plus a 30-question quiz at 80% or better.
Motors, Motor Controls, and HVAC Equipment & Overcurrent Protection and Short-Circuit/Coordination Concepts
Size branch-circuit conductors, short-circuit and ground-fault protection, overload protection, and disconnects for 10 motor circuits using nameplate and table data.
Determine controller and disconnecting-means requirements, including location, ampere rating, and allowable exceptions, for each of those 10 circuits.
Apply HVAC-specific rules for hermetic refrigerant motor-compressors, using nameplate values versus table values and selecting the correct protection type.
Interpret three motor control diagrams (start/stop with overloads, reversing, and hand-off-auto) and describe the function of each component.
Verify conductor and overcurrent coordination between a motor branch circuit, its feeder, and the supplying panel.
Your checkpoint
A motor-circuit sizing packet for 10 motors with all conductor, disconnect, and protection sizes shown, plus a redrawn start/stop ladder diagram produced from a blank page.
Special Occupancies, Special Locations, and Special Equipment & Electrical Safety, Code Administration, and Inspection Requirements
Classify hazardous locations by class, division, and zone, and match the permitted wiring methods and equipment markings to each classification.
List the key wiring and equipment requirements for at least five special occupancies or locations (health care facilities, assembly occupancies, mobile/manufactured homes, swimming pools and fountains, agricultural buildings).
Sequence an inspection from permit application through rough-in to final, stating what the inspector verifies at each stage and what triggers a correction notice.
Describe lockout/tagout procedure, approach boundaries, arc-flash PPE categories, and safe work practices for energized versus de-energized work.
Your checkpoint
Two one-page job aids: a hazardous-location wiring matrix and an inspection/safety checklist, plus a 30-question quiz at 80% or better.
Wiring Methods and Materials & Services, Feeders, and Branch Circuits
Re-take every quiz from weeks 1 through 6 and log each miss by domain and by code article.
Rebuild your ten weakest concepts by re-deriving the governing rule from the code book without looking at the answer key first.
Complete a timed 60-question set drawn mostly from domains 2, 3, 6, and 5, finishing within 90 minutes.
Drill table lookups under time pressure until ampacity, conductor sizing, and box-fill lookups take under two minutes each.
Your checkpoint
An error-analysis sheet mapping every missed item to a code article and a one-sentence corrected rule statement.
Electrical Theory, Principles, and General Knowledge & Electrical Safety, Code Administration, and Inspection Requirements
Complete two full-length timed practice exams under exam-day conditions, including a single sitting with no interruptions.
Review every missed or guessed item from both exams and re-solve each one until you can justify the correct answer.
Compress the highest-value numbers, tables, and exceptions into a single page you can recall from memory.
Confirm exam-day logistics: location or platform, identification required, allowed references, calculator policy, and arrival time.
Your checkpoint
Two timed full-length exam scores of 80% or better, each accompanied by a completed review log.
Milestones
Week 2: Score 80% or better on a 25-question quiz covering domains 2 and 6, and correctly size service conductors for a 200 A dwelling without reference help.
Week 4: Score 80% or better on a 40-question mixed quiz spanning domains 1 through 7, with a written error log for every missed item.
Week 6: Score 80% or better on a 40-question mixed quiz spanning domains 8, 9, and 10, and produce both job aids from memory before checking them.
Week 8: Two consecutive full-length timed practice exams completed with scores of 80% or better and all misses reviewed and re-solved.