33 cards. Read the term and the definition here. The deck at the top of this page is optional.

Project
A temporary endeavor undertaken to create a unique product, service, or result, with a defined start and end and constrained by scope, schedule, and cost.
Program
A group of related projects and activities managed in a coordinated way to obtain benefits not available from managing them individually.
Triple Constraint
The interdependent balance among scope, schedule, and cost; changing one typically affects the others, with quality and risk as related considerations.
PMO
A project management office that standardizes project practices and may be supportive, controlling, or directive in its authority over projects.
WBS
A hierarchical decomposition of the total scope of work into deliverables and work packages, governed by the 100% rule.
Work Package
The lowest level of the WBS, sized so it can be estimated, scheduled, assigned, and controlled; it is not further decomposed.
Scope Baseline
The approved combination of the project scope statement, the WBS, and the WBS dictionary, used as the reference for scope control.
Scope Creep
Uncontrolled expansion of project scope without approved change control, often adding work without corresponding time, cost, or resources.
Requirements Traceability Matrix
A grid linking each requirement to its source and to design and test artifacts, verifying that all requirements are covered and validated.
Validate Scope
The process of formalizing acceptance of completed deliverables by the customer or sponsor, distinct from verifying correctness through quality control.
Critical Path
The longest-duration path through the project network, which determines the shortest possible project duration and has zero total float.
Total Float
The amount of time an activity can be delayed from its early start without delaying the project finish date; calculated as LS minus ES.
Fast Tracking
A schedule compression technique that overlaps activities normally performed sequentially, increasing risk and potential rework.
Crashing
A schedule compression technique that adds resources to critical-path activities to shorten duration, usually increasing cost.
Resource Leveling
Adjusting start and finish dates to resolve resource overallocation or shortages, which may extend the project schedule beyond the critical path.
Milestone
A significant point or event in the project with zero duration, used to mark progress or a decision gate.
Cost Baseline
The approved, time-phased project budget excluding management reserve, against which cost performance is measured.
Earned Value
The budgeted cost of work actually performed, used with planned value and actual cost to measure cost and schedule performance.
Cost Performance Index
CPI equals earned value divided by actual cost; a value above 1.0 indicates the project is under budget.
Estimate at Completion
A forecast of total project cost, often computed as BAC divided by CPI when current cost performance is expected to continue.
Contingency Reserve
A budget allocated for identified risks and accepted residual risk, included in the cost baseline; management reserve covers unknown-unknowns.
Expected Monetary Value
The product of a risk's probability and its monetary impact, used to quantify risk exposure and size contingency reserves.
Risk Register
A document recording identified risks with their probability, impact, score, owner, planned response, and current status.
Risk Transfer
A threat response that shifts the impact and ownership of a risk to a third party, such as through insurance or a fixed-price contract.
Secondary Risk
A new risk that arises as a direct result of implementing a risk response action.
Communication Channels
The number of possible communication paths among stakeholders, calculated as n times n minus 1, divided by 2.
Power-Interest Grid
A stakeholder analysis tool that classifies stakeholders by authority and concern to determine how closely to manage their engagement.
Communications Management Plan
A plan specifying who receives which information, in what format, at what frequency, and through which channel.
Quality Assurance
The process of auditing quality requirements and results to ensure appropriate quality standards and processes are used.
Pareto Chart
A bar chart ordering causes by frequency, illustrating that a small number of causes produce most of the problems.
Control Chart
A graph of process data over time with control limits; points outside limits or nonrandom patterns signal an out-of-control process.
Conflict of Interest
A situation where personal or financial interests could improperly influence professional decisions, requiring disclosure and avoidance.
Governance
The framework of authority, decision rights, policies, and oversight that directs how projects are approved, monitored, and controlled.