High Risk Work Licence - Personnel and Materials Hoist (HP) study materials
High Risk Work Licence - Personnel and Materials Hoist (HP) study resources

High Risk Work Licence - Personnel and Materials Hoist (HP) case studies

High Risk Work Licence - Personnel and Materials Hoist (HP) · Put your knowledge to work in context.

This page supports candidates preparing for the High Risk Work Licence - Personnel and Materials Hoist (HP) assessment. The HP class covers the operation of hoists that lift people as well as materials on construction and industrial sites, so the assessment is built around safety-critical judgement rather than simple control familiarisation. Candidates are typically experienced plant operators, doggers, riggers or site supervisors who need the formal licence to work legally, plus employers and trainers who want a structured revision path. The examinable content is organised into six areas: planning and preparing work; routine pre-operational checks and maintenance; setting up, erecting and positioning the hoist; operating the hoist; shutting down, securing and storing it; and applying safety, hazard control and emergency procedures. The High Risk Work Licence - Personnel and Materials Hoist (HP) case studies are 5 cases and about 3,969 words.

1

Base Position on a Suspended Slab

A builder's hoist is to be installed at a six-level apartment project. The only position that keeps the landing gates within 900 mm of the floor slabs is on the suspended ground slab over the basement car park.

669 words, about 3 min
2

Return to Service After a Wet-Season Shutdown

The crew returns after a six-week wet-season shutdown. The hoist has stood at its full 24 m height, uncovered, with the cage parked at the bottom landing.

908 words, about 5 min
3

Erecting a 30 m Mast Beside an 11 kV Line

A 30 m hoist must be erected on a tight CBD site. The practical position puts the mast 3.2 m from a live 11 kV overhead line along the boundary and 2.5 m from the neighbouring building's windows.

805 words, about 4 min
4

Wind, Load and Fatigue on a Live Lift

A combined personnel/materials hoist rated 1000 kg or 12 persons serves a nine-level project. At 10:00 the wind is 14 m/s gusting 21 m/s; the manual's operating limit is 20 m/s.

753 words, about 4 min
5

Power Failure with Two Workers Aloft

At 16:40 the hoist loses power with two workers in the cage at level 6, about 18 m up and between landings. The site generator is not connected to the hoist.

834 words, about 4 min