BPC/VBA Building Design (Draftsperson) Exam flashcards
BPC/VBA Building Design (Draftsperson) Exam · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Occupant load calculation
- Divide floor area by the occupant load factor for the use (e.g., 9.3 m²/person for offices). This determines egress width, exits, and sanitary fixture counts.
- Travel distance limit
- Maximum distance from the most remote point to an exit, measured along the path of travel. Typically 60 m in sprinklered buildings, 45 m unsprinklered; confirm local code.
- Remote exit separation
- The distance between two required exits must be at least half the diagonal of the floor area, or a minimum specified distance, to prevent both being blocked by one fire.
- Accessible ramp slope
- Maximum gradient 1:12 (8.33%). Provide landings at top, bottom, and every 9 m of run; handrails on both sides at 865–965 mm above finished floor.
- Allowable building area
- Base area from code table multiplied by occupancy factor, sprinkler increase (up to 200% if fully sprinklered), and frontage increase. Height limits checked separately.
- Drawing line weights
- Cut elements 0.7–1.0 mm, visible edges 0.35–0.5 mm, hidden lines 0.25 mm, grid lines 0.18 mm. Hierarchy improves readability and distinguishes depth.
- Scale notation
- 1:100 means 1 mm on paper represents 100 mm in reality. Always use written dimensions; never scale from drawings because of reproduction distortion.
- Sheet numbering convention
- Discipline prefix plus two-digit sequence (A-101 architectural, S-201 structural). Revisions clouded with delta symbol and revision number; title block on right edge.
- Door schedule content
- Lists door tag, size, type, fire rating, hardware set, glazing, and frame material. Cross-referenced to plan tags and detail sheets for complete specification.
- Concrete cover requirements
- Minimum cover: 20 mm slabs, 40 mm beams/columns exposed to weather, 50 mm cast against earth. Protects reinforcement from corrosion and fire.
- Brick masonry quantities
- Standard brick 215×102.5×65 mm with 10 mm mortar joint. Approximately 60 bricks per square metre of single-leaf wall; add 5% waste.
- Roof pitch minimums
- Sheet metal 1:80, concrete tiles 1:60, asphalt shingles 1:12. Underlayment lapped 100 mm horizontally, 150 mm vertically to shed water.
- Thermal transmittance U-value
- U = 1/R, where R is thermal resistance. Lower U means better insulation. Typical targets: wall ≤ 0.35 W/m²K, roof ≤ 0.25 W/m²K in temperate climates.
- Waterproofing upturn heights
- Membrane turned up 150 mm at walls, 300 mm at shower recesses. Fall 1:80 to drains. Flood test for 24 hours before covering.
- Beam depth rule of thumb
- Simply supported steel beam depth ≈ span/20; concrete ≈ span/12. Verify deflection limits L/360 for floors, L/240 for roofs.
- Service void coordination
- Allocate ceiling void ≥ 400 mm for ducts, 150 mm sprinkler, 100 mm electrical. Resolve clashes before tender; no structural cutting without engineer approval.
- Sprinkler head spacing
- Maximum 4.6 m between heads and 2.3 m from walls for light hazard. Maintain 150 mm clearance below ceiling; pipe slope 1:500 to drain.
- Fire stopping penetrations
- Seal all service penetrations through fire-rated walls and floors with tested systems. Integrity rating must equal the element penetrated.
- Site coverage and plot ratio
- Site coverage = footprint ÷ site area × 100%. Plot ratio = gross floor area ÷ site area. Both limited by zoning; typical coverage 40–60% residential.
- Building setbacks
- Minimum distances from property boundary to building line: front 3–6 m, side 1.5–3 m, rear 3 m typical residential. Confirm local planning scheme.
- Solar orientation principle
- Long axis east–west maximises north/south daylight. North glazing gives consistent light; south needs shading to control summer heat gain.
- Stormwater detention
- Impervious surfaces increase runoff. Provide detention volume equal to post-development minus pre-development runoff for the design storm; size soakaway by infiltration rate.
- Accessible parking bay
- Minimum 3.7 m wide, or 2.4 m bay plus 1.2 m shared aisle. Gradient ≤ 1:50; accessible route to entrance with slope ≤ 1:20.
- Measurement rules for openings
- Under NRM2/SMM7, no deduction for openings less than 0.5 m² in walls. Measure net dimensions in m, m², m³, nr, kg.
- Quantity takeoff waste allowance
- Add 5–10% to net quantities for cutting and breakage. Concrete volume = plan area × thickness; formwork measured as contact area.
- Retention in construction contracts
- Typically 5% of each interim payment held. Half released at practical completion, remainder after defects liability period (often 12 months).
- Critical path float
- Float = late start − early start. Critical activities have zero float; any delay extends the programme. Monitor milestones at design freeze, tender, completion.
- Variation order pricing
- Documented instruction to change scope. Priced using BOQ rates where applicable, otherwise fair valuation. Time impact assessed separately.
- Professional duty of care
- Exercise reasonable skill and care of a competent professional. Document advice in writing; avoid conflicts of interest; maintain confidentiality.
- Drawing copyright
- Drawings remain the author's intellectual property. Client receives licence for the specific project; reuse for other projects requires permission.
- RFI protocol
- Request for Information: numbered, dated, with response deadline. Minutes issued within 5 working days; decisions recorded to avoid disputes.
- Professional indemnity insurance
- Cover for negligence claims. Maintain for statutory period (6–12 years); disclose claims history; cooperate with insurer in defence.