AWS D1.1 Endorsement flashcards
AWS D1.1 Endorsement · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- D1.1 thickness scope
- D1.1 applies to welded steel structures with base metal thickness of 1/8 in [3 mm] and greater, unless the contract specifies another code or thickness limit.
- Prequalified joint detail
- A joint detail listed in D1.1 Clause 3 that may be used without WPS qualification when all prequalified conditions for base metal, filler, position, preheat, and access are met.
- Minimum fillet weld size
- Based on thicker part: 1/8 in for ≤1/4 in, 3/16 in for >1/4 to 1/2 in, 1/4 in for >1/2 to 3/4 in, and 5/16 in for >3/4 in.
- Maximum fillet size on edge
- For edge fillets, maximum size equals material thickness when thickness is less than 1/4 in; for 1/4 in and thicker, it equals thickness minus 1/16 in.
- Effective fillet throat
- The effective throat of an equal-leg 45-degree fillet weld is 0.707 times the leg size; effective area is throat times effective length.
- Minimum fillet weld length
- A fillet weld shorter than four times its nominal size has effective size limited to one-quarter of its length; intermittent welds also have minimum length rules.
- Base metal Table 1.1
- D1.1 base metals are grouped in Table 1.1 by ASTM specification and grade; unlisted steels require engineer approval and may require WPS qualification.
- CJP groove effective throat
- For a complete joint penetration groove weld, the effective throat is the full thickness of the thinner joined part, provided backing or backgouging removes unsound root material.
- Prequalified WPS conditions
- A WPS may be prequalified only when it follows a prequalified joint detail and uses listed base metal, prequalified filler, qualified position, and D1.1 preheat and interpass limits.
- PQR
- A Procedure Qualification Record documents the WPS qualification test: materials, essential variables, test specimens, and results demonstrating the procedure produces sound welds meeting Clause 4.
- Essential variable
- A WPS variable that, when changed beyond the code-permitted range, requires requalification; examples include process, filler classification, base metal group, thickness range, and preheat.
- WPS qualification tests
- Groove weld procedure qualification typically uses reduced-section tension and guided-bend specimens; acceptance requires specified strength and no unacceptable defects in bends.
- Welder performance qualification
- A welder is qualified by visual examination and bend testing, or radiography, of a test coupon; the qualification records position, process, thickness, and backing conditions.
- Preheat requirement
- Minimum preheat depends on steel group, thickness, and process; it must be measured and maintained before and during welding, and interpass temperature must not exceed the code limit.
- Low-hydrogen electrode storage
- Low-hydrogen electrodes must be stored and handled to prevent moisture pickup; opened electrodes are limited in atmospheric exposure and damp electrodes must not be used.
- Fit-up misalignment
- Joint misalignment and fit-up must be within D1.1 tolerances; excessive offset shall be corrected before welding, and strongbacks or temporary welds must follow qualified procedures.
- Workmanship acceptance
- Welds must be free of cracks and unacceptable undercut, porosity, slag, and arc strikes; surfaces are cleaned before inspection, and repairs use a qualified WPS.
- Visual inspection extent
- All welds require visual inspection before, during, and after welding; the inspector checks joint preparation, fit-up, preheat, cleaning, and final weld appearance.
- CJP tension NDE
- Complete joint penetration groove welds in tension generally require ultrasonic or radiographic testing in addition to visual inspection, unless the contract grants a specific exemption.
- UT for CJP
- Ultrasonic testing detects internal planar defects in CJP groove welds; acceptance rejects cracks, incomplete fusion, and indications exceeding the D1.1 reference level.
- RT acceptance
- Radiographic acceptance prohibits cracks and incomplete fusion or penetration; porosity and slag limits depend on weld thickness and are tabulated in D1.1.
- MT/PT use
- Magnetic particle testing detects surface and near-surface defects in ferromagnetic steel; penetrant testing is used for nonmagnetic materials or where magnetic methods are unsuitable.
- Undercut limit
- D1.1 undercut acceptance depends on material thickness: generally 1/32 in is permitted for material under 1 in and 1/16 in for 1 in and thicker.
- NDE personnel qualification
- Nondestructive examination personnel shall be qualified to a recognized program such as ASNT SNT-TC-1A or an equivalent employer certification program acceptable under the contract.
- Repair inspection
- Defects shall be excavated and rewelded with a qualified WPS; repaired areas are reexamined by the same NDE method and accepted to the original criteria.
- NDE reports
- NDE reports identify the weld, method, procedure, equipment calibration, personnel, indications, and acceptance decision; they are reviewed by the inspector before final acceptance.
- Inspector authority
- The inspector verifies code compliance and may reject nonconforming work, but does not approve design changes or waive D1.1 requirements without the engineer's written authorization.
- WPS availability
- A written WPS and supporting PQR must be available to the inspector at the work site before welding; prequalified WPS still require documentation of compliance.
- Welder qualification record
- The record identifies the welder, process, position, thickness qualified, test date, and results; it is maintained by the contractor and available to the inspector.
- Material traceability
- Mill certificates, heat numbers, and filler metal classifications are checked against the contract and WPS; unidentified or unlisted materials are not accepted for code welding.
- Nonconformance report
- A nonconformance report describes the noncompliant condition, location, code requirement, disposition, repair or retest, and closure verification; it becomes part of the inspection record.
- Final inspection report
- The final report summarizes inspections, NDE results, nonconformances, repairs, and acceptance status, and is signed by the inspector before project closeout.