The Ten-Day Notice That Arrives Too Late

AZ Asbestos Abatement · Put your knowledge to work in context.

All case studies

The Ten-Day Notice That Arrives Too Late

An abatement contractor is scheduled to begin removing 3,200 sq ft of acoustical ceiling tile and 600 linear feet of pipe insulation in a commercial office building on Monday, March 3. The building is not a demolition; it is a renovation. The contractor mails the notification on Thursday, February 27, by first-class mail. The agency receives it on Monday, March 3, the same day work begins. The contractor also discovers on Friday, February 28, that the start date must move to March 10 because the building's elevator will not be available. The contractor's office manager says the mailed notice is sufficient because it was postmarked before the start date, and that the date change does not require anything because the work is still within the same month.

1. Determine whether the notification was timely and what the contractor must do about the start-date change.

Read the worked answer

The notification was not timely. NESHAP requires the owner or operator to provide written notice to the agency at least 10 working days before the start of the renovation. The notice must be received, not merely mailed, within that period. Mailing on Thursday, February 27, with receipt on Monday, March 3, gives zero working days of lead time. The ten-working-day clock runs backward from the start date, excluding weekends and federal holidays, so a March 3 start would require receipt no later than roughly February 14, depending on the holidays in the period. The office manager's 'postmarked before the start date' theory is wrong.

Because the notice was late, the contractor must not begin work on March 3. The contractor should immediately contact the agency, explain the late notice, and either delay the start until the notice is timely or obtain the agency's direction. Starting work on a late notice is a violation regardless of whether the agency received the form.

The date change to March 10 is a separate issue. A change in the start date is a significant change that must be reported to the agency. The contractor should submit an updated notice reflecting the new start date as soon as the change is known, and should confirm receipt. The office manager's 'same month' reasoning has no basis in the rule; the requirement is tied to the start date, not the calendar month.

2. Identify the information the notification must contain and explain why each item matters for this project.

Read the worked answer

The notification must identify the owner or operator and the facility, including the name, address, and contact information, and the type of operation (renovation or demolition). It must state the start and completion dates, the amount of asbestos-containing material to be removed, and whether the material is friable or nonfriable. It must identify the contractor and the accredited supervisor, and describe the work practices and waste disposal arrangements, including the waste shipment record and the disposal site.

For this project, the amount matters because 3,200 sq ft of ceiling tile and 600 linear feet of pipe insulation are both above the thresholds, so the project is a regulated renovation. The friability matters because the pipe insulation is likely friable and the ceiling tile may be nonfriable, which affects work practices and handling. The start and completion dates matter because the ten-working-day rule is measured from the start date and the agency uses the completion date to schedule inspections. The contractor and supervisor matter because the agency checks accreditation. The waste disposal information matters because the agency tracks the waste shipment records and the disposal site must be authorized to accept asbestos waste.

An incomplete notice is a common enforcement finding. The contractor should keep a copy of the notice and proof of receipt in the project file.