AZ Asbestos Abatement flashcards
AZ Asbestos Abatement · Build recall with a focused review session.
33 cards. Read the term and the definition here. The deck at the top of this page is optional.
- RACM definition
- Regulated asbestos-containing material includes friable asbestos, Category I nonfriable that became friable or was sanded, ground, cut, or abraded, and Category II nonfriable likely to crumble under expected forces.
- NESHAP asbestos citation
- The federal asbestos NESHAP is 40 CFR Part 61, Subpart M, which sets work practice standards for demolition and renovation of facilities containing regulated asbestos-containing material.
- Renovation threshold
- A renovation is regulated when at least 160 square feet of facility components, 260 linear feet of pipes, or 35 cubic feet of material will be disturbed.
- Category I nonfriable
- Category I nonfriable ACM includes packings, gaskets, resilient floor covering, and asphalt roofing products; it becomes regulated when friable or when sanded, ground, cut, or abraded.
- Category II nonfriable
- Category II nonfriable ACM is any nonfriable asbestos material other than Category I, such as asbestos cement products, and is regulated when likely to be crumbled or pulverized.
- Demolition notification trigger
- Demolition of a public or commercial facility is regulated regardless of asbestos quantity; residential buildings with four or fewer dwelling units are generally exempt unless part of a larger regulated project.
- Pre-work inspection duty
- The owner or operator must inspect for asbestos, by sampling and analysis or documented assumption, before any renovation or demolition begins and must keep the record available.
- Order of work rule
- All RACM must be removed before any activity that would disturb it, and before demolition of the structure, except where removal is impossible or would create a greater hazard.
- AHERA accreditation disciplines
- AHERA recognizes five disciplines: inspector, management planner, project designer, contractor/supervisor, and worker; each requires a training course, an exam, and periodic refresher training.
- Refresher training interval
- Accredited asbestos professionals, including inspectors, management planners, project designers, contractor/supervisors, and workers, must complete refresher training annually to maintain accreditation.
- Inspector role
- An accredited inspector locates and samples suspect material, documents homogeneous areas, and records the condition and quantity of asbestos-containing material found in a building.
- Management planner role
- An accredited management planner interprets inspection findings, assesses hazards, and develops response actions and an asbestos management plan for a school building.
- Bulk sampling minimums
- Sampling typically requires at least three samples per homogeneous area of surfacing material or thermal system insulation and at least two per miscellaneous material.
- NVLAP laboratory analysis
- Bulk samples are analyzed by an accredited laboratory, commonly using polarized light microscopy, and the report states the asbestos percentage and fiber type detected.
- Presumed asbestos material
- Thermal system insulation and surfacing material in older buildings are presumed to contain asbestos unless sampled and shown otherwise, and the presumption must be communicated to occupants and employees.
- On-site supervisor requirement
- An accredited contractor/supervisor must be present at the work site at all times while abatement is performed, and accreditation records must be available on site.
- Ten working day notice
- The owner or operator must submit written notification of renovation or demolition to the delegated agency at least 10 working days before work begins.
- Notification contents
- Notification states the owner/operator identity, facility location and description, estimated RACM quantity, scheduled start and completion dates, and the waste disposal site name and address.
- Twenty percent revision rule
- A revised notification is required if the start date changes or if the amount of RACM to be removed changes by more than 20 percent from the original estimate.
- Emergency renovation notice
- Emergency work caused by a sudden event may begin without the 10-working-day wait, but notification must be made as soon as possible and before the next working day.
- Ordered demolition
- A demolition ordered by a government agency because a structure is structurally unsound and in imminent danger of collapse requires notification as soon as possible rather than 10 working days ahead.
- Delegated program control
- Where a state or local agency has been delegated NESHAP authority, its rules govern and may be more stringent than the federal requirements, including notice timing and content.
- Disposal site in notice
- The notification must identify the permitted waste disposal site that will receive the asbestos waste, and a change of disposal site requires a revised notification.
- Notified work window
- Work may not begin before the notified start date and must finish by the notified completion date; changes to either date require a revised notification.
- Daily project log
- A daily log records dates and hours worked, areas abated, quantity of material removed, and waste generated, providing evidence that work stayed within the notified window.
- On-site document set
- Site records include the notification and amendments, inspection and sampling results, worker and supervisor accreditation certificates, the work plan, daily logs, and waste shipment records.
- OSHA exposure limit
- OSHA 29 CFR 1926.1101 sets a permissible exposure limit of 0.1 fibers per cubic centimeter as an 8-hour time-weighted average for asbestos work.
- Duration reconciliation
- Waste shipment dates, manifest numbers, and disposal receipts should show that all removed material left the site before the notified completion date.
- Record availability
- Notification, inspection, and waste records must be kept and made available to the EPA Administrator on request, and delegated states may require longer retention.
- Waste packaging rule
- Asbestos waste must be wetted, sealed in leak-tight bags or wrapped containers, labeled with the required warning, and kept sealed until it reaches the permitted disposal site.
- Manifest copies
- The generator, transporter, and disposal site each retain a manifest copy; the disposal site returns a signed copy to the generator as proof of receipt.
- Missing receipt follow-up
- If a signed disposal receipt is not returned within the interval set by the delegated program, the generator must investigate the discrepancy and document the follow-up.
- Quantity reconciliation
- Shipped waste quantities on manifests should be compared with the RACM amount estimated in the notification; unexplained differences are a common inspection finding.